Bilaspur Smart City to set up 6.3 MW solar power projects
POWER & RENEWABLE ENERGY

Bilaspur Smart City to set up 6.3 MW solar power projects

Bilaspur Smart City Limited (BSCL) has floated a tender for setting up 6.3 MW of grid-connected solar power projects at Smriti Van, Domuhani, and Guru Ameri in Chhattisgarh.

For the 2.3 MW, Domuhani ground-mounted solar project, the interested bidders would have to pay Rs 1.2 million as an earnest money deposit.

March 26, 2022, is the last date to submit the bids, and on March 28, bids would be opened.

The successful bidder would be responsible to operate and maintain the activities of the project for 25 years.

The estimated tender cost is Rs 126.5 million. The successful bidder would have to provide an amount equal to 10% of the bid value as a performance bank guarantee.

The project should be finished within 11 months from the work order issuance.

To participate in the bidding procedure, the bidder should have implemented a single grid-connected solar power project, ground-mounted solar power project, or rooftop solar system of overall capacity not less than 1.5 MW in the previous three years.

Alternatively, the bidder must have implemented ground-mounted solar power projects, rooftop solar projects, or two grid-connected solar power projects of a capacity of 1 MW each, not less than that.

The average annual turnover of the bidder in the previous three financial years (FY) must be at least 60 million, and they should also have a favourable net worth on the last day of the last FY.

BSCL would sign a power purchase agreement (PPA) with the Chhattisgarh State Power Distribution Company Limited (CSPDCL) for 25 years.

For the Smriti Van 2 MW solar project, BSCL invited bids for the engineering, design, installation, supply, testing, commissioning, operation and maintenance project.

To participate in the bidding process, the bidder must submit an amount equal to Rs 1.1 million as an earnest money deposit.The last date to submit the bids is March 26, 2022, and bids would be opened on March 28. The tender's estimated cost is Rs 110 million.

The successful bidder would have to provide an amount equal to 10% of the bid value as a performance bank guarantee.The project should be completed in 11 months from the date of the allotment of the work order.

The average annual turnover of the bidder must be Rs 55 million in the last three FYs.The CSPDCL would sign a PPA for 25 years with BSCL to procure power.

In another tender, BSCL also invited bids to set up a 2 MW solar project at Ghuru Ameri. The successful bidder would be responsible for the maintenance and operation activities of the project for 25 years.

The last date to submit the bids is March 26, 2022, and the bids would be opened on March 28.The estimated expense of the tender is Rs 110 million, and interested bidders must submit an amount equal to Rs 1.1 million as an earnest money deposit.

The successful bidder should provide 10% of the bid value as a performance bank guarantee, and the project should be completed within 11 months from the date of the issuance of the work order.

The average annual turnover of the bidder for the previous three FY must be Rs 755 million.The bidder also must have a favourable net worth on the last day of the last FY.

Image Source

Also read: Punjab floats tender for 217 MW solar projects under PM-KUSUM

Bilaspur Smart City Limited (BSCL) has floated a tender for setting up 6.3 MW of grid-connected solar power projects at Smriti Van, Domuhani, and Guru Ameri in Chhattisgarh. For the 2.3 MW, Domuhani ground-mounted solar project, the interested bidders would have to pay Rs 1.2 million as an earnest money deposit. March 26, 2022, is the last date to submit the bids, and on March 28, bids would be opened. The successful bidder would be responsible to operate and maintain the activities of the project for 25 years. The estimated tender cost is Rs 126.5 million. The successful bidder would have to provide an amount equal to 10% of the bid value as a performance bank guarantee. The project should be finished within 11 months from the work order issuance. To participate in the bidding procedure, the bidder should have implemented a single grid-connected solar power project, ground-mounted solar power project, or rooftop solar system of overall capacity not less than 1.5 MW in the previous three years. Alternatively, the bidder must have implemented ground-mounted solar power projects, rooftop solar projects, or two grid-connected solar power projects of a capacity of 1 MW each, not less than that. The average annual turnover of the bidder in the previous three financial years (FY) must be at least 60 million, and they should also have a favourable net worth on the last day of the last FY. BSCL would sign a power purchase agreement (PPA) with the Chhattisgarh State Power Distribution Company Limited (CSPDCL) for 25 years. For the Smriti Van 2 MW solar project, BSCL invited bids for the engineering, design, installation, supply, testing, commissioning, operation and maintenance project. To participate in the bidding process, the bidder must submit an amount equal to Rs 1.1 million as an earnest money deposit.The last date to submit the bids is March 26, 2022, and bids would be opened on March 28. The tender's estimated cost is Rs 110 million. The successful bidder would have to provide an amount equal to 10% of the bid value as a performance bank guarantee.The project should be completed in 11 months from the date of the allotment of the work order. The average annual turnover of the bidder must be Rs 55 million in the last three FYs.The CSPDCL would sign a PPA for 25 years with BSCL to procure power. In another tender, BSCL also invited bids to set up a 2 MW solar project at Ghuru Ameri. The successful bidder would be responsible for the maintenance and operation activities of the project for 25 years. The last date to submit the bids is March 26, 2022, and the bids would be opened on March 28.The estimated expense of the tender is Rs 110 million, and interested bidders must submit an amount equal to Rs 1.1 million as an earnest money deposit. The successful bidder should provide 10% of the bid value as a performance bank guarantee, and the project should be completed within 11 months from the date of the issuance of the work order. The average annual turnover of the bidder for the previous three FY must be Rs 755 million.The bidder also must have a favourable net worth on the last day of the last FY. Image Source Also read: Punjab floats tender for 217 MW solar projects under PM-KUSUM

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code