RUMSL invites tender for 170MW Neemuch solar project
POWER & RENEWABLE ENERGY

RUMSL invites tender for 170MW Neemuch solar project

RUMSL issued a request for proposal (RFP) for the development of a 170 MW grid-connected ground-mounted solar photovoltaic project in the Neemuch Solar Park in Madhya Pradesh. It was stated that the power generated from the project would be procured by Madhya Pradesh Power Management Company (MPPMCL) and West Central Railway (WCR).

The deadline to submit bids was mentioned as June 07, 2024, with bids set to be opened on the same day.

It was specified that RUMSL / Government of Madhya Pradesh (GoMP) would provide land for the project?s development, adhering to the terms and conditions outlined in the relevant land use agreement. Additionally, it was stated that RUMSL would provide bidders with the land layout within Neemuch Solar Park, identifying approximately 341 hectares of land for the project, which would then be handed over to the solar project developer.

Further details indicated that RUMSL would provide the power evacuation infrastructure, known as RUMSL Internal Evacuation Infrastructure, which included a 33/220 kV outdoor sub-station dedicated to the project at the Neemuch Solar Park site (Project Substation). This substation was to comprise two 110 MVA transformers, five 220 kV bays, nine 33 kV circuit terminals, and a single circuit 220 kV transmission line connecting the project substation to the bay at the 220/400 kV substation.

Regarding financial requirements, bidders were instructed to furnish an earnest money deposit equal to Rs 157.8 million as part of their Qualification Proposal. The selected bidder was also required to provide performance securities of Rs 2.32 million per MW within three days of accepting the letter of award. Additionally, bidders were mandated to have a minimum net worth of Rs 9.28 million per MW of the quoted capacity.

Consequences for project delays were outlined, stating that if the project?s commissioning exceeded six months from the Schedule Commencement of Supply Date (SCSD), and if 90% of the project?s capacity mentioned in the power purchase agreement had not been commissioned by that date, the developer would be excluded from participating in future bids issued by the procurers.

Furthermore, it was specified that bidders or any of their associates/affiliates should not have failed to perform any contract exceeding a contract value of Rs 3.94 billion, or had any contract terminated by any government or government instrumentality for breach by the bidder in the three years immediately preceding the Proposal Due Date.

RUMSL issued a request for proposal (RFP) for the development of a 170 MW grid-connected ground-mounted solar photovoltaic project in the Neemuch Solar Park in Madhya Pradesh. It was stated that the power generated from the project would be procured by Madhya Pradesh Power Management Company (MPPMCL) and West Central Railway (WCR). The deadline to submit bids was mentioned as June 07, 2024, with bids set to be opened on the same day. It was specified that RUMSL / Government of Madhya Pradesh (GoMP) would provide land for the project?s development, adhering to the terms and conditions outlined in the relevant land use agreement. Additionally, it was stated that RUMSL would provide bidders with the land layout within Neemuch Solar Park, identifying approximately 341 hectares of land for the project, which would then be handed over to the solar project developer. Further details indicated that RUMSL would provide the power evacuation infrastructure, known as RUMSL Internal Evacuation Infrastructure, which included a 33/220 kV outdoor sub-station dedicated to the project at the Neemuch Solar Park site (Project Substation). This substation was to comprise two 110 MVA transformers, five 220 kV bays, nine 33 kV circuit terminals, and a single circuit 220 kV transmission line connecting the project substation to the bay at the 220/400 kV substation. Regarding financial requirements, bidders were instructed to furnish an earnest money deposit equal to Rs 157.8 million as part of their Qualification Proposal. The selected bidder was also required to provide performance securities of Rs 2.32 million per MW within three days of accepting the letter of award. Additionally, bidders were mandated to have a minimum net worth of Rs 9.28 million per MW of the quoted capacity. Consequences for project delays were outlined, stating that if the project?s commissioning exceeded six months from the Schedule Commencement of Supply Date (SCSD), and if 90% of the project?s capacity mentioned in the power purchase agreement had not been commissioned by that date, the developer would be excluded from participating in future bids issued by the procurers. Furthermore, it was specified that bidders or any of their associates/affiliates should not have failed to perform any contract exceeding a contract value of Rs 3.94 billion, or had any contract terminated by any government or government instrumentality for breach by the bidder in the three years immediately preceding the Proposal Due Date.

Next Story
Equipment

BKT Partners All Teams in India’s Women’s T20 League

Balkrishna Industries (BKT), a global leader in the off-highway tyre market, announced its association as the Official Tyre Partner for all five teams competing in India’s premier women’s T20 championship – Mumbai Indians, Royal Challengers Bangalore, Delhi Capitals, Gujarat Giants, and UP Warriorz – for the upcoming season. This move reinforces BKT’s commitment to using sport as a platform for inclusion, opportunity, and long-term development.These partnerships reflect BKT’s belief in the transformative power of sport, particularly in advancing women’s participation and creating..

Next Story
Infrastructure Energy

Rajesh Power Secures 65 MW BESS Project in Gujarat

Rajesh Power Services has recently secured a 65 MW / 130 MWh standalone Battery Energy Storage System (BESS) project in Gujarat, marking its entry into utility-scale energy storage. The company received a Letter of Intent from Gujarat Urja Vikas Nigam for the project, which will be developed at Virpore under a tariff-based competitive bidding mechanism supported by Viability Gap Funding through the Power System Development Fund.The project is expected to be executed within 18 months from the signing of the Battery Energy Storage Purchase Agreement. With the ability to supply 65 MW of power for..

Next Story
Infrastructure Energy

ONGC Forms JV with MOL for Ethane Shipping Operations

Oil and Natural Gas Corporation (Oil and Natural Gas Corporation) has recently entered the ethane shipping segment through joint venture agreements with M/s Mitsui O.S.K. Lines Ltd (Mitsui O.S.K. Lines), Japan. The agreements involve equity participation in two joint venture entities—Bharat Ethane One IFSC Private Limited and Bharat Ethane Two IFSC Private Limited—registered at GIFT City, Gandhinagar.Under the arrangement, ONGC will subscribe to 2,00,000 equity shares of Rs 100 each in both entities, resulting in a 50 per cent equity holding in each joint venture, with the remaining stake ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App