KREDL seeks consultancy for 500 MW Bidar Solar Park Project
POWER & RENEWABLE ENERGY

KREDL seeks consultancy for 500 MW Bidar Solar Park Project

KREDL, the Karnataka Renewable Energy Development Limited, has issued an invitation for consultancy firms to tender bids for the comprehensive planning of a 500 MW solar park in Bidar.

The deadline for bid submissions is September 14, 2023. Only bidders previously prequalified by the Karnataka government are eligible to participate in this bidding process.

The project's scope encompasses the creation of detailed project reports, feasibility studies, solar resource evaluations, energy production estimations, and the optimisation of plot dimensions, layouts, and infrastructure.

Bidders are required to furnish a bid security of Rs 50,000 ($602). The selected bidder must also provide a performance bank guarantee equal to 10% of the total contract value within four working days of receiving the order acceptance.

Upon receiving the letter of award, the chosen bidder must conclude and execute the contract agreement within seven days.

Initially, the consulting firm will craft a concise feasibility report to understand the project's business model. Afterward, in collaboration with KREDL, the consulting firm will present an initial draft of the solar park's detailed project report (DPR).

Once written approval is received from KREDL, the consulting firm is obligated to deliver the final DPR as per the specifications outlined in the request for proposal.

The timeline for deliverables, starting from the contract agreement date, is as follows: the draft feasibility report should be provided within four weeks, followed by the final feasibility report, expected within two weeks after receiving written feedback on the draft.

Subsequently, the draft DPR must be submitted within four weeks from the date of acceptance and approval of the feasibility report. Finally, the conclusive DPR is to be delivered within two weeks of KREDL's acceptance of the draft DPR.

The entire project should be completed within 12 weeks from the date of signing the contract agreement.

Failure to meet the established deadlines may result in penalties imposed by KREDL. These liquidated damages will amount to 0.5% of the contract price for each week of delay, with a maximum cap set at 10% of the total contract value.

Furthermore, if the cumulative penalty exceeds 10% of the contract value, KREDL reserves the right to terminate the contract without incurring any liability.

The bidding entity should operate as a single unit, with a team composed of personnel possessing the relevant qualifications and experience.

In January, KREDL invited bids for the installation and commissioning of grid-connected distributed solar power systems. This initiative aimed to solarise agricultural feeders covering 75,000 individual pump sets under Component C of the Pradhan Mantri Kisan Urja Suraksha evam Utthaan Mahabhiyan (PM-KUSUM) program.

KREDL, the Karnataka Renewable Energy Development Limited, has issued an invitation for consultancy firms to tender bids for the comprehensive planning of a 500 MW solar park in Bidar.The deadline for bid submissions is September 14, 2023. Only bidders previously prequalified by the Karnataka government are eligible to participate in this bidding process.The project's scope encompasses the creation of detailed project reports, feasibility studies, solar resource evaluations, energy production estimations, and the optimisation of plot dimensions, layouts, and infrastructure.Bidders are required to furnish a bid security of Rs 50,000 ($602). The selected bidder must also provide a performance bank guarantee equal to 10% of the total contract value within four working days of receiving the order acceptance.Upon receiving the letter of award, the chosen bidder must conclude and execute the contract agreement within seven days.Initially, the consulting firm will craft a concise feasibility report to understand the project's business model. Afterward, in collaboration with KREDL, the consulting firm will present an initial draft of the solar park's detailed project report (DPR).Once written approval is received from KREDL, the consulting firm is obligated to deliver the final DPR as per the specifications outlined in the request for proposal.The timeline for deliverables, starting from the contract agreement date, is as follows: the draft feasibility report should be provided within four weeks, followed by the final feasibility report, expected within two weeks after receiving written feedback on the draft.Subsequently, the draft DPR must be submitted within four weeks from the date of acceptance and approval of the feasibility report. Finally, the conclusive DPR is to be delivered within two weeks of KREDL's acceptance of the draft DPR.The entire project should be completed within 12 weeks from the date of signing the contract agreement.Failure to meet the established deadlines may result in penalties imposed by KREDL. These liquidated damages will amount to 0.5% of the contract price for each week of delay, with a maximum cap set at 10% of the total contract value.Furthermore, if the cumulative penalty exceeds 10% of the contract value, KREDL reserves the right to terminate the contract without incurring any liability.The bidding entity should operate as a single unit, with a team composed of personnel possessing the relevant qualifications and experience.In January, KREDL invited bids for the installation and commissioning of grid-connected distributed solar power systems. This initiative aimed to solarise agricultural feeders covering 75,000 individual pump sets under Component C of the Pradhan Mantri Kisan Urja Suraksha evam Utthaan Mahabhiyan (PM-KUSUM) program.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code