+
Power crisis looms over Odisha
POWER & RENEWABLE ENERGY

Power crisis looms over Odisha

As the 460 MW Talcher Thermal Power Station (TTPS) of NTPC faces shutdown from 1 January 2021 for failing to follow the environmental standards set down by the Central Pollution Control Board (CPCB), Odisha could be moving towards a big power crisis from the beginning of 2021.

An ultimatum was given by the CPCB to the old power plants to take appropriate measures to reform themselves and comply with emission standards, including solid particulate matter (SPM), sulphur and nitrogen content. Power plants unable to fulfil these criteria would be closed as of December 31 this year.

The cost of fulfilling these requirements set by CPCB is around Rs 50 lakh per MW. Hence, fixing the deficiencies would have cost TTPS a considerable amount of Rs 23,000 crore. Therefore in 2018, it decided to replace its old plant with two new plants of 660 MW each. But the state government has remained a huge obstacle.

While the contract for the Rs 9,000 crore project was given the same year, the project approval was postponed by the state government until February of this year. Sources said that now it is too late for TTPS to introduce the programme, and disinterest from NTPC in the project has only made the situation worse.

Development of TTPS happened in two phases. Four units of 60 MW each were established in 1968, and two additional 110 MW units followed in 1982. Initially, the plant was operated by the former Orissa State Electricity Board.

Later, it was sold to NTPC in 1995, when Biju Patnaik was the CM, due less than 15 per cent load factor and losses. In 2000, NTPC invested extensively in the plant for reconstruction and modernisation, and its life was set by the Central Electricity Authority up to March 2021.

Although in the meantime, CPCB came up with new regulations that have put TTPS in a problematic situation. A top TTPS official, however, sounded optimistic. He said there is an ultimatum, but they are hopeful of its extension beyond the end of the current year.

Source- New Indian Express

As the 460 MW Talcher Thermal Power Station (TTPS) of NTPC faces shutdown from 1 January 2021 for failing to follow the environmental standards set down by the Central Pollution Control Board (CPCB), Odisha could be moving towards a big power crisis from the beginning of 2021.An ultimatum was given by the CPCB to the old power plants to take appropriate measures to reform themselves and comply with emission standards, including solid particulate matter (SPM), sulphur and nitrogen content. Power plants unable to fulfil these criteria would be closed as of December 31 this year. The cost of fulfilling these requirements set by CPCB is around Rs 50 lakh per MW. Hence, fixing the deficiencies would have cost TTPS a considerable amount of Rs 23,000 crore. Therefore in 2018, it decided to replace its old plant with two new plants of 660 MW each. But the state government has remained a huge obstacle. While the contract for the Rs 9,000 crore project was given the same year, the project approval was postponed by the state government until February of this year. Sources said that now it is too late for TTPS to introduce the programme, and disinterest from NTPC in the project has only made the situation worse. Development of TTPS happened in two phases. Four units of 60 MW each were established in 1968, and two additional 110 MW units followed in 1982. Initially, the plant was operated by the former Orissa State Electricity Board.Later, it was sold to NTPC in 1995, when Biju Patnaik was the CM, due less than 15 per cent load factor and losses. In 2000, NTPC invested extensively in the plant for reconstruction and modernisation, and its life was set by the Central Electricity Authority up to March 2021. Although in the meantime, CPCB came up with new regulations that have put TTPS in a problematic situation. A top TTPS official, however, sounded optimistic. He said there is an ultimatum, but they are hopeful of its extension beyond the end of the current year. Source- New Indian Express

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App