CERC Clears Rs 5.89 Billion Tariff for Adani-Led Grid Project
POWER & RENEWABLE ENERGY

CERC Clears Rs 5.89 Billion Tariff for Adani-Led Grid Project

The Central Electricity Regulatory Commission (CERC) has approved annual transmission charges of Rs 5.89 billion for the Pune-III Transmission Limited project, part of efforts to evacuate 7 GW of renewable power from Gujarat’s Khavda region under Phase IV, Part D. The project will be implemented on a Build, Own, Operate, and Transfer (BOOT) basis and was originally floated by PFC Consulting Limited (PFCCL), later awarded to Adani Energy Solutions Limited through tariff-based competitive bidding.
The process commenced with the publication of the Request for Proposal on 19 October 2023, followed by bid submissions on 19 April 2024. Financial bids were opened on 25 September 2024, and an intense e-reverse auction, lasting 178 rounds, concluded on 28 September 2024. The final discovered tariff, quoted by Adani Energy Solutions, exceeded CERC's earlier levelised tariff estimate of Rs 4.56 billion by 11.24 per cent. The rise was attributed to revised Right of Way (RoW) compensation norms, changes in land values, and a recalculated completion factor for project cost escalation. The Cost Committee subsequently revised the project cost from Rs 33.81 billion to Rs 40.21 billion.
Despite the higher bid, the Bid Evaluation Committee and the CERC deemed the process transparent, competitive, and consistent with the Ministry of Power’s guidelines. A Letter of Intent was issued to Adani Energy on 21 October 2024, and the company acquired Pune-III Transmission on 19 November 2024 after furnishing a Rs 700 million performance guarantee. The Commission has now adopted the Rs 5.89 billion per annum tariff for the duration of the Transmission Service Agreement.
CERC also instructed PFCCL to improve clarity in committee documentation for future tenders. The transmission charges will be shared by designated interstate transmission customers, as outlined in the 2020 CERC regulations. This order marks the formal closure of Petition No. 75/AT/2025 and sets the stage for one of India’s largest renewable power evacuation systems to move forward. 

The Central Electricity Regulatory Commission (CERC) has approved annual transmission charges of Rs 5.89 billion for the Pune-III Transmission Limited project, part of efforts to evacuate 7 GW of renewable power from Gujarat’s Khavda region under Phase IV, Part D. The project will be implemented on a Build, Own, Operate, and Transfer (BOOT) basis and was originally floated by PFC Consulting Limited (PFCCL), later awarded to Adani Energy Solutions Limited through tariff-based competitive bidding.The process commenced with the publication of the Request for Proposal on 19 October 2023, followed by bid submissions on 19 April 2024. Financial bids were opened on 25 September 2024, and an intense e-reverse auction, lasting 178 rounds, concluded on 28 September 2024. The final discovered tariff, quoted by Adani Energy Solutions, exceeded CERC's earlier levelised tariff estimate of Rs 4.56 billion by 11.24 per cent. The rise was attributed to revised Right of Way (RoW) compensation norms, changes in land values, and a recalculated completion factor for project cost escalation. The Cost Committee subsequently revised the project cost from Rs 33.81 billion to Rs 40.21 billion.Despite the higher bid, the Bid Evaluation Committee and the CERC deemed the process transparent, competitive, and consistent with the Ministry of Power’s guidelines. A Letter of Intent was issued to Adani Energy on 21 October 2024, and the company acquired Pune-III Transmission on 19 November 2024 after furnishing a Rs 700 million performance guarantee. The Commission has now adopted the Rs 5.89 billion per annum tariff for the duration of the Transmission Service Agreement.CERC also instructed PFCCL to improve clarity in committee documentation for future tenders. The transmission charges will be shared by designated interstate transmission customers, as outlined in the 2020 CERC regulations. This order marks the formal closure of Petition No. 75/AT/2025 and sets the stage for one of India’s largest renewable power evacuation systems to move forward. 

Next Story
Infrastructure Transport

Tunnelling Begins for Thane, Borivali twin tunnel project

Tunnelling work has commenced for the 11.84-km Thane–Borivali Twin Tunnel, set to be India’s longest urban road tunnel, marking a key milestone in Mumbai’s infrastructure development.As per a post shared by Mumbai Metropolitan Region Development Authority on social media platform X, the tunnel boring machine (TBM) ‘Nayak’—the country’s largest single-shield hard rock TBM for an urban tunnel—was launched by Devendra Fadnavis on Tuesday. The event was attended by Eknath Shinde and Sunetra Pawar, among other dignitaries. A second TBM, ‘Arjuna’, is expected to be launched so..

Next Story
Infrastructure Transport

Large Format Store Planned At M G Road Metro Station

M G Road station in Bengaluru is set to host the city’s first large-format commercial and experience space, with planning led by Bangalore Metro Rail Corporation Limited. BMRCL has invited proposals to develop and operate a central business district destination at the Purple?Pink Line interchange. The plan positions the station as a commercial hub designed to serve a broad commuter base across the city. The proposal is part of a broader effort to activate transit nodes commercially. Tender documents set a minimum monthly rental of Rs 0.944 million (mn), inclusive of GST, for the large-format..

Next Story
Infrastructure Energy

Government Cancels Auction Of Eleven Critical Mineral Blocks

The government has cancelled the auction of 11 critical and strategic mineral blocks after receiving a poor investor response and failing to attract a sufficient number of qualified bidders. The decision represents a setback to plans to ramp up domestic exploration and production of critical minerals amid global supply chain disruptions and rising demand for materials used in clean energy and advanced technologies. The mines ministry issued an annulment notice setting out the reasons for the cancellations. The annulment notice indicated that the auction process for five mineral blocks was canc..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement