Only 12 Per Cent of TBCB Transmission Projects Met SCOD
POWER & RENEWABLE ENERGY

Only 12 Per Cent of TBCB Transmission Projects Met SCOD

A latest report by ICRA has highlighted a mismatch between the rapid growth in renewable energy projects and the pace of associated transmission infrastructure development. It found that out of the total projects commissioned by March 2026 under the tariff-based competitive bidding route only 12 per cent met their scheduled commissioning date, while the remainder were commissioned with delays ranging from two months to three years and a median delay of over ten months. The agency warned that such delays increase the risk of inadequate power evacuation and grid curtailment for developers.

The rating agency projects capital expenditure of Rs. five to six trillion (tn) between FY2026-27 and FY2031-32 to strengthen existing infrastructure, add evacuation capacity and develop new transmission routes. ICRA noted that the investment requirement is driven by the Government plan to evacuate power from over 900 GW of non-fossil fuel capacity by 2035-36, of which around 548 GW is expected to be solar and wind. It added that land acquisition and right of way constraints remain key execution challenges that could delay project completion timelines.

ICRA reported that around 33 per cent of recently commissioned renewable capacity was being evacuated under the Temporary General Network Access route as of May 2026, reflecting persistent transmission constraints. Curtailment under T-GNA was highest during solar hours and remained in the range of 50 to 60 per cent in affected regions, particularly Rajasthan and Gujarat, while southern regions experienced limited curtailment. The agency also noted that outstanding orders and inflows for transmission equipment suppliers more than doubled in FY2025-26 versus FY2021-22, but supply and labour constraints persist.

To bridge the gap ICRA estimated the sector needs a significant increase in annual transmission line and substation capacity additions of about 20,000 circuit kilometres and 120 gigavolt-amperes (GVA), implying an investment opportunity of at least Rs. five to six tn between 2026-27 and 2031-32. It warned that slippages in commissioning of planned transmission infrastructure could impede renewable capacity additions or prolong grid curtailment, materially affecting project returns unless execution bottlenecks are addressed.

A latest report by ICRA has highlighted a mismatch between the rapid growth in renewable energy projects and the pace of associated transmission infrastructure development. It found that out of the total projects commissioned by March 2026 under the tariff-based competitive bidding route only 12 per cent met their scheduled commissioning date, while the remainder were commissioned with delays ranging from two months to three years and a median delay of over ten months. The agency warned that such delays increase the risk of inadequate power evacuation and grid curtailment for developers. The rating agency projects capital expenditure of Rs. five to six trillion (tn) between FY2026-27 and FY2031-32 to strengthen existing infrastructure, add evacuation capacity and develop new transmission routes. ICRA noted that the investment requirement is driven by the Government plan to evacuate power from over 900 GW of non-fossil fuel capacity by 2035-36, of which around 548 GW is expected to be solar and wind. It added that land acquisition and right of way constraints remain key execution challenges that could delay project completion timelines. ICRA reported that around 33 per cent of recently commissioned renewable capacity was being evacuated under the Temporary General Network Access route as of May 2026, reflecting persistent transmission constraints. Curtailment under T-GNA was highest during solar hours and remained in the range of 50 to 60 per cent in affected regions, particularly Rajasthan and Gujarat, while southern regions experienced limited curtailment. The agency also noted that outstanding orders and inflows for transmission equipment suppliers more than doubled in FY2025-26 versus FY2021-22, but supply and labour constraints persist. To bridge the gap ICRA estimated the sector needs a significant increase in annual transmission line and substation capacity additions of about 20,000 circuit kilometres and 120 gigavolt-amperes (GVA), implying an investment opportunity of at least Rs. five to six tn between 2026-27 and 2031-32. It warned that slippages in commissioning of planned transmission infrastructure could impede renewable capacity additions or prolong grid curtailment, materially affecting project returns unless execution bottlenecks are addressed.

Related Stories

Gold Stories

Next Story
Products

Walplast reports strong Q1 growth

Walplast Products has reported strong year-on-year growth across key categories in its HomeSure portfolio during the April–June 2026 quarter, driven by product expansion, manufacturing capabilities and wider distribution.HomeSure GypEx Walbond recorded the highest growth at 157 per cent, followed by HomeSure GypEx Gypsum Plaster at 97 per cent and HomeSure TileEx Tile Adhesive at 75 per cent. Textures grew by 55 per cent, while HomeSure Wall Putty and HomeSure TileEx Tile Cleaner recorded 40 per cent growth each. HomeSure TileEx Cementitious Tile Grout grew by 25 per cent.The company has exp..

Next Story
Technology

Matrix Geo completes 314-km highway survey

Matrix Geo Solutions has completed a geospatial survey assignment covering approximately 314 km across five highway sections under LOT-2/HARYANA/Package-1 for RITES, on behalf of the National Highways Authority of India.The assignment formed part of consultancy services for preparing Detailed Project Reports for economic corridors, inter-corridor and feeder routes. The scope included Aerial and Mobile LiDAR surveys, UAV-based topographic mapping, Ground Penetrating Radar utility mapping, Final Location Survey, land acquisition support and digitisation of cadastral maps.The five sections covere..

Next Story
Real Estate

Sugee enters Thane with Lake District

Sugee Group has announced its entry into the Thane market with Sugee Lake District, a 52-acre waterfront development in Thane West that will bring together commercial, retail, hospitality and lifestyle spaces.Located opposite Korum Mall near Cadbury Junction in Khopat, the Eastern Express Highway-facing development will feature Grade A++ office spaces with views of Siddheshwar Lake and the city. The project will also include high-street retail, dining and a six-acre lakeview promenade.The development has been registered under the LEED green building rating system and has been designed by Archi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement