+
CERC Clears Rs 5.89 Billion Tariff for Adani-Led Grid Project
POWER & RENEWABLE ENERGY

CERC Clears Rs 5.89 Billion Tariff for Adani-Led Grid Project

The Central Electricity Regulatory Commission (CERC) has approved annual transmission charges of Rs 5.89 billion for the Pune-III Transmission Limited project, part of efforts to evacuate 7 GW of renewable power from Gujarat’s Khavda region under Phase IV, Part D. The project will be implemented on a Build, Own, Operate, and Transfer (BOOT) basis and was originally floated by PFC Consulting Limited (PFCCL), later awarded to Adani Energy Solutions Limited through tariff-based competitive bidding.
The process commenced with the publication of the Request for Proposal on 19 October 2023, followed by bid submissions on 19 April 2024. Financial bids were opened on 25 September 2024, and an intense e-reverse auction, lasting 178 rounds, concluded on 28 September 2024. The final discovered tariff, quoted by Adani Energy Solutions, exceeded CERC's earlier levelised tariff estimate of Rs 4.56 billion by 11.24 per cent. The rise was attributed to revised Right of Way (RoW) compensation norms, changes in land values, and a recalculated completion factor for project cost escalation. The Cost Committee subsequently revised the project cost from Rs 33.81 billion to Rs 40.21 billion.
Despite the higher bid, the Bid Evaluation Committee and the CERC deemed the process transparent, competitive, and consistent with the Ministry of Power’s guidelines. A Letter of Intent was issued to Adani Energy on 21 October 2024, and the company acquired Pune-III Transmission on 19 November 2024 after furnishing a Rs 700 million performance guarantee. The Commission has now adopted the Rs 5.89 billion per annum tariff for the duration of the Transmission Service Agreement.
CERC also instructed PFCCL to improve clarity in committee documentation for future tenders. The transmission charges will be shared by designated interstate transmission customers, as outlined in the 2020 CERC regulations. This order marks the formal closure of Petition No. 75/AT/2025 and sets the stage for one of India’s largest renewable power evacuation systems to move forward. 

Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

The Central Electricity Regulatory Commission (CERC) has approved annual transmission charges of Rs 5.89 billion for the Pune-III Transmission Limited project, part of efforts to evacuate 7 GW of renewable power from Gujarat’s Khavda region under Phase IV, Part D. The project will be implemented on a Build, Own, Operate, and Transfer (BOOT) basis and was originally floated by PFC Consulting Limited (PFCCL), later awarded to Adani Energy Solutions Limited through tariff-based competitive bidding.The process commenced with the publication of the Request for Proposal on 19 October 2023, followed by bid submissions on 19 April 2024. Financial bids were opened on 25 September 2024, and an intense e-reverse auction, lasting 178 rounds, concluded on 28 September 2024. The final discovered tariff, quoted by Adani Energy Solutions, exceeded CERC's earlier levelised tariff estimate of Rs 4.56 billion by 11.24 per cent. The rise was attributed to revised Right of Way (RoW) compensation norms, changes in land values, and a recalculated completion factor for project cost escalation. The Cost Committee subsequently revised the project cost from Rs 33.81 billion to Rs 40.21 billion.Despite the higher bid, the Bid Evaluation Committee and the CERC deemed the process transparent, competitive, and consistent with the Ministry of Power’s guidelines. A Letter of Intent was issued to Adani Energy on 21 October 2024, and the company acquired Pune-III Transmission on 19 November 2024 after furnishing a Rs 700 million performance guarantee. The Commission has now adopted the Rs 5.89 billion per annum tariff for the duration of the Transmission Service Agreement.CERC also instructed PFCCL to improve clarity in committee documentation for future tenders. The transmission charges will be shared by designated interstate transmission customers, as outlined in the 2020 CERC regulations. This order marks the formal closure of Petition No. 75/AT/2025 and sets the stage for one of India’s largest renewable power evacuation systems to move forward. 

Next Story
Infrastructure Transport

Rs 2.82 Billion Approved for NH-48 Flyovers, Footbridges

Gurugram’s section of National Highway 48 is set for a significant infrastructure upgrade, with the Central Government approving Rs 2.82 billion for the construction of four flyovers and nine foot overbridges along the Gurgaon–Kotputli–Jaipur corridor. This initiative aims to ease congestion, improve commuter safety, and boost regional connectivity, according to officials.The planned flyovers will be built at Panchgaon Chowk, Rathiwas, near the Hero Company, and Sahlawas. The nine foot overbridges will be constructed at Shikhopur, Manesar, Binola, Rathiwas, Malpura, Jaisinghpurkhera, Sid..

Next Story
Infrastructure Energy

VSL Wins Rs 810-Cr O&M Deal for 810 MWp NGEL Solar Assets

VSL Renewable Services has secured a Rs 810 crore operation and maintenance (O&M) contract for 810 MWp of NTPC Green Energy’s (NGEL) solar power projects spread across Andhra Pradesh, Madhya Pradesh, and Rajasthan. The contract duration is 36 months.The tender, issued in January 2025, was divided into two lots: Lot 1 for 1,054 MWp and Lot 2 for 810 MWp. VSL emerged as the lowest bidder in both categories, but was awarded only Lot 2 in accordance with NTPC’s tender guidelines.Advanced Monitoring and Tailored StrategiesThe O&M scope will employ artificial intelligence and Internet of..

Next Story
Infrastructure Energy

AP Issues Bid for Rs 34.9 Billion Battery Storage Project

The Transmission Corporation of Andhra Pradesh (APTRANSCO) has invited bids for the development of 1,000 MW/2,000 MWh battery energy storage systems (BESS) across seven substations in the state. The project, with an estimated viability gap funding of up to Rs 34.9 billion, will be executed under a build, own, and operate (BOO) model through tariff-based competitive bidding.Bid Timeline and StructureBids must be submitted by 29 September 2025 and will be opened on 6 October. The VGF support per project is capped at Rs 1.8 million per MWh and will be released in three instalments—20 per cent u..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?