Chakan MIDC's infrastructure being upgraded by the power utility
POWER & RENEWABLE ENERGY

Chakan MIDC's infrastructure being upgraded by the power utility

The Maharashtra State Energy Distribution Company (MSEDCL) has started upgrading the electrical infrastructure in the Chakan industrial area for Rs 150 million under the electricity system improvement scheme, providing relief to over 3,000 industrial customers.

Three new switching stations, one switching station's capacity improvement, 35 km of new underground cables, the division of overloaded lines and the construction of new lines, six new ring main units, and other things are included in the work.

Rajendra Pawar, Head Engineer, MSEDCL's Pune zone, predicted that the project will be finished in three months. "We are making steps to hasten the power system's empowerment. Additionally, a number of projects are suggested, including boosting the power transformer capacity in the high-pressure substations run by the Maharashtra State Electricity Transmission Company (MSETCL). Soon, a plan for it will be created.

The industry and MSEDCL both experience revenue and production losses as a result of the frequent power outages. It is encouraging to see that construction has finally started in the industrial belt after several years of our calling for the upgrading of the power infrastructure.

Also read:
Nepal, India agrees to allow export of power longterm basis
NTPC to have 2,000 MW of nuclear power by 2032


The Maharashtra State Energy Distribution Company (MSEDCL) has started upgrading the electrical infrastructure in the Chakan industrial area for Rs 150 million under the electricity system improvement scheme, providing relief to over 3,000 industrial customers. Three new switching stations, one switching station's capacity improvement, 35 km of new underground cables, the division of overloaded lines and the construction of new lines, six new ring main units, and other things are included in the work. Rajendra Pawar, Head Engineer, MSEDCL's Pune zone, predicted that the project will be finished in three months. We are making steps to hasten the power system's empowerment. Additionally, a number of projects are suggested, including boosting the power transformer capacity in the high-pressure substations run by the Maharashtra State Electricity Transmission Company (MSETCL). Soon, a plan for it will be created. The industry and MSEDCL both experience revenue and production losses as a result of the frequent power outages. It is encouraging to see that construction has finally started in the industrial belt after several years of our calling for the upgrading of the power infrastructure. Also read: Nepal, India agrees to allow export of power longterm basis NTPC to have 2,000 MW of nuclear power by 2032

Next Story
Real Estate

AI: The New Recruit

From getting ideas to evaluating designs, presenting concepts to clients and tracking projects, artificial intelligence (AI) is helping architects work better and faster.“AI allows architects to spend more time doing what only they can do: think critically, synthesise complexity and design with intent,” says Dikshu C Kukreja, Managing Principal, CP Kukreja Architects. “Every minute reclaimed from repetitive processes can be invested in creativity, contextual understanding, interdisciplinary collaboration and innovation – the qualities that define meaningful architecture.”To read the ..

Next Story
Real Estate

Redevelopment 2.0

In 2017, Mumbai identified 160,000 ageing buildings due for structural audit. Close to half of these were in the Western Suburbs. Redeveloping the oldest and structurally weakest of these would help unlock new housing, much needed given the city’s growing population density and constant developed area of 437.7 sq km. At 30,600 people per sq km in 2024, Mumbai’s density was almost thrice that of Gurugram, and 60 per cent higher than Bengaluru’s.Essentially, Mumbai’s realty market has demand. It has capital. It has realty development potential.Fast forward to 2026. Mumbai has 1,094 regis..

Next Story
Technology

Cost intelligence will become a strategic contributor to project success

As India's construction industry accelerates its digital transformation, integrated platforms, AI and connected data are becoming essential to improving cost certainty, project efficiency and sustainability. Ravi Kumar, Sales Director – India, RIB Software India, shares how digital workflows are reshaping project planning, commercial management and decision-making across the construction value chain.India's construction sector is embracing digital technologies at an unprecedented pace. From your perspective, what are the biggest shifts driving this transformation and how is RIB Software enab..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement