+
KERC okays Rs 8.40 per kWh tariff for Cambria Solar PPA with BESCOM
POWER & RENEWABLE ENERGY

KERC okays Rs 8.40 per kWh tariff for Cambria Solar PPA with BESCOM

The Karnataka Electricity Regulatory Commission (KERC) has given its nod for a tariff of Rs 8.40 per kWh as per the power purchase agreement (PPA) signed between Bangalore Electricity Supply Company Ltd (BESCOM) and the developer of the project—Cambria Solar.

KERC also approved the extension of six months granted by BESCOM for the commissioning date of the solar project.

Cambria Solar had filed a petition requesting the KERC to approve the extension of six months granted by BESCOM to the scheduled commercial operation date (SCOD) as agreed between the parties. It had also requested the regulator to approve the tariff of Rs 8.40 per kWh from the project’s commercial operation date for the whole term of the PPA.

A land-owning farmer, Gangaraju, had applied for a 3 MW solar power project under the solar program initiated by the Karnataka Renewable Energy Development Ltd (KREDL). The project was allotted to him.

BESCOM, in its meeting held in July 2015, gave consent for the purchase of solar power from the project. Both the parties signed the PPA in the same month, and subsequently, the PPA was approved by the KERC in August 2015.

As per the PPA, the scheduled date of completion was to be achieved within 18 months from the PPA signing. The power to extend the time for commissioning was vested with BESCOM.

According to the PPA, the project promoter had the right to form a special purpose vehicle (SPV) after the PPA execution. Accordingly, Cambria Solar was incorporated as an SPV.

The developer informed BESCOM in November 2016 that it had applied for the bay allocation from the Karnataka Power Transmission Corporation Limited (KPTCL) but had not received the bay allotment due to augmentation of the transformer at 66/11 KV Moregere Substation.

The developer sought an extension of six months from January 6, 2017, which it perceived to be the SCOD. KPTCL granted evacuation approval to the petitioner.

Later, BESCOM granted an extension of six months from the SCOD as per the PPA, subject to the bank guarantee extension. The developer said it was entitled to a tariff of Rs 8.40 per kWh, according to the PPA.

BESCOM, in its submission, said that as the developer was unable to execute the project on time, a letter was addressed to it seeking an extension of time for commissioning the project.

The Karnataka government issued an order in November 2016, directing all the electricity supply companies (escoms) to constitute a three-member committee to consider and dispose of the farmers’ and developers’ requests.

After detailed discussions, the committee suggested the approval be granted for the extension of SCOD for up to six months. According to KERC, it was not in dispute that PPA was executed on 7 July 2015, and the effective date meant the date of signing of the agreement by the parties, ie, 7 July 2015.

The regulator noted that in pursuance of the government’s direction, a three-member committee decided to approve an extension of SCOD by six months.

KERC noted that the developer had applied for power evacuation in September 2016, and KPTCL gave approval for evacuation in December 2016, after a lapse of more than two months.

BESCOM granted an extension by six months considering these facts and considering a substantial investment in the project.

The regulator noted that the petitioner was entitled to the tariff of Rs 8.40 per kWh from the commercial operation date because it had implemented the project within the extended time. Due to the ‘force majeure’ event, it could not commission the project within 18 months from the effective date.

Image Source


Also read: GESCOM invites bids for 10 MW rooftop solar net metering in Karnataka

The Karnataka Electricity Regulatory Commission (KERC) has given its nod for a tariff of Rs 8.40 per kWh as per the power purchase agreement (PPA) signed between Bangalore Electricity Supply Company Ltd (BESCOM) and the developer of the project—Cambria Solar. KERC also approved the extension of six months granted by BESCOM for the commissioning date of the solar project. Cambria Solar had filed a petition requesting the KERC to approve the extension of six months granted by BESCOM to the scheduled commercial operation date (SCOD) as agreed between the parties. It had also requested the regulator to approve the tariff of Rs 8.40 per kWh from the project’s commercial operation date for the whole term of the PPA. A land-owning farmer, Gangaraju, had applied for a 3 MW solar power project under the solar program initiated by the Karnataka Renewable Energy Development Ltd (KREDL). The project was allotted to him. BESCOM, in its meeting held in July 2015, gave consent for the purchase of solar power from the project. Both the parties signed the PPA in the same month, and subsequently, the PPA was approved by the KERC in August 2015. As per the PPA, the scheduled date of completion was to be achieved within 18 months from the PPA signing. The power to extend the time for commissioning was vested with BESCOM. According to the PPA, the project promoter had the right to form a special purpose vehicle (SPV) after the PPA execution. Accordingly, Cambria Solar was incorporated as an SPV. The developer informed BESCOM in November 2016 that it had applied for the bay allocation from the Karnataka Power Transmission Corporation Limited (KPTCL) but had not received the bay allotment due to augmentation of the transformer at 66/11 KV Moregere Substation. The developer sought an extension of six months from January 6, 2017, which it perceived to be the SCOD. KPTCL granted evacuation approval to the petitioner. Later, BESCOM granted an extension of six months from the SCOD as per the PPA, subject to the bank guarantee extension. The developer said it was entitled to a tariff of Rs 8.40 per kWh, according to the PPA. BESCOM, in its submission, said that as the developer was unable to execute the project on time, a letter was addressed to it seeking an extension of time for commissioning the project. The Karnataka government issued an order in November 2016, directing all the electricity supply companies (escoms) to constitute a three-member committee to consider and dispose of the farmers’ and developers’ requests. After detailed discussions, the committee suggested the approval be granted for the extension of SCOD for up to six months. According to KERC, it was not in dispute that PPA was executed on 7 July 2015, and the effective date meant the date of signing of the agreement by the parties, ie, 7 July 2015. The regulator noted that in pursuance of the government’s direction, a three-member committee decided to approve an extension of SCOD by six months. KERC noted that the developer had applied for power evacuation in September 2016, and KPTCL gave approval for evacuation in December 2016, after a lapse of more than two months. BESCOM granted an extension by six months considering these facts and considering a substantial investment in the project. The regulator noted that the petitioner was entitled to the tariff of Rs 8.40 per kWh from the commercial operation date because it had implemented the project within the extended time. Due to the ‘force majeure’ event, it could not commission the project within 18 months from the effective date. Image Source Also read: GESCOM invites bids for 10 MW rooftop solar net metering in Karnataka

Next Story
Infrastructure Urban

Budget Proposal Aims to Boost Investments

The recent budget proposal has introduced measures designed to promote investments and generate job opportunities across various industries, as reported by the Economic Times. This initiative seeks to stimulate economic activity and strengthen the country's growth trajectory by encouraging both domestic and foreign investments. Key aspects of the proposal include targeted incentives for sectors poised for expansion, such as renewable energy, infrastructure, and technology. The government aims to create a more favorable investment climate by offering tax benefits, subsidies, and streamlined reg..

Next Story
Infrastructure Urban

Indian Financial System Resilient Amidst Challenges

The Reserve Bank of India (RBI) Deputy Governor M. Rajeshwar Rao has emphasized the robust nature of the Indian financial system despite global economic headwinds, according to Economic Times. Rao?s comments reflect confidence in the stability and resilience of India's financial sector amidst a backdrop of international economic uncertainties and financial volatility. Rao highlighted that India?s financial system is well-equipped to handle external shocks due to its solid regulatory framework and prudent risk management practices. The country?s banking sector has demonstrated resilience throug..

Next Story
Infrastructure Energy

SC Allows State Tax on Mines, Minerals

Opposition leaders have welcomed the Supreme Court's recent decision permitting states to levy taxes on mines and mineral-bearing lands, as reported. The ruling is seen as a significant victory for state governments seeking greater control and revenue from natural resource extraction within their jurisdictions. The Supreme Court?s decision empowers states to impose taxes on mining operations and mineral-rich lands, which could enhance their revenue streams and enable better management of local resources. This move is particularly important for states with substantial mineral resources, as it a..

Talk to us?