KERC okays Rs 8.40 per kWh tariff for Cambria Solar PPA with BESCOM
POWER & RENEWABLE ENERGY

KERC okays Rs 8.40 per kWh tariff for Cambria Solar PPA with BESCOM

The Karnataka Electricity Regulatory Commission (KERC) has given its nod for a tariff of Rs 8.40 per kWh as per the power purchase agreement (PPA) signed between Bangalore Electricity Supply Company Ltd (BESCOM) and the developer of the project—Cambria Solar.

KERC also approved the extension of six months granted by BESCOM for the commissioning date of the solar project.

Cambria Solar had filed a petition requesting the KERC to approve the extension of six months granted by BESCOM to the scheduled commercial operation date (SCOD) as agreed between the parties. It had also requested the regulator to approve the tariff of Rs 8.40 per kWh from the project’s commercial operation date for the whole term of the PPA.

A land-owning farmer, Gangaraju, had applied for a 3 MW solar power project under the solar program initiated by the Karnataka Renewable Energy Development Ltd (KREDL). The project was allotted to him.

BESCOM, in its meeting held in July 2015, gave consent for the purchase of solar power from the project. Both the parties signed the PPA in the same month, and subsequently, the PPA was approved by the KERC in August 2015.

As per the PPA, the scheduled date of completion was to be achieved within 18 months from the PPA signing. The power to extend the time for commissioning was vested with BESCOM.

According to the PPA, the project promoter had the right to form a special purpose vehicle (SPV) after the PPA execution. Accordingly, Cambria Solar was incorporated as an SPV.

The developer informed BESCOM in November 2016 that it had applied for the bay allocation from the Karnataka Power Transmission Corporation Limited (KPTCL) but had not received the bay allotment due to augmentation of the transformer at 66/11 KV Moregere Substation.

The developer sought an extension of six months from January 6, 2017, which it perceived to be the SCOD. KPTCL granted evacuation approval to the petitioner.

Later, BESCOM granted an extension of six months from the SCOD as per the PPA, subject to the bank guarantee extension. The developer said it was entitled to a tariff of Rs 8.40 per kWh, according to the PPA.

BESCOM, in its submission, said that as the developer was unable to execute the project on time, a letter was addressed to it seeking an extension of time for commissioning the project.

The Karnataka government issued an order in November 2016, directing all the electricity supply companies (escoms) to constitute a three-member committee to consider and dispose of the farmers’ and developers’ requests.

After detailed discussions, the committee suggested the approval be granted for the extension of SCOD for up to six months. According to KERC, it was not in dispute that PPA was executed on 7 July 2015, and the effective date meant the date of signing of the agreement by the parties, ie, 7 July 2015.

The regulator noted that in pursuance of the government’s direction, a three-member committee decided to approve an extension of SCOD by six months.

KERC noted that the developer had applied for power evacuation in September 2016, and KPTCL gave approval for evacuation in December 2016, after a lapse of more than two months.

BESCOM granted an extension by six months considering these facts and considering a substantial investment in the project.

The regulator noted that the petitioner was entitled to the tariff of Rs 8.40 per kWh from the commercial operation date because it had implemented the project within the extended time. Due to the ‘force majeure’ event, it could not commission the project within 18 months from the effective date.

Image Source


Also read: GESCOM invites bids for 10 MW rooftop solar net metering in Karnataka

The Karnataka Electricity Regulatory Commission (KERC) has given its nod for a tariff of Rs 8.40 per kWh as per the power purchase agreement (PPA) signed between Bangalore Electricity Supply Company Ltd (BESCOM) and the developer of the project—Cambria Solar. KERC also approved the extension of six months granted by BESCOM for the commissioning date of the solar project. Cambria Solar had filed a petition requesting the KERC to approve the extension of six months granted by BESCOM to the scheduled commercial operation date (SCOD) as agreed between the parties. It had also requested the regulator to approve the tariff of Rs 8.40 per kWh from the project’s commercial operation date for the whole term of the PPA. A land-owning farmer, Gangaraju, had applied for a 3 MW solar power project under the solar program initiated by the Karnataka Renewable Energy Development Ltd (KREDL). The project was allotted to him. BESCOM, in its meeting held in July 2015, gave consent for the purchase of solar power from the project. Both the parties signed the PPA in the same month, and subsequently, the PPA was approved by the KERC in August 2015. As per the PPA, the scheduled date of completion was to be achieved within 18 months from the PPA signing. The power to extend the time for commissioning was vested with BESCOM. According to the PPA, the project promoter had the right to form a special purpose vehicle (SPV) after the PPA execution. Accordingly, Cambria Solar was incorporated as an SPV. The developer informed BESCOM in November 2016 that it had applied for the bay allocation from the Karnataka Power Transmission Corporation Limited (KPTCL) but had not received the bay allotment due to augmentation of the transformer at 66/11 KV Moregere Substation. The developer sought an extension of six months from January 6, 2017, which it perceived to be the SCOD. KPTCL granted evacuation approval to the petitioner. Later, BESCOM granted an extension of six months from the SCOD as per the PPA, subject to the bank guarantee extension. The developer said it was entitled to a tariff of Rs 8.40 per kWh, according to the PPA. BESCOM, in its submission, said that as the developer was unable to execute the project on time, a letter was addressed to it seeking an extension of time for commissioning the project. The Karnataka government issued an order in November 2016, directing all the electricity supply companies (escoms) to constitute a three-member committee to consider and dispose of the farmers’ and developers’ requests. After detailed discussions, the committee suggested the approval be granted for the extension of SCOD for up to six months. According to KERC, it was not in dispute that PPA was executed on 7 July 2015, and the effective date meant the date of signing of the agreement by the parties, ie, 7 July 2015. The regulator noted that in pursuance of the government’s direction, a three-member committee decided to approve an extension of SCOD by six months. KERC noted that the developer had applied for power evacuation in September 2016, and KPTCL gave approval for evacuation in December 2016, after a lapse of more than two months. BESCOM granted an extension by six months considering these facts and considering a substantial investment in the project. The regulator noted that the petitioner was entitled to the tariff of Rs 8.40 per kWh from the commercial operation date because it had implemented the project within the extended time. Due to the ‘force majeure’ event, it could not commission the project within 18 months from the effective date. Image Source Also read: GESCOM invites bids for 10 MW rooftop solar net metering in Karnataka

Related Stories

Gold Stories

Next Story
Real Estate

L&T Wins Mega Order for India’s Largest NVIDIA B300 AI Factory

Larsen & Toubro (L&T), through Vyoma.AI’s AI infrastructure subsidiary LTN Compute, has secured a mega order to develop what the company describes as India’s largest single-cluster AI infrastructure facility. The NVIDIA B300 AI Factory will support US-based AI cloud company Together AI’s platform for large-scale inference, fine-tuning and training workloads.The integrated AI Factory will be hosted at Vyoma.AI’s Chennai data centre campus and will have a capacity of 10,000 NVIDIA B300 GPUs. The platform will combine hyperscale data centre infrastructure, accelerated computing, h..

Next Story
Infrastructure Urban

Autodesk Elevates Nikhil Bagalkotkar to Lead AEC in India, SAARC

Autodesk has elevated Nikhil Bagalkotkar as Head – Architecture, Engineering and Construction (AEC), India and SAARC, with immediate effect.In his new role, Bagalkotkar will lead Autodesk's AEC business strategy across the region and drive adoption of the company's Design and Make platform. He will also focus on promoting digital design and construction technologies to help customers accelerate innovation and deliver more sustainable and resilient infrastructure.Bagalkotkar will be responsible for expanding Autodesk's AEC business, strengthening customer and partner engagement, and accelerat..

Next Story
Real Estate

Listed Developers' Pre-Sales Seen Rising 22.3 Per Cent in FY27

India's leading listed residential developers are expected to sustain strong sales momentum in FY27, with combined pre-sales of 11 major players projected to rise 22.3 per cent year-on-year, according to an analysis by ANAROCK Research & Advisory.Combined pre-sales of the developers are estimated to increase from Rs 1.49 trillion in FY26 to Rs 1.82 lakh crore in FY27. ANAROCK attributed the growth to sustained end-user demand, new project launches and strong execution despite higher property prices, construction costs and global uncertainties.Dr Prashant Thakur, Executive Director and Head..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement