+
RUMSL invites tender for 170MW Neemuch solar project
POWER & RENEWABLE ENERGY

RUMSL invites tender for 170MW Neemuch solar project

RUMSL issued a request for proposal (RFP) for the development of a 170 MW grid-connected ground-mounted solar photovoltaic project in the Neemuch Solar Park in Madhya Pradesh. It was stated that the power generated from the project would be procured by Madhya Pradesh Power Management Company (MPPMCL) and West Central Railway (WCR).

The deadline to submit bids was mentioned as June 07, 2024, with bids set to be opened on the same day.

It was specified that RUMSL / Government of Madhya Pradesh (GoMP) would provide land for the project?s development, adhering to the terms and conditions outlined in the relevant land use agreement. Additionally, it was stated that RUMSL would provide bidders with the land layout within Neemuch Solar Park, identifying approximately 341 hectares of land for the project, which would then be handed over to the solar project developer.

Further details indicated that RUMSL would provide the power evacuation infrastructure, known as RUMSL Internal Evacuation Infrastructure, which included a 33/220 kV outdoor sub-station dedicated to the project at the Neemuch Solar Park site (Project Substation). This substation was to comprise two 110 MVA transformers, five 220 kV bays, nine 33 kV circuit terminals, and a single circuit 220 kV transmission line connecting the project substation to the bay at the 220/400 kV substation.

Regarding financial requirements, bidders were instructed to furnish an earnest money deposit equal to Rs 157.8 million as part of their Qualification Proposal. The selected bidder was also required to provide performance securities of Rs 2.32 million per MW within three days of accepting the letter of award. Additionally, bidders were mandated to have a minimum net worth of Rs 9.28 million per MW of the quoted capacity.

Consequences for project delays were outlined, stating that if the project?s commissioning exceeded six months from the Schedule Commencement of Supply Date (SCSD), and if 90% of the project?s capacity mentioned in the power purchase agreement had not been commissioned by that date, the developer would be excluded from participating in future bids issued by the procurers.

Furthermore, it was specified that bidders or any of their associates/affiliates should not have failed to perform any contract exceeding a contract value of Rs 3.94 billion, or had any contract terminated by any government or government instrumentality for breach by the bidder in the three years immediately preceding the Proposal Due Date.

RUMSL issued a request for proposal (RFP) for the development of a 170 MW grid-connected ground-mounted solar photovoltaic project in the Neemuch Solar Park in Madhya Pradesh. It was stated that the power generated from the project would be procured by Madhya Pradesh Power Management Company (MPPMCL) and West Central Railway (WCR). The deadline to submit bids was mentioned as June 07, 2024, with bids set to be opened on the same day. It was specified that RUMSL / Government of Madhya Pradesh (GoMP) would provide land for the project?s development, adhering to the terms and conditions outlined in the relevant land use agreement. Additionally, it was stated that RUMSL would provide bidders with the land layout within Neemuch Solar Park, identifying approximately 341 hectares of land for the project, which would then be handed over to the solar project developer. Further details indicated that RUMSL would provide the power evacuation infrastructure, known as RUMSL Internal Evacuation Infrastructure, which included a 33/220 kV outdoor sub-station dedicated to the project at the Neemuch Solar Park site (Project Substation). This substation was to comprise two 110 MVA transformers, five 220 kV bays, nine 33 kV circuit terminals, and a single circuit 220 kV transmission line connecting the project substation to the bay at the 220/400 kV substation. Regarding financial requirements, bidders were instructed to furnish an earnest money deposit equal to Rs 157.8 million as part of their Qualification Proposal. The selected bidder was also required to provide performance securities of Rs 2.32 million per MW within three days of accepting the letter of award. Additionally, bidders were mandated to have a minimum net worth of Rs 9.28 million per MW of the quoted capacity. Consequences for project delays were outlined, stating that if the project?s commissioning exceeded six months from the Schedule Commencement of Supply Date (SCSD), and if 90% of the project?s capacity mentioned in the power purchase agreement had not been commissioned by that date, the developer would be excluded from participating in future bids issued by the procurers. Furthermore, it was specified that bidders or any of their associates/affiliates should not have failed to perform any contract exceeding a contract value of Rs 3.94 billion, or had any contract terminated by any government or government instrumentality for breach by the bidder in the three years immediately preceding the Proposal Due Date.

Next Story
Real Estate

MoHUA Sanctions 1.47 Lakh Additional Houses Under PMAY-U 2.0

In a major push towards the Government’s Housing for All mission, the Ministry of Housing and Urban Affairs (MoHUA) has approved 1,46,582 additional pucca houses under Pradhan Mantri Awas Yojana – Urban 2.0 (PMAY-U 2.0) for 14 States/UTs, bringing total sanctions under the revamped scheme to 8.56 lakh.The decision came during the fourth meeting of the Central Sanctioning and Monitoring Committee (CSMC), chaired by Srinivas Katikithala, Secretary, MoHUA, at the Ministry’s Kasturba Gandhi Marg office. Senior officials, State Principal Secretaries, and PMAY-U Mission Directors participated ..

Next Story
Real Estate

Piyush Goyal Inaugurates Expanded ISA Building at Intellectual Property Office

Union Minister of Commerce and Industry, Piyush Goyal, today inaugurated the newly expanded International Searching Authority (ISA) building at the Intellectual Property Office (IPO) in Dwarka, New Delhi, marking a major step forward in India’s intellectual property ecosystem.Addressing the gathering, Goyal highlighted that innovation has been central to India’s heritage for centuries, citing the engineering brilliance of the Konark Temple as a historic example. He emphasised that innovation is not just intellectual property but a symbol of sovereignty, and a key driver in India’s journe..

Next Story
Real Estate

SIEGER Boosts Automation in Mumbai Realty

SIEGER, a leading automation solutions provider, is expanding its advanced manufacturing capabilities to meet the surging demand for precision, high-speed automation in Mumbai’s rapidly growing real estate sector.Operating from a 21,000 m² advanced production hub in Coimbatore—part of a 40,000 m² integrated campus—SIEGER offers complete solutions from design and prototyping to manufacturing and deployment. The fully digitalised facility features CNC machining, QR-coded component tracking, conveyorized powder coating, and a Government of India–certified R&D centre, ensuring unmatc..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?