+
NUPPL Synchronises Unit-2 of Ghatampur Project
POWER & RENEWABLE ENERGY

NUPPL Synchronises Unit-2 of Ghatampur Project

Neyveli Uttar Pradesh Power Limited (NUPPL), a joint venture between NLC India Limited (51 per cent) and Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (49 per cent), has successfully completed the “TG Rolling & Synchronisation” of Unit-2 (660 MW) of its 1,980 MW Ghatampur Thermal Power Project. The unit was synchronised with the 765 kV grid at 00:05 hours today in a single attempt, well ahead of schedule following the completion of the steam blowing milestone.
This synchronisation represents a significant milestone in the path toward Commercial Operation Declaration (COD) and highlights NUPPL’s commitment to supplying 31.68 million units of reliable and sustainable electricity.
Commenting on the achievement, Shri Prasanna Kumar Motupalli, CMD of NLC India and Chairman of NUPPL, credited the coordinated efforts of NUPPL, NLCIL, UPRVUNL, the Ministry of Coal, and project contractors for enabling this success.
With Unit-1 already operational since December 2024, the successful synchronisation of Unit-2 marks another major step in project completion, with Unit-3 expected to be commissioned in FY 2025–26.
Located in Ghatampur Tehsil, Kanpur Nagar district, Uttar Pradesh, the Ghatampur Thermal Power Project comprises three supercritical thermal units of 660 MW each, totalling 1,980 MW. The project’s main plant boiler package is delivered by M/s LMBPL, the turbine by M/s GEPSIPL, and the Balance of Plant by M/s BGRESL. Power supply from the project is allocated with 75.12 per cent (1,487.28 MW) going to Uttar Pradesh and 24.88 per cent (492.72 MW) to Assam.
In parallel, NUPPL is progressing on the development of its fuel source—the Pachwara South Coal Block in Dumka District, Jharkhand—ensuring a sustainable coal supply for the plant.
The project’s advanced design incorporates supercritical technology and complies with stringent environmental norms through the use of Flue Gas Desulphurisation (FGD) and Selective Catalytic Reduction (SCR) systems, ensuring Zero Liquid Discharge.
With Unit-2 now synchronised, NUPPL is in the final phase of commissioning activities before declaring full commercial operation.

Neyveli Uttar Pradesh Power Limited (NUPPL), a joint venture between NLC India Limited (51 per cent) and Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (49 per cent), has successfully completed the “TG Rolling & Synchronisation” of Unit-2 (660 MW) of its 1,980 MW Ghatampur Thermal Power Project. The unit was synchronised with the 765 kV grid at 00:05 hours today in a single attempt, well ahead of schedule following the completion of the steam blowing milestone.This synchronisation represents a significant milestone in the path toward Commercial Operation Declaration (COD) and highlights NUPPL’s commitment to supplying 31.68 million units of reliable and sustainable electricity.Commenting on the achievement, Shri Prasanna Kumar Motupalli, CMD of NLC India and Chairman of NUPPL, credited the coordinated efforts of NUPPL, NLCIL, UPRVUNL, the Ministry of Coal, and project contractors for enabling this success.With Unit-1 already operational since December 2024, the successful synchronisation of Unit-2 marks another major step in project completion, with Unit-3 expected to be commissioned in FY 2025–26.Located in Ghatampur Tehsil, Kanpur Nagar district, Uttar Pradesh, the Ghatampur Thermal Power Project comprises three supercritical thermal units of 660 MW each, totalling 1,980 MW. The project’s main plant boiler package is delivered by M/s LMBPL, the turbine by M/s GEPSIPL, and the Balance of Plant by M/s BGRESL. Power supply from the project is allocated with 75.12 per cent (1,487.28 MW) going to Uttar Pradesh and 24.88 per cent (492.72 MW) to Assam.In parallel, NUPPL is progressing on the development of its fuel source—the Pachwara South Coal Block in Dumka District, Jharkhand—ensuring a sustainable coal supply for the plant.The project’s advanced design incorporates supercritical technology and complies with stringent environmental norms through the use of Flue Gas Desulphurisation (FGD) and Selective Catalytic Reduction (SCR) systems, ensuring Zero Liquid Discharge.With Unit-2 now synchronised, NUPPL is in the final phase of commissioning activities before declaring full commercial operation.

Next Story
Infrastructure Transport

MMRDA Installs 325-Tonne Steel Spans on Mumbai Metro Line 4

The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a key construction milestone on Metro Line 4 with the successful installation of three large steel spans at Bhandup West during overnight operations.The spans, together weighing 325 metric tonnes, were launched using eight heavy-duty cranes and 12 multi-axle vehicles. The operation required precise engineering and meticulous planning to minimise disruption in the densely populated suburban area.Due to effective inter-agency coordination, the work—originally scheduled across four nights—was completed within just two n..

Next Story
Infrastructure Transport

CMRL Targets March 2027 Opening for Vadapalani–Panagal Park

Chennai Metro Rail Limited (CMRL) is progressing as scheduled to open the Vadapalani–Panagal Park section of Phase II’s Corridor 4 by March 2027. The 3.5 km underground stretch is part of the 26.1 km Corridor 4 connecting Lighthouse with Poonamallee Bypass.Construction activities are advancing steadily, with tunnelling works between Vadapalani and Panagal Park already completed. Track-laying operations are expected to commence shortly. At Panagal Park station, structural works have reached the concourse and platform levels, while excavation continues at the lowest level.CMRL is also consid..

Next Story
Infrastructure Transport

Maha-Metro Invites Pune Metro Civil Maintenance Bids

Maharashtra Metro Rail Corporation Limited (Maha-Metro) has invited bids for the annual civil maintenance contract of the Pune Metro Rail Project. The tender, bearing ID and number P1-O&M-20/2025, is scheduled to close on 23 February 2026, with a pre-bid meeting slated for 10 February 2026. The earnest money deposit (EMD) for the contract is Rs 3,50,500, and the duration of the contract is one year.The scope of work includes annual civil maintenance of 28 elevated and underground stations, 28.079 km of elevated viaduct including steel bridges, 12.15 km of tunnels, and two depots under the ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App