Hubballi airport to generate solar power for other airports
POWER & RENEWABLE ENERGY

Hubballi airport to generate solar power for other airports

From March 2021, the Hubballi Domestic Airport would be footing the electric bills of all airports that are managed by the Airports Authority of India (AAI) located in Karnataka excluding Bengaluru and Mangaluru International Airports in the plan.

The airport would be generating 140 lakh units of electricity by March 2021 through an eight-megawatt grid that is ground-mounted. The grid is connected to a photovoltaic (PV) solar plant that will be installed. The power generated would be used for the high-tension grid of Karnataka Power Transmission Corporation Limited through a drive wheel system. Additionally, it will take credit of the electricity bill of airports based in Karnataka that is managed by AAI. Once the project is completed, the airport’s external power supply would be lower than 85% annually.

The project is handed over to a Gujarat-based company called Madhav Infra Private Limited that would be executing the project at Rs 64 crore. As of now laying cables, establishing transformed and miscellaneous civil work has been completed. The remaining should be done by the end of March or early week of April.

Over 22,500 solar panels would be installed on nearly 24 acres of land. It is done so that the PV solar system manages to get maximum solar radiable throughout the year based on the orientation and titling of modules. It would help avoid shading and modules would be arranged in a row arrangement called string to ensure a higher system voltage. Moreover, a higher system voltage means lesser installation work and greater efficiency of the solar plant with the usage of cross-section cables in smaller sizes.

Currently, the combined power consumption of all airports based in Karnataka is close to 132 lakh units per year, and the Hubballi Airport would be generating approximately 140 lakh units.

Image Source

From March 2021, the Hubballi Domestic Airport would be footing the electric bills of all airports that are managed by the Airports Authority of India (AAI) located in Karnataka excluding Bengaluru and Mangaluru International Airports in the plan. The airport would be generating 140 lakh units of electricity by March 2021 through an eight-megawatt grid that is ground-mounted. The grid is connected to a photovoltaic (PV) solar plant that will be installed. The power generated would be used for the high-tension grid of Karnataka Power Transmission Corporation Limited through a drive wheel system. Additionally, it will take credit of the electricity bill of airports based in Karnataka that is managed by AAI. Once the project is completed, the airport’s external power supply would be lower than 85% annually. The project is handed over to a Gujarat-based company called Madhav Infra Private Limited that would be executing the project at Rs 64 crore. As of now laying cables, establishing transformed and miscellaneous civil work has been completed. The remaining should be done by the end of March or early week of April. Over 22,500 solar panels would be installed on nearly 24 acres of land. It is done so that the PV solar system manages to get maximum solar radiable throughout the year based on the orientation and titling of modules. It would help avoid shading and modules would be arranged in a row arrangement called string to ensure a higher system voltage. Moreover, a higher system voltage means lesser installation work and greater efficiency of the solar plant with the usage of cross-section cables in smaller sizes. Currently, the combined power consumption of all airports based in Karnataka is close to 132 lakh units per year, and the Hubballi Airport would be generating approximately 140 lakh units. Image Source

Next Story
Infrastructure Transport

Gurgaon-Pataudi-Rewari Highway Set for Completion by December 2025

The National Highways Authority of India (NHAI) has set a new target to complete the four-lane Gurgaon-Pataudi-Rewari highway by December 2025, following a two-year delay.Originally planned in 2018 to upgrade the two-lane state highway into a national highway, the project is estimated to cost Rs 9 billion. Construction, which began in 2021, was initially scheduled for completion in November 2023. According to NHAI, around 70 per cent of the work is already complete, with two major structures still pending: a railway overbridge at Pahari village and a two-lane unidirectional flyover on Dwarka E..

Next Story
Infrastructure Transport

UP Plans Rs 900 Million Extensions to Hindon Elevated Road

The Uttar Pradesh state bridge corporation has prepared the detailed project report and cost estimates for two proposed extensions of the 10.3-km Hindon elevated road, officials said on Thursday. The road connects Raj Nagar Extension to UP-Gate near the east Delhi border, and the project is expected to cost around Rs 900 million.The two extensions, each 400 metres long, will be added to the existing elevated road to ensure smoother traffic flow. “One of the extensions will be from near the Kanawani culvert (near Indirapuram) to the elevated road for commuters heading towards Delhi. The other..

Next Story
Infrastructure Urban

Goa Likely to Miss October Deadline for Maritime Master Plan

Goa is expected to miss the October 31 deadline for submitting its maritime and waterways master plan, which covers the state’s 105 km coastline and river network. The delay is due to the project management consultant not yet being appointed. The plan is now anticipated to be completed by December, Captain of Ports Octavio Rodrigues stated at the India Maritime Week 2025 roadshow.“We have already selected the consultant and will bring them on board within a week. Only then can we begin drafting the master plan, which is essential to secure central government funding,” Rodrigues added.A c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?