MNRE Extends Timeline for Ultra Mega Solar Park Program
POWER & RENEWABLE ENERGY

MNRE Extends Timeline for Ultra Mega Solar Park Program

The 'Development of Solar Parks and Ultra Mega Solar Power Projects' programme now has a deadline of March 31, 2026 (FY 2026), as opposed to the former deadline of FY 2024, according to the Ministry of New and Renewable Energy (MNRE).

There are no financial consequences to the longer schedule. It occurs at a time when the construction of the solar power park has been extremely slow, with only nine of the 57 permitted solar parks completed as of February 2023 and an additional eight halfway installed, with a combined capacity of 10,117 MW.

The programme, which was initially implemented in December 2014, was launched with the goal of establishing at least 25 solar parks and 20 GW ultra mega solar power plants within five years beginning with FY 2014–15.

In March 2017, the program's capacity was raised to 40 GW, and it was suggested that parks be constructed by FY 2023–2024.

In order to qualify for the programme, solar parks must have a capacity of 500 MW or more. Smaller parks are only taken into consideration in cases where there is a severe lack of contiguous or non- agricultural land.

The programme was put in place to promote the quick installation of grid-connected solar power projects for massive electricity production. As they addressed the issues of land acquisition and availability, solar parks were appealing. Solar parks have fewer potential legal problems and other obstacles, which makes them a financially viable choice for developers.

The 'Development of Solar Parks and Ultra Mega Solar Power Projects' programme now has a deadline of March 31, 2026 (FY 2026), as opposed to the former deadline of FY 2024, according to the Ministry of New and Renewable Energy (MNRE). There are no financial consequences to the longer schedule. It occurs at a time when the construction of the solar power park has been extremely slow, with only nine of the 57 permitted solar parks completed as of February 2023 and an additional eight halfway installed, with a combined capacity of 10,117 MW. The programme, which was initially implemented in December 2014, was launched with the goal of establishing at least 25 solar parks and 20 GW ultra mega solar power plants within five years beginning with FY 2014–15. In March 2017, the program's capacity was raised to 40 GW, and it was suggested that parks be constructed by FY 2023–2024. In order to qualify for the programme, solar parks must have a capacity of 500 MW or more. Smaller parks are only taken into consideration in cases where there is a severe lack of contiguous or non- agricultural land. The programme was put in place to promote the quick installation of grid-connected solar power projects for massive electricity production. As they addressed the issues of land acquisition and availability, solar parks were appealing. Solar parks have fewer potential legal problems and other obstacles, which makes them a financially viable choice for developers.

Next Story
Infrastructure Transport

Tamil Nadu Sets Compensation For Parandur Airport Land

The Tamil Nadu government has approved the compensation payable to landowners for the proposed second Chennai airport at Parandur in Kancheepuram district, fixing payments at between Rs 3.5 million and Rs 25.7 million per acre. The figures were calculated from guideline values, recent sale prices and state level negotiations, according to a government order issued on 25 June by the Industries, Investment Promotion and Commerce Department.Although officials insist the package sits “well above market price”, residents of thirteen affected villages—who have opposed the scheme si..

Next Story
Real Estate

Nirala World Plans Rs 10 Billion Mixed Use Duo in Noida

Real estate developer Nirala World will invest about Rs 10 billion in two mixed use schemes—Nirala Gateway in Sector 12 and Nirala Diadem in Sector 10—both in Greater Noida West. Each project covers roughly 10,600 square metres and will combine retail floors, office space and serviced studio apartments.Land acquisition is budgeted at around Rs 2 billion per project, while construction is estimated at Rs 3–3.5 billion for each site. More than 500 studio units, priced at about Rs 6.5 million apiece, will be managed by an international operator.Nirala World..

Next Story
Infrastructure Transport

Titagarh Wins Rs 4.31 Billion Order For Pune Metro Trains

Shares of Titagarh Rail Systems advanced on Monday after the company announced a fresh contract for the Pune Metro Rail Project. The stock touched an intraday high of Rs 961.80 on the NSE, up 2.72 per cent, before easing to Rs 949.20—still 1.37 per cent above Friday’s close.In a regulatory filing, the consortium of Titagarh Rail Systems and its associate, Titagarh Firema S.p.A., said it had received a Letter of Approval from Maharashtra Metro Rail Corporation Ltd for the supply of 12 additional electric multiple unit trainsets. The order, issued under a quanti..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?