Power crisis looms over Odisha
POWER & RENEWABLE ENERGY

Power crisis looms over Odisha

As the 460 MW Talcher Thermal Power Station (TTPS) of NTPC faces shutdown from 1 January 2021 for failing to follow the environmental standards set down by the Central Pollution Control Board (CPCB), Odisha could be moving towards a big power crisis from the beginning of 2021.

An ultimatum was given by the CPCB to the old power plants to take appropriate measures to reform themselves and comply with emission standards, including solid particulate matter (SPM), sulphur and nitrogen content. Power plants unable to fulfil these criteria would be closed as of December 31 this year.

The cost of fulfilling these requirements set by CPCB is around Rs 50 lakh per MW. Hence, fixing the deficiencies would have cost TTPS a considerable amount of Rs 23,000 crore. Therefore in 2018, it decided to replace its old plant with two new plants of 660 MW each. But the state government has remained a huge obstacle.

While the contract for the Rs 9,000 crore project was given the same year, the project approval was postponed by the state government until February of this year. Sources said that now it is too late for TTPS to introduce the programme, and disinterest from NTPC in the project has only made the situation worse.

Development of TTPS happened in two phases. Four units of 60 MW each were established in 1968, and two additional 110 MW units followed in 1982. Initially, the plant was operated by the former Orissa State Electricity Board.

Later, it was sold to NTPC in 1995, when Biju Patnaik was the CM, due less than 15 per cent load factor and losses. In 2000, NTPC invested extensively in the plant for reconstruction and modernisation, and its life was set by the Central Electricity Authority up to March 2021.

Although in the meantime, CPCB came up with new regulations that have put TTPS in a problematic situation. A top TTPS official, however, sounded optimistic. He said there is an ultimatum, but they are hopeful of its extension beyond the end of the current year.

Source- New Indian Express

As the 460 MW Talcher Thermal Power Station (TTPS) of NTPC faces shutdown from 1 January 2021 for failing to follow the environmental standards set down by the Central Pollution Control Board (CPCB), Odisha could be moving towards a big power crisis from the beginning of 2021.An ultimatum was given by the CPCB to the old power plants to take appropriate measures to reform themselves and comply with emission standards, including solid particulate matter (SPM), sulphur and nitrogen content. Power plants unable to fulfil these criteria would be closed as of December 31 this year. The cost of fulfilling these requirements set by CPCB is around Rs 50 lakh per MW. Hence, fixing the deficiencies would have cost TTPS a considerable amount of Rs 23,000 crore. Therefore in 2018, it decided to replace its old plant with two new plants of 660 MW each. But the state government has remained a huge obstacle. While the contract for the Rs 9,000 crore project was given the same year, the project approval was postponed by the state government until February of this year. Sources said that now it is too late for TTPS to introduce the programme, and disinterest from NTPC in the project has only made the situation worse. Development of TTPS happened in two phases. Four units of 60 MW each were established in 1968, and two additional 110 MW units followed in 1982. Initially, the plant was operated by the former Orissa State Electricity Board.Later, it was sold to NTPC in 1995, when Biju Patnaik was the CM, due less than 15 per cent load factor and losses. In 2000, NTPC invested extensively in the plant for reconstruction and modernisation, and its life was set by the Central Electricity Authority up to March 2021. Although in the meantime, CPCB came up with new regulations that have put TTPS in a problematic situation. A top TTPS official, however, sounded optimistic. He said there is an ultimatum, but they are hopeful of its extension beyond the end of the current year. Source- New Indian Express

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train Set to Launch by 2028

India’s first bullet train is set to revolutionize high-speed travel along the western corridor, with the Mumbai-Ahmedabad high-speed rail project aiming for a 2028 launch. This announcement marks a major milestone in India’s infrastructure goals, as it promises to reduce travel time between the two economic hubs from eight hours to just three.Spanning a planned 508-kilometre stretch, the corridor stands as a flagship example of Indo-Japanese collaboration in technology and engineering. Once operational, the train is expected to transform intercity mobility and place India among the select..

Next Story
Infrastructure Transport

Mumbai-Gandhinagar Train Service Enhances Passenger Capacity

The Mumbai Central–Gandhinagar Capital Vande Bharat Express has increased its passenger capacity by adding four additional AC chair car coaches to meet the growing commuter demand on one of India’s busiest business corridors. This upgrade, effective from 11 May, raised the train’s seating capacity from 1,128 to 1,440 passengers, allowing it to serve 936 more passengers daily in both directions. The increase was described as a practical measure to accommodate the surging demand on the busy Mumbai–Ahmedabad–Gandhinagar route, which regularly operates at over 150 percent seat occupancy...

Next Story
Infrastructure Urban

Delhi Plans 12 Sewage Plants to Clean Najafgarh Drain Efficiently

Delhi’s ambitious plan to improve the water quality of the Yamuna River has gained significant momentum as the Delhi Jal Board (DJB) has begun work on 12 new sewage treatment plants (STPs) aimed at reducing the volume of untreated sewage being discharged from the Najafgarh Drain.This initiative forms part of the ongoing efforts to clean the Yamuna and restore the river’s health, which has long been a critical environmental issue for the national capital. Given the alarming pollution levels in the Yamuna, experts and officials consider this project a vital step toward addressing the persist..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?