KERC okays Rs 8.40 per kWh tariff for Cambria Solar PPA with BESCOM
POWER & RENEWABLE ENERGY

KERC okays Rs 8.40 per kWh tariff for Cambria Solar PPA with BESCOM

The Karnataka Electricity Regulatory Commission (KERC) has given its nod for a tariff of Rs 8.40 per kWh as per the power purchase agreement (PPA) signed between Bangalore Electricity Supply Company Ltd (BESCOM) and the developer of the project—Cambria Solar.

KERC also approved the extension of six months granted by BESCOM for the commissioning date of the solar project.

Cambria Solar had filed a petition requesting the KERC to approve the extension of six months granted by BESCOM to the scheduled commercial operation date (SCOD) as agreed between the parties. It had also requested the regulator to approve the tariff of Rs 8.40 per kWh from the project’s commercial operation date for the whole term of the PPA.

A land-owning farmer, Gangaraju, had applied for a 3 MW solar power project under the solar program initiated by the Karnataka Renewable Energy Development Ltd (KREDL). The project was allotted to him.

BESCOM, in its meeting held in July 2015, gave consent for the purchase of solar power from the project. Both the parties signed the PPA in the same month, and subsequently, the PPA was approved by the KERC in August 2015.

As per the PPA, the scheduled date of completion was to be achieved within 18 months from the PPA signing. The power to extend the time for commissioning was vested with BESCOM.

According to the PPA, the project promoter had the right to form a special purpose vehicle (SPV) after the PPA execution. Accordingly, Cambria Solar was incorporated as an SPV.

The developer informed BESCOM in November 2016 that it had applied for the bay allocation from the Karnataka Power Transmission Corporation Limited (KPTCL) but had not received the bay allotment due to augmentation of the transformer at 66/11 KV Moregere Substation.

The developer sought an extension of six months from January 6, 2017, which it perceived to be the SCOD. KPTCL granted evacuation approval to the petitioner.

Later, BESCOM granted an extension of six months from the SCOD as per the PPA, subject to the bank guarantee extension. The developer said it was entitled to a tariff of Rs 8.40 per kWh, according to the PPA.

BESCOM, in its submission, said that as the developer was unable to execute the project on time, a letter was addressed to it seeking an extension of time for commissioning the project.

The Karnataka government issued an order in November 2016, directing all the electricity supply companies (escoms) to constitute a three-member committee to consider and dispose of the farmers’ and developers’ requests.

After detailed discussions, the committee suggested the approval be granted for the extension of SCOD for up to six months. According to KERC, it was not in dispute that PPA was executed on 7 July 2015, and the effective date meant the date of signing of the agreement by the parties, ie, 7 July 2015.

The regulator noted that in pursuance of the government’s direction, a three-member committee decided to approve an extension of SCOD by six months.

KERC noted that the developer had applied for power evacuation in September 2016, and KPTCL gave approval for evacuation in December 2016, after a lapse of more than two months.

BESCOM granted an extension by six months considering these facts and considering a substantial investment in the project.

The regulator noted that the petitioner was entitled to the tariff of Rs 8.40 per kWh from the commercial operation date because it had implemented the project within the extended time. Due to the ‘force majeure’ event, it could not commission the project within 18 months from the effective date.

Image Source


Also read: GESCOM invites bids for 10 MW rooftop solar net metering in Karnataka

The Karnataka Electricity Regulatory Commission (KERC) has given its nod for a tariff of Rs 8.40 per kWh as per the power purchase agreement (PPA) signed between Bangalore Electricity Supply Company Ltd (BESCOM) and the developer of the project—Cambria Solar. KERC also approved the extension of six months granted by BESCOM for the commissioning date of the solar project. Cambria Solar had filed a petition requesting the KERC to approve the extension of six months granted by BESCOM to the scheduled commercial operation date (SCOD) as agreed between the parties. It had also requested the regulator to approve the tariff of Rs 8.40 per kWh from the project’s commercial operation date for the whole term of the PPA. A land-owning farmer, Gangaraju, had applied for a 3 MW solar power project under the solar program initiated by the Karnataka Renewable Energy Development Ltd (KREDL). The project was allotted to him. BESCOM, in its meeting held in July 2015, gave consent for the purchase of solar power from the project. Both the parties signed the PPA in the same month, and subsequently, the PPA was approved by the KERC in August 2015. As per the PPA, the scheduled date of completion was to be achieved within 18 months from the PPA signing. The power to extend the time for commissioning was vested with BESCOM. According to the PPA, the project promoter had the right to form a special purpose vehicle (SPV) after the PPA execution. Accordingly, Cambria Solar was incorporated as an SPV. The developer informed BESCOM in November 2016 that it had applied for the bay allocation from the Karnataka Power Transmission Corporation Limited (KPTCL) but had not received the bay allotment due to augmentation of the transformer at 66/11 KV Moregere Substation. The developer sought an extension of six months from January 6, 2017, which it perceived to be the SCOD. KPTCL granted evacuation approval to the petitioner. Later, BESCOM granted an extension of six months from the SCOD as per the PPA, subject to the bank guarantee extension. The developer said it was entitled to a tariff of Rs 8.40 per kWh, according to the PPA. BESCOM, in its submission, said that as the developer was unable to execute the project on time, a letter was addressed to it seeking an extension of time for commissioning the project. The Karnataka government issued an order in November 2016, directing all the electricity supply companies (escoms) to constitute a three-member committee to consider and dispose of the farmers’ and developers’ requests. After detailed discussions, the committee suggested the approval be granted for the extension of SCOD for up to six months. According to KERC, it was not in dispute that PPA was executed on 7 July 2015, and the effective date meant the date of signing of the agreement by the parties, ie, 7 July 2015. The regulator noted that in pursuance of the government’s direction, a three-member committee decided to approve an extension of SCOD by six months. KERC noted that the developer had applied for power evacuation in September 2016, and KPTCL gave approval for evacuation in December 2016, after a lapse of more than two months. BESCOM granted an extension by six months considering these facts and considering a substantial investment in the project. The regulator noted that the petitioner was entitled to the tariff of Rs 8.40 per kWh from the commercial operation date because it had implemented the project within the extended time. Due to the ‘force majeure’ event, it could not commission the project within 18 months from the effective date. Image Source Also read: GESCOM invites bids for 10 MW rooftop solar net metering in Karnataka

Next Story
Real Estate

Serene, Gardencity to Develop Rs 3 Billion Senior Living Project in Bengaluru

Serene Communities, a leading senior living brand, has partnered with Gardencity Realty to develop a premium senior living community in Budigere, one of Bengaluru’s fastest-growing residential micro-markets. The project will span approximately 300,000 sq ft, with a Gross Development Value of about Rs 3 billion, and will add roughly 250 senior-friendly residences to the city’s growing retirement housing segment.The launch forms part of Serene Communities’ national expansion strategy. The company has 11 new projects under development with a planned investment of Rs 25 billion that will add..

Next Story
Real Estate

Alliance City Developers Marks Major 2025 Milestones in Vile Parle

Alliance City Developers Realtors has announced significant project milestones and expansions in 2025, underscoring what the company terms a transformational year. The developer completed multiple residential projects and launched two premium developments in Vile Parle (East), one of Mumbai’s most sought-after neighbourhoods.During the year, Alliance Legacy in Matunga (East) received its Occupancy Certificate (OC), while Alliance Eternis in Borivali (West) and Alliance Vista in Vile Parle (East) were granted Completion Certificates (CC), marking final project delivery. Alliance Abhimanyu is ..

Next Story
Infrastructure Energy

Moro Hub and PwC Middle East Partner to Accelerate Smart City Solutions

Moro Hub, a subsidiary of Digital DEWA, the digital arm of Dubai Electricity and Water Authority (DEWA), has announced a strategic collaboration with PwC Middle East to advance Smart City, Integrated Command Centre (ICC), Critical Infrastructure Monitoring and Internet of Things (IoT) initiatives across the region. The partnership brings together Moro Hub’s digital infrastructure and IoT capabilities with PwC’s global expertise in digital trust, smart city strategy and cybersecurity to support the UAE’s vision for intelligent and sustainable cities.“Our collaboration with PwC Middle Ea..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App