Only 12 Per Cent of TBCB Transmission Projects Met SCOD
POWER & RENEWABLE ENERGY

Only 12 Per Cent of TBCB Transmission Projects Met SCOD

A latest report by ICRA has highlighted a mismatch between the rapid growth in renewable energy projects and the pace of associated transmission infrastructure development. It found that out of the total projects commissioned by March 2026 under the tariff-based competitive bidding route only 12 per cent met their scheduled commissioning date, while the remainder were commissioned with delays ranging from two months to three years and a median delay of over ten months. The agency warned that such delays increase the risk of inadequate power evacuation and grid curtailment for developers.

The rating agency projects capital expenditure of Rs. five to six trillion (tn) between FY2026-27 and FY2031-32 to strengthen existing infrastructure, add evacuation capacity and develop new transmission routes. ICRA noted that the investment requirement is driven by the Government plan to evacuate power from over 900 GW of non-fossil fuel capacity by 2035-36, of which around 548 GW is expected to be solar and wind. It added that land acquisition and right of way constraints remain key execution challenges that could delay project completion timelines.

ICRA reported that around 33 per cent of recently commissioned renewable capacity was being evacuated under the Temporary General Network Access route as of May 2026, reflecting persistent transmission constraints. Curtailment under T-GNA was highest during solar hours and remained in the range of 50 to 60 per cent in affected regions, particularly Rajasthan and Gujarat, while southern regions experienced limited curtailment. The agency also noted that outstanding orders and inflows for transmission equipment suppliers more than doubled in FY2025-26 versus FY2021-22, but supply and labour constraints persist.

To bridge the gap ICRA estimated the sector needs a significant increase in annual transmission line and substation capacity additions of about 20,000 circuit kilometres and 120 gigavolt-amperes (GVA), implying an investment opportunity of at least Rs. five to six tn between 2026-27 and 2031-32. It warned that slippages in commissioning of planned transmission infrastructure could impede renewable capacity additions or prolong grid curtailment, materially affecting project returns unless execution bottlenecks are addressed.

A latest report by ICRA has highlighted a mismatch between the rapid growth in renewable energy projects and the pace of associated transmission infrastructure development. It found that out of the total projects commissioned by March 2026 under the tariff-based competitive bidding route only 12 per cent met their scheduled commissioning date, while the remainder were commissioned with delays ranging from two months to three years and a median delay of over ten months. The agency warned that such delays increase the risk of inadequate power evacuation and grid curtailment for developers. The rating agency projects capital expenditure of Rs. five to six trillion (tn) between FY2026-27 and FY2031-32 to strengthen existing infrastructure, add evacuation capacity and develop new transmission routes. ICRA noted that the investment requirement is driven by the Government plan to evacuate power from over 900 GW of non-fossil fuel capacity by 2035-36, of which around 548 GW is expected to be solar and wind. It added that land acquisition and right of way constraints remain key execution challenges that could delay project completion timelines. ICRA reported that around 33 per cent of recently commissioned renewable capacity was being evacuated under the Temporary General Network Access route as of May 2026, reflecting persistent transmission constraints. Curtailment under T-GNA was highest during solar hours and remained in the range of 50 to 60 per cent in affected regions, particularly Rajasthan and Gujarat, while southern regions experienced limited curtailment. The agency also noted that outstanding orders and inflows for transmission equipment suppliers more than doubled in FY2025-26 versus FY2021-22, but supply and labour constraints persist. To bridge the gap ICRA estimated the sector needs a significant increase in annual transmission line and substation capacity additions of about 20,000 circuit kilometres and 120 gigavolt-amperes (GVA), implying an investment opportunity of at least Rs. five to six tn between 2026-27 and 2031-32. It warned that slippages in commissioning of planned transmission infrastructure could impede renewable capacity additions or prolong grid curtailment, materially affecting project returns unless execution bottlenecks are addressed.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code