Maharashtra: MSEDCL invite bids for 431 MW solar electricity projects
POWER & RENEWABLE ENERGY

Maharashtra: MSEDCL invite bids for 431 MW solar electricity projects

Under Component-A of the Pradhan Mantri Kisan Urja Suraksha evam Utthan Mahabhiyan (PM KUSUM) initiative, the Maharashtra State Electricity Distribution Company Limited (MSEDCL) has invited bids for 431 MW of solar electricity from decentralised solar projects with capacities ranging from 500 kW to 2 MW.

The deadline for bid submissions is June 3, 2022. The tender has a ceiling tariff of 23.10/kWh established by MSEDCL.

The government plans to build 10,000 MW of grid-connected solar power plants with individual project sizes of up to 2 MW under Component A of the PM-KUSUM programme.

As an earnest money deposit, bidders must contribute $100,000 per MW.

Within 30 days of receiving the letter of award, the winning bidder must provide a performance bank guarantee in the amount of 500,000 per MW.

The chosen bidders will engage in power purchase agreements (PPAs) with MSEDCL for 25 years from the start of commercial operation.

To prevent the high cost of sub-transmission lines and reduce transmission losses, solar power projects will be placed within a five-kilometre radius of substations.

To reduce technological risk and ensure project commissioning on schedule, only commercially established and operational technologies can be chosen.

Construction projects that have not yet been commissioned, and projects that have been commissioned but have no long-term PPA with any agency and are selling electricity on a short-term or merchant plant basis would be eligible.

Bidders can participate as an individual or as a group of farmers, cooperatives, panchayats, farmer producer associations, or water user organisations, and the project can be built upon their land.

If bidders can't come up with the money, they can put up the projects by signing a land leasing arrangement with a developer.

The annual lease rate to be paid to the landowner will be $730,000 per acre, with a 3% annual increase. The leasing deal would last between 26 and 30 years, as both sides have agreed.

Individual farmers, farmer groups, cooperatives, panchayats, farmer producer organisations, water user associations, and farmers establishing the project on their lands are excluded from the financial qualifying criteria.

If the project is to be built on leased property, the bidder's net worth must be at least $10 million. The bidder's yearly turnover should be at least $2.5 million.

As of the end day of the preceding financial year (FY), the developer must have an internal resource generating capability in the form of profit before depreciation, interest, and taxes for a minimum of 1 million of the quoted capacity.

To satisfy the working capital need, the developer should obtain an in-principle commitment from a financing institution pledging a Line of Credit for a minimum of 21.25 million of the stated capacity.

The project should be built to supply energy at the MSEDCL substation's 11/22 kV level. The selected bidder would be responsible for establishing grid connectivity with MSEDCL.

According to MSEDCL, the claimed capacity usage factor should not be less than 15% throughout the year.

Image Source

Also read: SJVN invites bid from consultants to draft DPR for solar projects

Under Component-A of the Pradhan Mantri Kisan Urja Suraksha evam Utthan Mahabhiyan (PM KUSUM) initiative, the Maharashtra State Electricity Distribution Company Limited (MSEDCL) has invited bids for 431 MW of solar electricity from decentralised solar projects with capacities ranging from 500 kW to 2 MW. The deadline for bid submissions is June 3, 2022. The tender has a ceiling tariff of 23.10/kWh established by MSEDCL. The government plans to build 10,000 MW of grid-connected solar power plants with individual project sizes of up to 2 MW under Component A of the PM-KUSUM programme. As an earnest money deposit, bidders must contribute $100,000 per MW. Within 30 days of receiving the letter of award, the winning bidder must provide a performance bank guarantee in the amount of 500,000 per MW. The chosen bidders will engage in power purchase agreements (PPAs) with MSEDCL for 25 years from the start of commercial operation. To prevent the high cost of sub-transmission lines and reduce transmission losses, solar power projects will be placed within a five-kilometre radius of substations. To reduce technological risk and ensure project commissioning on schedule, only commercially established and operational technologies can be chosen. Construction projects that have not yet been commissioned, and projects that have been commissioned but have no long-term PPA with any agency and are selling electricity on a short-term or merchant plant basis would be eligible. Bidders can participate as an individual or as a group of farmers, cooperatives, panchayats, farmer producer associations, or water user organisations, and the project can be built upon their land. If bidders can't come up with the money, they can put up the projects by signing a land leasing arrangement with a developer. The annual lease rate to be paid to the landowner will be $730,000 per acre, with a 3% annual increase. The leasing deal would last between 26 and 30 years, as both sides have agreed. Individual farmers, farmer groups, cooperatives, panchayats, farmer producer organisations, water user associations, and farmers establishing the project on their lands are excluded from the financial qualifying criteria. If the project is to be built on leased property, the bidder's net worth must be at least $10 million. The bidder's yearly turnover should be at least $2.5 million. As of the end day of the preceding financial year (FY), the developer must have an internal resource generating capability in the form of profit before depreciation, interest, and taxes for a minimum of 1 million of the quoted capacity. To satisfy the working capital need, the developer should obtain an in-principle commitment from a financing institution pledging a Line of Credit for a minimum of 21.25 million of the stated capacity. The project should be built to supply energy at the MSEDCL substation's 11/22 kV level. The selected bidder would be responsible for establishing grid connectivity with MSEDCL. According to MSEDCL, the claimed capacity usage factor should not be less than 15% throughout the year. Image Source Also read: SJVN invites bid from consultants to draft DPR for solar projects

Next Story
Infrastructure Energy

J&K CM Rules Out Power Privatisation, Focuses on Sector Reform

Jammu and Kashmir Chief Minister Omar Abdullah has dismissed speculation regarding privatisation of electricity in the Union Territory, emphasising that his priority is to strengthen and reform the power sector.“We are not discussing privatisation. By reducing losses, improving billing efficiency, and enhancing revenue, there will be no need for it. My vision is to strengthen and reform the power sector in J&K,” Abdullah stated.He addressed the gathering at the 58th Engineers’ Day at SKICC on Monday evening, an event honouring Bharat Ratna Sir M Visvesvaraya for his pioneering contri..

Next Story
Infrastructure Urban

Mumbai’s Sassoon Dock to Get Tech-Driven Modernisation with Finland

The Maharashtra government, in collaboration with Finland, will modernise Mumbai’s historic Sassoon Dock using advanced technology, state minister Nitesh Rane announced on Wednesday.Rane met a delegation of Finnish officials and representatives of Finnish companies at the dock to discuss strategic plans for upgrading the facility in south Mumbai, according to an official statement.Built in the 19th century, Sassoon Dock is one of Mumbai’s oldest and busiest fishing harbours. Operations currently exceed its original capacity, raising concerns over hygiene, odour, fish handling standards, an..

Next Story
Infrastructure Energy

Agarwal Industrial Wins Rs 3.3 Billion IOCL Bitumen Tender

Agarwal Industrial Corporation rose 3.84 per cent to Rs 945.65 after announcing it had secured a prestigious tender from Indian Oil Corporation (IOCL) worth Rs 3.3 billion.In a regulatory filing during market hours, the company confirmed it had won the tender to supply Bulk Bitumen (VG-30 and VG-40 grades) to IOCL’s Kakinada locations.The firm quantity under the award totals around 60,500 tonnes across 11 parcels, while the optional quantity is approximately 33,000 tonnes across six parcels. This brings the total awarded quantity to roughly 93,500 tonnes. At current market prices, the firm o..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?