+
Maharashtra: MSEDCL invite bids for 431 MW solar electricity projects
POWER & RENEWABLE ENERGY

Maharashtra: MSEDCL invite bids for 431 MW solar electricity projects

Under Component-A of the Pradhan Mantri Kisan Urja Suraksha evam Utthan Mahabhiyan (PM KUSUM) initiative, the Maharashtra State Electricity Distribution Company Limited (MSEDCL) has invited bids for 431 MW of solar electricity from decentralised solar projects with capacities ranging from 500 kW to 2 MW.

The deadline for bid submissions is June 3, 2022. The tender has a ceiling tariff of 23.10/kWh established by MSEDCL.

The government plans to build 10,000 MW of grid-connected solar power plants with individual project sizes of up to 2 MW under Component A of the PM-KUSUM programme.

As an earnest money deposit, bidders must contribute $100,000 per MW.

Within 30 days of receiving the letter of award, the winning bidder must provide a performance bank guarantee in the amount of 500,000 per MW.

The chosen bidders will engage in power purchase agreements (PPAs) with MSEDCL for 25 years from the start of commercial operation.

To prevent the high cost of sub-transmission lines and reduce transmission losses, solar power projects will be placed within a five-kilometre radius of substations.

To reduce technological risk and ensure project commissioning on schedule, only commercially established and operational technologies can be chosen.

Construction projects that have not yet been commissioned, and projects that have been commissioned but have no long-term PPA with any agency and are selling electricity on a short-term or merchant plant basis would be eligible.

Bidders can participate as an individual or as a group of farmers, cooperatives, panchayats, farmer producer associations, or water user organisations, and the project can be built upon their land.

If bidders can't come up with the money, they can put up the projects by signing a land leasing arrangement with a developer.

The annual lease rate to be paid to the landowner will be $730,000 per acre, with a 3% annual increase. The leasing deal would last between 26 and 30 years, as both sides have agreed.

Individual farmers, farmer groups, cooperatives, panchayats, farmer producer organisations, water user associations, and farmers establishing the project on their lands are excluded from the financial qualifying criteria.

If the project is to be built on leased property, the bidder's net worth must be at least $10 million. The bidder's yearly turnover should be at least $2.5 million.

As of the end day of the preceding financial year (FY), the developer must have an internal resource generating capability in the form of profit before depreciation, interest, and taxes for a minimum of 1 million of the quoted capacity.

To satisfy the working capital need, the developer should obtain an in-principle commitment from a financing institution pledging a Line of Credit for a minimum of 21.25 million of the stated capacity.

The project should be built to supply energy at the MSEDCL substation's 11/22 kV level. The selected bidder would be responsible for establishing grid connectivity with MSEDCL.

According to MSEDCL, the claimed capacity usage factor should not be less than 15% throughout the year.

Image Source

Also read: SJVN invites bid from consultants to draft DPR for solar projects

Under Component-A of the Pradhan Mantri Kisan Urja Suraksha evam Utthan Mahabhiyan (PM KUSUM) initiative, the Maharashtra State Electricity Distribution Company Limited (MSEDCL) has invited bids for 431 MW of solar electricity from decentralised solar projects with capacities ranging from 500 kW to 2 MW. The deadline for bid submissions is June 3, 2022. The tender has a ceiling tariff of 23.10/kWh established by MSEDCL. The government plans to build 10,000 MW of grid-connected solar power plants with individual project sizes of up to 2 MW under Component A of the PM-KUSUM programme. As an earnest money deposit, bidders must contribute $100,000 per MW. Within 30 days of receiving the letter of award, the winning bidder must provide a performance bank guarantee in the amount of 500,000 per MW. The chosen bidders will engage in power purchase agreements (PPAs) with MSEDCL for 25 years from the start of commercial operation. To prevent the high cost of sub-transmission lines and reduce transmission losses, solar power projects will be placed within a five-kilometre radius of substations. To reduce technological risk and ensure project commissioning on schedule, only commercially established and operational technologies can be chosen. Construction projects that have not yet been commissioned, and projects that have been commissioned but have no long-term PPA with any agency and are selling electricity on a short-term or merchant plant basis would be eligible. Bidders can participate as an individual or as a group of farmers, cooperatives, panchayats, farmer producer associations, or water user organisations, and the project can be built upon their land. If bidders can't come up with the money, they can put up the projects by signing a land leasing arrangement with a developer. The annual lease rate to be paid to the landowner will be $730,000 per acre, with a 3% annual increase. The leasing deal would last between 26 and 30 years, as both sides have agreed. Individual farmers, farmer groups, cooperatives, panchayats, farmer producer organisations, water user associations, and farmers establishing the project on their lands are excluded from the financial qualifying criteria. If the project is to be built on leased property, the bidder's net worth must be at least $10 million. The bidder's yearly turnover should be at least $2.5 million. As of the end day of the preceding financial year (FY), the developer must have an internal resource generating capability in the form of profit before depreciation, interest, and taxes for a minimum of 1 million of the quoted capacity. To satisfy the working capital need, the developer should obtain an in-principle commitment from a financing institution pledging a Line of Credit for a minimum of 21.25 million of the stated capacity. The project should be built to supply energy at the MSEDCL substation's 11/22 kV level. The selected bidder would be responsible for establishing grid connectivity with MSEDCL. According to MSEDCL, the claimed capacity usage factor should not be less than 15% throughout the year. Image Source Also read: SJVN invites bid from consultants to draft DPR for solar projects

Next Story
Infrastructure Urban

Flender Inaugurates Wind Gearbox Test Rig In Chennai

Chennai, 6 March 2026: Flender has inaugurated a 13.5 MW wind turbine gearbox test rig at its Walajabad facility near Chennai, marking the installation of the largest test rig of its kind in India. The facility was inaugurated on 5 March in the presence of Andreas Evertz, CEO, Flender Group; Lars Wiegemann, Vice President – Wind Gears; and Vinod Shetty, CEO, Flender India.The test rig has been developed to support testing and validation of wind turbine gearboxes, strengthening the company’s capabilities in the renewable energy sector. The commissioning was completed within three months thr..

Next Story
Infrastructure Energy

BMW Industries partners with IOCL for PNG supply at Bokaro plant

BMW Industries has entered into a strategic partnership with Indian Oil Corporation (IOCL) for the supply of Piped Natural Gas (PNG), reinforcing its commitment to adopting cleaner and more efficient energy sources for its operations.The agreement was signed at the Eastern Region Pipelines (ERPL) headquarters in Kolkata. The partnership is expected to support the company’s upcoming manufacturing facility in Bokaro by facilitating the use of natural gas as a primary energy source.According to the company, the adoption of PNG will help enhance operational efficiency while also contributing to ..

Next Story
Real Estate

Bombay Realty Secures RERA for Three ICC Tower in South Mumbai

Bombay Realty, the real estate arm of Bombay Dyeing and part of the Wadia Group, has received Real Estate Regulatory Authority (RERA) certification for Three ICC – Wing A, the latest luxury residential tower at Island City Center in Mumbai’s Dadar.The RERA registration marks a key milestone in the development timeline and reinforces the company’s focus on regulatory transparency, timely project delivery, and high construction standards.Following the success of One ICC and Two ICC, the upcoming Three ICC tower represents the next phase of the Island City Center development. The project ai..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement