+
RE Projects Face 60 Per Cent Solar-Hour Curtailment as RoW Delays Persist
POWER & RENEWABLE ENERGY

RE Projects Face 60 Per Cent Solar-Hour Curtailment as RoW Delays Persist

A report by Icra has found that critical delays in land acquisition and right-of-way (RoW) for transmission lines have left 33 per cent of India’s recently commissioned renewable energy capacity evacuated through temporary general network access as of May 2026, with curtailment during solar hours remaining as high as 50-60 per cent. The agency noted that these bottlenecks coincide with a planned transmission capex cycle of Rs 5-6 trillion (tn) between 2026-27 and 2031-32 intended to integrate additional capacity into the grid.

Icra said the capex is expected to support the government’s aim to evacuate more than 900 GW of non-fossil fuel capacity by 2035-36, including roughly 548 GW of solar and wind, and will involve strengthening existing infrastructure and adding new evacuation routes. The firm indicated that this scale of investment would also lift prospects for equipment suppliers as order inflows and outstanding orders have more than doubled since 2021-22.

To meet the targets set out in the earlier National Electricity Plan-II, Icra estimated the sector will require annual additions of about 20,000 circuit kilometres of transmission lines and 120 gigavolt-amperes of sub-station capacity, creating a significant investment opportunity in transmission equipment and services. The agency stressed that timely scaling up of manufacturing and project execution capacity will be vital to translate the pipeline into operational capacity.

Supply-side constraints could weigh on project timelines, with limited capacity of equipment manufacturers and shortages of skilled manpower likely to constrain execution unless participants scale up. Icra highlighted persistent execution risks linked to land acquisition, RoW and regulatory approvals; most projects awarded through tariff-based competitive bidding were delayed, with only about 12 per cent completed within the scheduled timeline and the remainder delayed by periods ranging from two months to three years and a median delay exceeding ten months.

The report warned that slippages in transmission commissioning are already feeding into curtailment episodes in regions with high renewable penetration, notably Rajasthan and Gujarat, while the southern region has seen more limited curtailment during solar hours. A pipeline of roughly 107 GW that has been granted connectivity is slated for integration between 2026-27 and 2030-31, and continued delays could impact renewable energy additions and materially affect project returns.

A report by Icra has found that critical delays in land acquisition and right-of-way (RoW) for transmission lines have left 33 per cent of India’s recently commissioned renewable energy capacity evacuated through temporary general network access as of May 2026, with curtailment during solar hours remaining as high as 50-60 per cent. The agency noted that these bottlenecks coincide with a planned transmission capex cycle of Rs 5-6 trillion (tn) between 2026-27 and 2031-32 intended to integrate additional capacity into the grid. Icra said the capex is expected to support the government’s aim to evacuate more than 900 GW of non-fossil fuel capacity by 2035-36, including roughly 548 GW of solar and wind, and will involve strengthening existing infrastructure and adding new evacuation routes. The firm indicated that this scale of investment would also lift prospects for equipment suppliers as order inflows and outstanding orders have more than doubled since 2021-22. To meet the targets set out in the earlier National Electricity Plan-II, Icra estimated the sector will require annual additions of about 20,000 circuit kilometres of transmission lines and 120 gigavolt-amperes of sub-station capacity, creating a significant investment opportunity in transmission equipment and services. The agency stressed that timely scaling up of manufacturing and project execution capacity will be vital to translate the pipeline into operational capacity. Supply-side constraints could weigh on project timelines, with limited capacity of equipment manufacturers and shortages of skilled manpower likely to constrain execution unless participants scale up. Icra highlighted persistent execution risks linked to land acquisition, RoW and regulatory approvals; most projects awarded through tariff-based competitive bidding were delayed, with only about 12 per cent completed within the scheduled timeline and the remainder delayed by periods ranging from two months to three years and a median delay exceeding ten months. The report warned that slippages in transmission commissioning are already feeding into curtailment episodes in regions with high renewable penetration, notably Rajasthan and Gujarat, while the southern region has seen more limited curtailment during solar hours. A pipeline of roughly 107 GW that has been granted connectivity is slated for integration between 2026-27 and 2030-31, and continued delays could impact renewable energy additions and materially affect project returns.

Related Stories

Gold Stories

Next Story
Products

Interio by Godrej launches modular workplace solutions

Interio by Godrej has launched Workscapes, a modular workplace solutions category designed to help organisations configure and adapt workspaces to changing requirements. The portfolio combines mobile and compatible furniture and support elements that can be rearranged across different work modes without changes to fixed layouts.Workscapes includes Collaboration Tables, Privacy Solutions, Mobile Markerboards and Space Dividers, Power Solutions, Storage and Support Elements, Meeting and Presentation Tools, and Seating Elements. The range is designed for focused work, collaboration, informal disc..

Next Story
Infrastructure Urban

CAFE-III Gives Auto Industry Investment Clarity

The government’s new Corporate Average Fuel Economy (CAFE-III) norms have provided the automobile industry with a clearer framework for technology investments, according to industry representatives. The framework seeks to balance environmental objectives with flexibility for manufacturers while encouraging the adoption of flex-fuel vehicles and biofuels. Society of Indian Automobile Manufacturers (SIAM) President Shenu Agarwal said the five-year framework would give automakers greater predictability to plan investments and accelerate innovation. He said the regulation established annual targ..

Next Story
Infrastructure Energy

Mines Ministry to Auction Two Offshore Mineral Blocks in Andaman Sea

The Ministry of Mines will launch an auction of two offshore mineral blocks in the Andaman Sea on Thursday, seeking to unlock India’s offshore mineral potential and strengthen long-term mineral resource security. The blocks will be offered under a composite licence, which permits exploration and development activities in accordance with the applicable regulatory framework. The ministry said the auction was intended to encourage systematic exploration, attract investment and promote the use of advanced technologies for offshore mineral exploration and development. The initiative is also aimed..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code