Chakan MIDC's infrastructure being upgraded by the power utility
POWER & RENEWABLE ENERGY

Chakan MIDC's infrastructure being upgraded by the power utility

The Maharashtra State Energy Distribution Company (MSEDCL) has started upgrading the electrical infrastructure in the Chakan industrial area for Rs 150 million under the electricity system improvement scheme, providing relief to over 3,000 industrial customers.

Three new switching stations, one switching station's capacity improvement, 35 km of new underground cables, the division of overloaded lines and the construction of new lines, six new ring main units, and other things are included in the work.

Rajendra Pawar, Head Engineer, MSEDCL's Pune zone, predicted that the project will be finished in three months. "We are making steps to hasten the power system's empowerment. Additionally, a number of projects are suggested, including boosting the power transformer capacity in the high-pressure substations run by the Maharashtra State Electricity Transmission Company (MSETCL). Soon, a plan for it will be created.

The industry and MSEDCL both experience revenue and production losses as a result of the frequent power outages. It is encouraging to see that construction has finally started in the industrial belt after several years of our calling for the upgrading of the power infrastructure.

Also read:
Nepal, India agrees to allow export of power longterm basis
NTPC to have 2,000 MW of nuclear power by 2032


Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

The Maharashtra State Energy Distribution Company (MSEDCL) has started upgrading the electrical infrastructure in the Chakan industrial area for Rs 150 million under the electricity system improvement scheme, providing relief to over 3,000 industrial customers. Three new switching stations, one switching station's capacity improvement, 35 km of new underground cables, the division of overloaded lines and the construction of new lines, six new ring main units, and other things are included in the work. Rajendra Pawar, Head Engineer, MSEDCL's Pune zone, predicted that the project will be finished in three months. We are making steps to hasten the power system's empowerment. Additionally, a number of projects are suggested, including boosting the power transformer capacity in the high-pressure substations run by the Maharashtra State Electricity Transmission Company (MSETCL). Soon, a plan for it will be created. The industry and MSEDCL both experience revenue and production losses as a result of the frequent power outages. It is encouraging to see that construction has finally started in the industrial belt after several years of our calling for the upgrading of the power infrastructure. Also read: Nepal, India agrees to allow export of power longterm basis NTPC to have 2,000 MW of nuclear power by 2032

Next Story
Real Estate

Vitizen Hotels Signs Deal at Manyata Tech Park

Vikram Kamats Hospitality, as part of its ongoing expansion in key metropolitan markets, announced that its material subsidiary, Vitizen Hotels, has signed a long-term lease agreement for a 45-key hotel property at Manyata Tech Park, Bengaluru.Strategically located in the city’s prominent IT hub, the property is well-positioned to serve corporate travelers, business professionals, and long-stay guests. The addition aligns with the company’s asset-light growth model, leveraging long-term leases to expand its footprint in high-demand urban markets.The hotel is expected to strengthen the comp..

Next Story
Infrastructure Transport

CONCOR Signs MoU with BPIPL to Operate Container Terminal at Bhavnagar Port

Container Corporation of India (CONCOR) has signed a Memorandum of Understanding (MoU) with Bhavnagar Port Infrastructure (BPIPL) on September 4, 2025, in New Delhi to operate and maintain the upcoming container terminal at the northside of Bhavnagar Port, Gujarat.BPIPL had earlier entered into an agreement with the Gujarat Maritime Board (GMB) in September 2024 for the port’s development. Under this arrangement, 235 hectares of land has been leased to BPIPL for 30 years, with provision for expansion by an additional 250 hectares.The new terminal is expected to significantly enhance logistic..

Next Story
Infrastructure Transport

Concord Launches India’s First Indigenous Zero-Emission Rail Propulsion

Concord Control Systems (CCSL), a leader in embedded electronics and critical rail technologies, has announced the development of India’s first fully indigenous zero-emission propulsion system, marking a significant step toward the country’s railway electrification and net-zero goals for 2030.Powered by Lithium Iron Phosphate (LFP) batteries and featuring a DC chopper-based drive, the propulsion system eliminates idling losses common in diesel engines, offering higher efficiency, lower costs, and zero emissions.What sets this innovation apart is its completely indigenous design. Except for..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?