Power Min informs 39 hydro projects being implemented, 9 stalled
POWER & RENEWABLE ENERGY

Power Min informs 39 hydro projects being implemented, 9 stalled

39 hydro projects with a combined 14,623.5 MW of capacity are currently being built across the nation. Nine of these projects are inactive. R K Singh, Power Minister, informed that initiatives are being taken by the government and developers to restart the stalled projects in a written response to the Lok Sabha.

"39 hydroelectric projects (greater than 25 MW) totaling 14,623.5 MW are being built throughout the nation. Nine of these projects totaling 1,236 MW are now delayed (as of December 31, 2022), whereas 30 projects totaling 13,387.5 MW are under active construction and are expected to be completed by 2026–2027 "announced Singh.

According to him, CPSUs have undertaken a basin-wise indication of projects in order to accelerate the development of HEPs in the northeastern region.

There were a total of 211 HEPs operating in the nation as of December 31, 2022, with a combined installed capacity of 46,850.15 MW.

In a different response to the House, Singh stated that 30 big HEPs with a combined installed capacity of 11,137.50 MW are now being built in the Himalayan belt across several states in the nation.

Of them, seven HEPs totaling 756 MW are being held up, while 23 projects totaling 10,381.5 MW are currently under active construction.

Also read:
Mazagon Shipbuilders seek bids to maintain 1 MW of rooftop solar systems
Nirmala Sitharaman allots Rs 350 billion towards energy transition


39 hydro projects with a combined 14,623.5 MW of capacity are currently being built across the nation. Nine of these projects are inactive. R K Singh, Power Minister, informed that initiatives are being taken by the government and developers to restart the stalled projects in a written response to the Lok Sabha. 39 hydroelectric projects (greater than 25 MW) totaling 14,623.5 MW are being built throughout the nation. Nine of these projects totaling 1,236 MW are now delayed (as of December 31, 2022), whereas 30 projects totaling 13,387.5 MW are under active construction and are expected to be completed by 2026–2027 announced Singh. According to him, CPSUs have undertaken a basin-wise indication of projects in order to accelerate the development of HEPs in the northeastern region. There were a total of 211 HEPs operating in the nation as of December 31, 2022, with a combined installed capacity of 46,850.15 MW. In a different response to the House, Singh stated that 30 big HEPs with a combined installed capacity of 11,137.50 MW are now being built in the Himalayan belt across several states in the nation. Of them, seven HEPs totaling 756 MW are being held up, while 23 projects totaling 10,381.5 MW are currently under active construction. Also read: Mazagon Shipbuilders seek bids to maintain 1 MW of rooftop solar systems Nirmala Sitharaman allots Rs 350 billion towards energy transition

Next Story
Technology

AI-Enabled Workflows Lift Profitability and Productivity

Organisations modernising frontline workflows with artificial intelligence, automation and real-time data are reporting stronger financial performance, higher productivity and improved employee engagement, according to a global study by Zebra Technologies and Oxford Economics.The research covered 1,000 senior leaders across retail, manufacturing, transportation and logistics in the US, Mexico, the UK, Germany, India, Japan, Australia and New Zealand.In transportation and logistics, 54 per cent of companies that improved picking and packing operations reported faster operational performance, wh..

Next Story
Real Estate

India Leads Global AI Readiness but Implementation Lags

Indian companies lead global averages across all eight artificial intelligence readiness indicators tracked by JLL, but only 19 per cent have started making changes to their workplaces, according to the JLL 2026 Future of Work Survey.The study found that 77 per cent of Indian business leaders expect AI to change their office requirements, creating a 58-percentage-point gap between awareness and implementation. The survey covered more than 2,200 CEOs, CFOs and real estate leaders across 21 countries during the first quarter of 2026.Despite concerns over automation, 58 per cent of Indian leaders..

Next Story
Equipment

Three WOLFF Cranes Build Riyadh Cable-Stayed Bridges

Three WOLFF 180 B luffing jib cranes are supporting the construction of two cable-stayed bridges alongside the existing Wadi Laban Bridge in Riyadh, Saudi Arabia. The project is being developed for the Royal Commission for Riyadh City and executed by the ICRC joint venture comprising IC Ictas and Al Rashid Trading & Contracting Company.The cranes are handling lifting operations including formwork, reinforcement, concrete placement, work platforms, surveying equipment and other construction materials. Each crane is fitted with a 40 m jib, reaches a hook height of 157 m and offers a maximum ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement