CERC Clears Rs 5.89 Billion Tariff for Adani-Led Grid Project
POWER & RENEWABLE ENERGY

CERC Clears Rs 5.89 Billion Tariff for Adani-Led Grid Project

The Central Electricity Regulatory Commission (CERC) has approved annual transmission charges of Rs 5.89 billion for the Pune-III Transmission Limited project, part of efforts to evacuate 7 GW of renewable power from Gujarat’s Khavda region under Phase IV, Part D. The project will be implemented on a Build, Own, Operate, and Transfer (BOOT) basis and was originally floated by PFC Consulting Limited (PFCCL), later awarded to Adani Energy Solutions Limited through tariff-based competitive bidding.
The process commenced with the publication of the Request for Proposal on 19 October 2023, followed by bid submissions on 19 April 2024. Financial bids were opened on 25 September 2024, and an intense e-reverse auction, lasting 178 rounds, concluded on 28 September 2024. The final discovered tariff, quoted by Adani Energy Solutions, exceeded CERC's earlier levelised tariff estimate of Rs 4.56 billion by 11.24 per cent. The rise was attributed to revised Right of Way (RoW) compensation norms, changes in land values, and a recalculated completion factor for project cost escalation. The Cost Committee subsequently revised the project cost from Rs 33.81 billion to Rs 40.21 billion.
Despite the higher bid, the Bid Evaluation Committee and the CERC deemed the process transparent, competitive, and consistent with the Ministry of Power’s guidelines. A Letter of Intent was issued to Adani Energy on 21 October 2024, and the company acquired Pune-III Transmission on 19 November 2024 after furnishing a Rs 700 million performance guarantee. The Commission has now adopted the Rs 5.89 billion per annum tariff for the duration of the Transmission Service Agreement.
CERC also instructed PFCCL to improve clarity in committee documentation for future tenders. The transmission charges will be shared by designated interstate transmission customers, as outlined in the 2020 CERC regulations. This order marks the formal closure of Petition No. 75/AT/2025 and sets the stage for one of India’s largest renewable power evacuation systems to move forward. 

The Central Electricity Regulatory Commission (CERC) has approved annual transmission charges of Rs 5.89 billion for the Pune-III Transmission Limited project, part of efforts to evacuate 7 GW of renewable power from Gujarat’s Khavda region under Phase IV, Part D. The project will be implemented on a Build, Own, Operate, and Transfer (BOOT) basis and was originally floated by PFC Consulting Limited (PFCCL), later awarded to Adani Energy Solutions Limited through tariff-based competitive bidding.The process commenced with the publication of the Request for Proposal on 19 October 2023, followed by bid submissions on 19 April 2024. Financial bids were opened on 25 September 2024, and an intense e-reverse auction, lasting 178 rounds, concluded on 28 September 2024. The final discovered tariff, quoted by Adani Energy Solutions, exceeded CERC's earlier levelised tariff estimate of Rs 4.56 billion by 11.24 per cent. The rise was attributed to revised Right of Way (RoW) compensation norms, changes in land values, and a recalculated completion factor for project cost escalation. The Cost Committee subsequently revised the project cost from Rs 33.81 billion to Rs 40.21 billion.Despite the higher bid, the Bid Evaluation Committee and the CERC deemed the process transparent, competitive, and consistent with the Ministry of Power’s guidelines. A Letter of Intent was issued to Adani Energy on 21 October 2024, and the company acquired Pune-III Transmission on 19 November 2024 after furnishing a Rs 700 million performance guarantee. The Commission has now adopted the Rs 5.89 billion per annum tariff for the duration of the Transmission Service Agreement.CERC also instructed PFCCL to improve clarity in committee documentation for future tenders. The transmission charges will be shared by designated interstate transmission customers, as outlined in the 2020 CERC regulations. This order marks the formal closure of Petition No. 75/AT/2025 and sets the stage for one of India’s largest renewable power evacuation systems to move forward. 

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->