RUMSL invites tender for 170MW Neemuch solar project
POWER & RENEWABLE ENERGY

RUMSL invites tender for 170MW Neemuch solar project

RUMSL issued a request for proposal (RFP) for the development of a 170 MW grid-connected ground-mounted solar photovoltaic project in the Neemuch Solar Park in Madhya Pradesh. It was stated that the power generated from the project would be procured by Madhya Pradesh Power Management Company (MPPMCL) and West Central Railway (WCR).

The deadline to submit bids was mentioned as June 07, 2024, with bids set to be opened on the same day.

It was specified that RUMSL / Government of Madhya Pradesh (GoMP) would provide land for the project?s development, adhering to the terms and conditions outlined in the relevant land use agreement. Additionally, it was stated that RUMSL would provide bidders with the land layout within Neemuch Solar Park, identifying approximately 341 hectares of land for the project, which would then be handed over to the solar project developer.

Further details indicated that RUMSL would provide the power evacuation infrastructure, known as RUMSL Internal Evacuation Infrastructure, which included a 33/220 kV outdoor sub-station dedicated to the project at the Neemuch Solar Park site (Project Substation). This substation was to comprise two 110 MVA transformers, five 220 kV bays, nine 33 kV circuit terminals, and a single circuit 220 kV transmission line connecting the project substation to the bay at the 220/400 kV substation.

Regarding financial requirements, bidders were instructed to furnish an earnest money deposit equal to Rs 157.8 million as part of their Qualification Proposal. The selected bidder was also required to provide performance securities of Rs 2.32 million per MW within three days of accepting the letter of award. Additionally, bidders were mandated to have a minimum net worth of Rs 9.28 million per MW of the quoted capacity.

Consequences for project delays were outlined, stating that if the project?s commissioning exceeded six months from the Schedule Commencement of Supply Date (SCSD), and if 90% of the project?s capacity mentioned in the power purchase agreement had not been commissioned by that date, the developer would be excluded from participating in future bids issued by the procurers.

Furthermore, it was specified that bidders or any of their associates/affiliates should not have failed to perform any contract exceeding a contract value of Rs 3.94 billion, or had any contract terminated by any government or government instrumentality for breach by the bidder in the three years immediately preceding the Proposal Due Date.

RUMSL issued a request for proposal (RFP) for the development of a 170 MW grid-connected ground-mounted solar photovoltaic project in the Neemuch Solar Park in Madhya Pradesh. It was stated that the power generated from the project would be procured by Madhya Pradesh Power Management Company (MPPMCL) and West Central Railway (WCR). The deadline to submit bids was mentioned as June 07, 2024, with bids set to be opened on the same day. It was specified that RUMSL / Government of Madhya Pradesh (GoMP) would provide land for the project?s development, adhering to the terms and conditions outlined in the relevant land use agreement. Additionally, it was stated that RUMSL would provide bidders with the land layout within Neemuch Solar Park, identifying approximately 341 hectares of land for the project, which would then be handed over to the solar project developer. Further details indicated that RUMSL would provide the power evacuation infrastructure, known as RUMSL Internal Evacuation Infrastructure, which included a 33/220 kV outdoor sub-station dedicated to the project at the Neemuch Solar Park site (Project Substation). This substation was to comprise two 110 MVA transformers, five 220 kV bays, nine 33 kV circuit terminals, and a single circuit 220 kV transmission line connecting the project substation to the bay at the 220/400 kV substation. Regarding financial requirements, bidders were instructed to furnish an earnest money deposit equal to Rs 157.8 million as part of their Qualification Proposal. The selected bidder was also required to provide performance securities of Rs 2.32 million per MW within three days of accepting the letter of award. Additionally, bidders were mandated to have a minimum net worth of Rs 9.28 million per MW of the quoted capacity. Consequences for project delays were outlined, stating that if the project?s commissioning exceeded six months from the Schedule Commencement of Supply Date (SCSD), and if 90% of the project?s capacity mentioned in the power purchase agreement had not been commissioned by that date, the developer would be excluded from participating in future bids issued by the procurers. Furthermore, it was specified that bidders or any of their associates/affiliates should not have failed to perform any contract exceeding a contract value of Rs 3.94 billion, or had any contract terminated by any government or government instrumentality for breach by the bidder in the three years immediately preceding the Proposal Due Date.

Next Story
Infrastructure Urban

Panasonic Showcases Connected Display Solutions

Panasonic Life Solutions India showcased its integrated display, projection, broadcast and communication technologies at Panasonic Tech Summit 2026 in New Delhi. Hosted through its System Solutions Division, the two-day event highlighted connected technology solutions for education, healthcare, retail, transportation, corporate offices and entertainment.The summit, themed ‘Turning Technology into Value’, featured experience-led zones covering QSR, retail, transit, corporate offices, healthcare, education, security, projection, home theatre and professional displays. Panasonic also introduc..

Next Story
Infrastructure Transport

Kapsch to Deliver India’s First C-ITS Project

"Kapsch TrafficCom will deliver India’s first Cooperative Intelligent Transport Systems project on a key expressway near New Delhi. The project will be implemented with Superwave Communication And Infrasolution Limited to demonstrate how connected mobility can improve road safety and traffic efficiency.The pilot will use real-time connectivity and AI-enabled situational awareness to support road users, especially in high-risk areas such as temporary work zones. Drivers will receive alerts on roadworks, maintenance vehicles, hazardous locations, traffic queues and temporary virtual signage di..

Next Story
Infrastructure Urban

Eurobond Net Profit Rises 44 Per Cent

Euro Panel Products, the parent company of Eurobond, reported a 44.13 per cent year-on-year rise in net profit for FY25–26. The company’s revenue from operations grew 18.91 per cent to Rs 503.20 crore, compared to Rs 423.18 crore in the previous financial year.The company’s full-year EBITDA stood at Rs 56.67 crore, marking a 31.82 per cent increase. Profit after tax rose to Rs 26.56 crore, while net worth increased 20.15 per cent to Rs 160.07 crore. Earnings per share for the year stood at Rs 10.84.Divyam Rajesh Shah, Whole Time Director and CFO, Euro Panel Products, said the company’s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->