+
India’s Stranded Green Power Projects Cross 50 GW
POWER & RENEWABLE ENERGY

India’s Stranded Green Power Projects Cross 50 GW

India’s stranded renewable energy capacity—projects awarded but unable to commence operations—has more than doubled in just nine months, largely due to unfinished transmission lines, and persistent legal and regulatory bottlenecks, according to letters sent by the Sustainable Projects Developers Association (SPDA) to the government.
As of June 2025, over 50 gigawatts (GW) of solar and wind projects remain idle, despite winning tenders, because they are yet to secure power purchase agreements (PPAs) with buyers. This is a significant increase from over 20 GW of stranded capacity reported by the SPDA in a previous letter dated October 2024. Reuters reviewed both letters.
The 50 GW in stranded projects represents nearly one-quarter of India’s total installed renewable capacity of 184.6 GW.
“India's energy transition is not just about installing solar and wind capacity—it must also ensure that clean power is delivered optimally, cost-effectively, and on time,” the SPDA said in its 27 June letter to the Ministry of New and Renewable Energy.
India aims to increase its non-fossil fuel power capacity to 500 GW by 2030. A record 22 GW of solar and wind capacity was commissioned in the six months ending June 2025, as per government data.
However, billions of dollars' worth of tendered projects awarded to major developers—including JSW, NTPC, Adani Green, ReNew, ACME Solar, and Sembcorp—remain stranded, said two industry officials familiar with the matter. These companies did not respond to Reuters’ requests for comment.
The SPDA, which counts ReNew Power, ACME Group, and Avaada Group among its core members, highlighted that transmission infrastructure delays—particularly in solar-rich states like Rajasthan and Gujarat—are causing missed commissioning deadlines, risking penalties and loss of incentives.
The association urged the government to classify such delays and pending regulatory approvals as force majeure events, shielding developers from financial penalties. It also called for faster environmental clearances and land-use approvals, noting that many projects remain stalled due to ongoing litigation.
Several developers have reportedly paused operations until these legal uncertainties are resolved. 

India’s stranded renewable energy capacity—projects awarded but unable to commence operations—has more than doubled in just nine months, largely due to unfinished transmission lines, and persistent legal and regulatory bottlenecks, according to letters sent by the Sustainable Projects Developers Association (SPDA) to the government.As of June 2025, over 50 gigawatts (GW) of solar and wind projects remain idle, despite winning tenders, because they are yet to secure power purchase agreements (PPAs) with buyers. This is a significant increase from over 20 GW of stranded capacity reported by the SPDA in a previous letter dated October 2024. Reuters reviewed both letters.The 50 GW in stranded projects represents nearly one-quarter of India’s total installed renewable capacity of 184.6 GW.“India's energy transition is not just about installing solar and wind capacity—it must also ensure that clean power is delivered optimally, cost-effectively, and on time,” the SPDA said in its 27 June letter to the Ministry of New and Renewable Energy.India aims to increase its non-fossil fuel power capacity to 500 GW by 2030. A record 22 GW of solar and wind capacity was commissioned in the six months ending June 2025, as per government data.However, billions of dollars' worth of tendered projects awarded to major developers—including JSW, NTPC, Adani Green, ReNew, ACME Solar, and Sembcorp—remain stranded, said two industry officials familiar with the matter. These companies did not respond to Reuters’ requests for comment.The SPDA, which counts ReNew Power, ACME Group, and Avaada Group among its core members, highlighted that transmission infrastructure delays—particularly in solar-rich states like Rajasthan and Gujarat—are causing missed commissioning deadlines, risking penalties and loss of incentives.The association urged the government to classify such delays and pending regulatory approvals as force majeure events, shielding developers from financial penalties. It also called for faster environmental clearances and land-use approvals, noting that many projects remain stalled due to ongoing litigation.Several developers have reportedly paused operations until these legal uncertainties are resolved. 

Next Story
Infrastructure Transport

Railways Opens First Section of Bullet Train Tunnel in Maharashtra

The Mumbai–Ahmedabad bullet train project has achieved a key milestone with the opening of the first section of a 21-km undersea tunnel between Ghansoli and Shilphata in Maharashtra. The high-speed rail corridor, powered entirely by Japanese Shinkansen technology, has seen 310 km of viaducts completed, alongside rapid progress in track laying, electrical works, and station construction. Five of the 12 stations are complete, with three more nearing completion. The BKC station, located 32.5 metres underground, is designed to support a 95-metre structure above. The next-generation E10 Shin..

Next Story
Infrastructure Urban

Mahindra, Osaka Ink Pact to Boost Japanese Investment

Mahindra Industrial Park Chennai (MIPCL), along with its Japanese stakeholder Sumitomo Corporation, has signed a strategic cooperation agreement with the Osaka Prefecture and Osaka Industrial Development Bureau to support Osaka-based businesses entering India.The partnership aims to streamline entry for Japanese manufacturers, providing support such as business visits, regulatory guidance, and market insights. MIPCL and Sumitomo will act as local facilitators, while Osaka authorities will identify and recommend companies for expansion.With India’s projected GDP growth of 6.3 per cent in FY25..

Next Story
Building Material

Govt Plans Mandatory Public Procurement of Green Steel

The Ministry of Steel is working on modalities to mandate public procurement of green steel, as part of its efforts to decarbonise the industry. A Rs 150 billion Green Steel Mission is being formulated to support emission reduction and move towards net-zero targets.The mission will include a PLI scheme, incentives for renewable energy use, and mandates for government agencies to buy green steel. Green steel is produced with significantly lower carbon emissions compared to conventional methods.Speaking at the India Steel Conclave 2025, a senior official said procurement mandates are under consi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?