MNRE Extends Timeline for Ultra Mega Solar Park Program
POWER & RENEWABLE ENERGY

MNRE Extends Timeline for Ultra Mega Solar Park Program

The 'Development of Solar Parks and Ultra Mega Solar Power Projects' programme now has a deadline of March 31, 2026 (FY 2026), as opposed to the former deadline of FY 2024, according to the Ministry of New and Renewable Energy (MNRE).

There are no financial consequences to the longer schedule. It occurs at a time when the construction of the solar power park has been extremely slow, with only nine of the 57 permitted solar parks completed as of February 2023 and an additional eight halfway installed, with a combined capacity of 10,117 MW.

The programme, which was initially implemented in December 2014, was launched with the goal of establishing at least 25 solar parks and 20 GW ultra mega solar power plants within five years beginning with FY 2014–15.

In March 2017, the program's capacity was raised to 40 GW, and it was suggested that parks be constructed by FY 2023–2024.

In order to qualify for the programme, solar parks must have a capacity of 500 MW or more. Smaller parks are only taken into consideration in cases where there is a severe lack of contiguous or non- agricultural land.

The programme was put in place to promote the quick installation of grid-connected solar power projects for massive electricity production. As they addressed the issues of land acquisition and availability, solar parks were appealing. Solar parks have fewer potential legal problems and other obstacles, which makes them a financially viable choice for developers.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The 'Development of Solar Parks and Ultra Mega Solar Power Projects' programme now has a deadline of March 31, 2026 (FY 2026), as opposed to the former deadline of FY 2024, according to the Ministry of New and Renewable Energy (MNRE). There are no financial consequences to the longer schedule. It occurs at a time when the construction of the solar power park has been extremely slow, with only nine of the 57 permitted solar parks completed as of February 2023 and an additional eight halfway installed, with a combined capacity of 10,117 MW. The programme, which was initially implemented in December 2014, was launched with the goal of establishing at least 25 solar parks and 20 GW ultra mega solar power plants within five years beginning with FY 2014–15. In March 2017, the program's capacity was raised to 40 GW, and it was suggested that parks be constructed by FY 2023–2024. In order to qualify for the programme, solar parks must have a capacity of 500 MW or more. Smaller parks are only taken into consideration in cases where there is a severe lack of contiguous or non- agricultural land. The programme was put in place to promote the quick installation of grid-connected solar power projects for massive electricity production. As they addressed the issues of land acquisition and availability, solar parks were appealing. Solar parks have fewer potential legal problems and other obstacles, which makes them a financially viable choice for developers.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement