Only 12 Per Cent of TBCB Transmission Projects Met SCOD
POWER & RENEWABLE ENERGY

Only 12 Per Cent of TBCB Transmission Projects Met SCOD

A latest report by ICRA has highlighted a mismatch between the rapid growth in renewable energy projects and the pace of associated transmission infrastructure development. It found that out of the total projects commissioned by March 2026 under the tariff-based competitive bidding route only 12 per cent met their scheduled commissioning date, while the remainder were commissioned with delays ranging from two months to three years and a median delay of over ten months. The agency warned that such delays increase the risk of inadequate power evacuation and grid curtailment for developers.

The rating agency projects capital expenditure of Rs. five to six trillion (tn) between FY2026-27 and FY2031-32 to strengthen existing infrastructure, add evacuation capacity and develop new transmission routes. ICRA noted that the investment requirement is driven by the Government plan to evacuate power from over 900 GW of non-fossil fuel capacity by 2035-36, of which around 548 GW is expected to be solar and wind. It added that land acquisition and right of way constraints remain key execution challenges that could delay project completion timelines.

ICRA reported that around 33 per cent of recently commissioned renewable capacity was being evacuated under the Temporary General Network Access route as of May 2026, reflecting persistent transmission constraints. Curtailment under T-GNA was highest during solar hours and remained in the range of 50 to 60 per cent in affected regions, particularly Rajasthan and Gujarat, while southern regions experienced limited curtailment. The agency also noted that outstanding orders and inflows for transmission equipment suppliers more than doubled in FY2025-26 versus FY2021-22, but supply and labour constraints persist.

To bridge the gap ICRA estimated the sector needs a significant increase in annual transmission line and substation capacity additions of about 20,000 circuit kilometres and 120 gigavolt-amperes (GVA), implying an investment opportunity of at least Rs. five to six tn between 2026-27 and 2031-32. It warned that slippages in commissioning of planned transmission infrastructure could impede renewable capacity additions or prolong grid curtailment, materially affecting project returns unless execution bottlenecks are addressed.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

A latest report by ICRA has highlighted a mismatch between the rapid growth in renewable energy projects and the pace of associated transmission infrastructure development. It found that out of the total projects commissioned by March 2026 under the tariff-based competitive bidding route only 12 per cent met their scheduled commissioning date, while the remainder were commissioned with delays ranging from two months to three years and a median delay of over ten months. The agency warned that such delays increase the risk of inadequate power evacuation and grid curtailment for developers. The rating agency projects capital expenditure of Rs. five to six trillion (tn) between FY2026-27 and FY2031-32 to strengthen existing infrastructure, add evacuation capacity and develop new transmission routes. ICRA noted that the investment requirement is driven by the Government plan to evacuate power from over 900 GW of non-fossil fuel capacity by 2035-36, of which around 548 GW is expected to be solar and wind. It added that land acquisition and right of way constraints remain key execution challenges that could delay project completion timelines. ICRA reported that around 33 per cent of recently commissioned renewable capacity was being evacuated under the Temporary General Network Access route as of May 2026, reflecting persistent transmission constraints. Curtailment under T-GNA was highest during solar hours and remained in the range of 50 to 60 per cent in affected regions, particularly Rajasthan and Gujarat, while southern regions experienced limited curtailment. The agency also noted that outstanding orders and inflows for transmission equipment suppliers more than doubled in FY2025-26 versus FY2021-22, but supply and labour constraints persist. To bridge the gap ICRA estimated the sector needs a significant increase in annual transmission line and substation capacity additions of about 20,000 circuit kilometres and 120 gigavolt-amperes (GVA), implying an investment opportunity of at least Rs. five to six tn between 2026-27 and 2031-32. It warned that slippages in commissioning of planned transmission infrastructure could impede renewable capacity additions or prolong grid curtailment, materially affecting project returns unless execution bottlenecks are addressed.

Next Story
Infrastructure Transport

Bhogapuram Airport Set For Take Off After Licence Issued

Union Civil Aviation Minister Kinjarapu Ram Mohan Naidu announced that Alluri Sitharama Raju Bhogapuram International Airport has achieved 100 per cent completion following issuance of its aerodrome licence by the Ministry of Civil Aviation after an inspection with public representatives, district officials and GMR Group representatives. The licence was granted after extensive verification over the past month to ensure that safety and operational standards were met. The Chief Minister's Office has already contacted the Prime Minister's Office to finalise an inauguration date and commercial fli..

Next Story
Infrastructure Urban

Auto Sector To Grow 22-24 Per Cent In Q1 FY27

Credit Rating Information Services of India (Crisil) estimated that India's automobile sector is expected to report revenue growth of 22-24 per cent year-on-year in the first quarter of FY27 and to be among the largest contributors to corporate revenue growth in the quarter. The agency estimated overall corporate revenue to have grown 11-11.5 per cent year-on-year in the quarter ended 30 June 2026, the fastest pace in two years despite supply chain disruptions and higher input costs from the West Asia conflict. This compared with growth of 9.6 per cent in the preceding quarter. Crisil said the..

Next Story
Infrastructure Urban

Nomura Sees Q1 Pressure On Cement Margins; Backs Major Players

Nomura said cement margins will be under pressure in the June quarter as fuel and packaging costs rose, although volume growth is expected to remain healthy. The brokerage forecast six to seven per cent year-on-year organic volume growth for the Indian cement industry in the period, with Shree Cement identified as likely to post the highest growth at 15 per cent year-on-year. It noted that the West and North regions outperformed on pricing, aiding companies with greater exposure in those markets. Average trade prices improved three per cent sequentially to around Rs 326 per bag after price inc..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement