RE Projects Face 60 Per Cent Solar-Hour Curtailment as RoW Delays Persist
POWER & RENEWABLE ENERGY

RE Projects Face 60 Per Cent Solar-Hour Curtailment as RoW Delays Persist

A report by Icra has found that critical delays in land acquisition and right-of-way (RoW) for transmission lines have left 33 per cent of India’s recently commissioned renewable energy capacity evacuated through temporary general network access as of May 2026, with curtailment during solar hours remaining as high as 50-60 per cent. The agency noted that these bottlenecks coincide with a planned transmission capex cycle of Rs 5-6 trillion (tn) between 2026-27 and 2031-32 intended to integrate additional capacity into the grid.

Icra said the capex is expected to support the government’s aim to evacuate more than 900 GW of non-fossil fuel capacity by 2035-36, including roughly 548 GW of solar and wind, and will involve strengthening existing infrastructure and adding new evacuation routes. The firm indicated that this scale of investment would also lift prospects for equipment suppliers as order inflows and outstanding orders have more than doubled since 2021-22.

To meet the targets set out in the earlier National Electricity Plan-II, Icra estimated the sector will require annual additions of about 20,000 circuit kilometres of transmission lines and 120 gigavolt-amperes of sub-station capacity, creating a significant investment opportunity in transmission equipment and services. The agency stressed that timely scaling up of manufacturing and project execution capacity will be vital to translate the pipeline into operational capacity.

Supply-side constraints could weigh on project timelines, with limited capacity of equipment manufacturers and shortages of skilled manpower likely to constrain execution unless participants scale up. Icra highlighted persistent execution risks linked to land acquisition, RoW and regulatory approvals; most projects awarded through tariff-based competitive bidding were delayed, with only about 12 per cent completed within the scheduled timeline and the remainder delayed by periods ranging from two months to three years and a median delay exceeding ten months.

The report warned that slippages in transmission commissioning are already feeding into curtailment episodes in regions with high renewable penetration, notably Rajasthan and Gujarat, while the southern region has seen more limited curtailment during solar hours. A pipeline of roughly 107 GW that has been granted connectivity is slated for integration between 2026-27 and 2030-31, and continued delays could impact renewable energy additions and materially affect project returns.

A report by Icra has found that critical delays in land acquisition and right-of-way (RoW) for transmission lines have left 33 per cent of India’s recently commissioned renewable energy capacity evacuated through temporary general network access as of May 2026, with curtailment during solar hours remaining as high as 50-60 per cent. The agency noted that these bottlenecks coincide with a planned transmission capex cycle of Rs 5-6 trillion (tn) between 2026-27 and 2031-32 intended to integrate additional capacity into the grid. Icra said the capex is expected to support the government’s aim to evacuate more than 900 GW of non-fossil fuel capacity by 2035-36, including roughly 548 GW of solar and wind, and will involve strengthening existing infrastructure and adding new evacuation routes. The firm indicated that this scale of investment would also lift prospects for equipment suppliers as order inflows and outstanding orders have more than doubled since 2021-22. To meet the targets set out in the earlier National Electricity Plan-II, Icra estimated the sector will require annual additions of about 20,000 circuit kilometres of transmission lines and 120 gigavolt-amperes of sub-station capacity, creating a significant investment opportunity in transmission equipment and services. The agency stressed that timely scaling up of manufacturing and project execution capacity will be vital to translate the pipeline into operational capacity. Supply-side constraints could weigh on project timelines, with limited capacity of equipment manufacturers and shortages of skilled manpower likely to constrain execution unless participants scale up. Icra highlighted persistent execution risks linked to land acquisition, RoW and regulatory approvals; most projects awarded through tariff-based competitive bidding were delayed, with only about 12 per cent completed within the scheduled timeline and the remainder delayed by periods ranging from two months to three years and a median delay exceeding ten months. The report warned that slippages in transmission commissioning are already feeding into curtailment episodes in regions with high renewable penetration, notably Rajasthan and Gujarat, while the southern region has seen more limited curtailment during solar hours. A pipeline of roughly 107 GW that has been granted connectivity is slated for integration between 2026-27 and 2030-31, and continued delays could impact renewable energy additions and materially affect project returns.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

Asian Energy Services Q1 FY27 PAT Rises 129 Per Cent

Asian Energy Services Limited reported a 129 per cent year-on-year rise in net profit to Rs 128 million for Q1 FY27, compared with the corresponding quarter last year.Revenue increased 135 per cent year-on-year to Rs 2.71 billion, supported by continued momentum across its services business, disciplined execution and contributions from domestic and international operations. EBITDA grew 81 per cent year-on-year during the quarter.As of June 30, 2026, the company’s standalone order book stood at Rs 17.54 billion, with around 60 per cent coming from oil and gas services and 40 per cent from min..

Next Story
Infrastructure Urban

BioBTX to Build First Commercial-Scale Circular Chemicals Plant

Dutch circular chemistry technology developer BioBTX is building what it says will be the world’s first commercial-scale plant to convert mixed plastic waste into high-quality aromatic chemicals using its proprietary Integrated Catalytic Cracking Process (ICCP) technology.The facility will be built at Chemical Park Delfzijl on the northern coast of the Netherlands and is expected to create 35 jobs. Covestro, which has been a shareholder and strategic partner of BioBTX since 2024, holds a mid-single-digit million-euro investment in the company.BioBTX’s ICCP technology uses catalytic pyrolys..

Next Story
Real Estate

Awfis Q1 FY27 PAT Jumps 140% as Revenue Rises 27%

Awfis Space Solutions reported a 140 per cent year-on-year rise in consolidated profit after tax (PAT) to Rs 240 million for Q1 FY27, compared with Rs 100 million in the corresponding quarter last year.Revenue from operations increased 27 per cent to Rs 4.25 billion from Rs 3.35 billion, while EBITDA rose 28 per cent to Rs 1.62 billion. EBITDA margin improved to 38.2 per cent from 37.8 per cent. Profit before tax increased 135 per cent to Rs 240 million.The company's co-working business recorded 27 per cent year-on-year growth, supported by demand from enterprises, Global Capability Centres (G..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement