+
RUMSL invites tender for 170MW Neemuch solar project
POWER & RENEWABLE ENERGY

RUMSL invites tender for 170MW Neemuch solar project

RUMSL issued a request for proposal (RFP) for the development of a 170 MW grid-connected ground-mounted solar photovoltaic project in the Neemuch Solar Park in Madhya Pradesh. It was stated that the power generated from the project would be procured by Madhya Pradesh Power Management Company (MPPMCL) and West Central Railway (WCR).

The deadline to submit bids was mentioned as June 07, 2024, with bids set to be opened on the same day.

It was specified that RUMSL / Government of Madhya Pradesh (GoMP) would provide land for the project?s development, adhering to the terms and conditions outlined in the relevant land use agreement. Additionally, it was stated that RUMSL would provide bidders with the land layout within Neemuch Solar Park, identifying approximately 341 hectares of land for the project, which would then be handed over to the solar project developer.

Further details indicated that RUMSL would provide the power evacuation infrastructure, known as RUMSL Internal Evacuation Infrastructure, which included a 33/220 kV outdoor sub-station dedicated to the project at the Neemuch Solar Park site (Project Substation). This substation was to comprise two 110 MVA transformers, five 220 kV bays, nine 33 kV circuit terminals, and a single circuit 220 kV transmission line connecting the project substation to the bay at the 220/400 kV substation.

Regarding financial requirements, bidders were instructed to furnish an earnest money deposit equal to Rs 157.8 million as part of their Qualification Proposal. The selected bidder was also required to provide performance securities of Rs 2.32 million per MW within three days of accepting the letter of award. Additionally, bidders were mandated to have a minimum net worth of Rs 9.28 million per MW of the quoted capacity.

Consequences for project delays were outlined, stating that if the project?s commissioning exceeded six months from the Schedule Commencement of Supply Date (SCSD), and if 90% of the project?s capacity mentioned in the power purchase agreement had not been commissioned by that date, the developer would be excluded from participating in future bids issued by the procurers.

Furthermore, it was specified that bidders or any of their associates/affiliates should not have failed to perform any contract exceeding a contract value of Rs 3.94 billion, or had any contract terminated by any government or government instrumentality for breach by the bidder in the three years immediately preceding the Proposal Due Date.

RUMSL issued a request for proposal (RFP) for the development of a 170 MW grid-connected ground-mounted solar photovoltaic project in the Neemuch Solar Park in Madhya Pradesh. It was stated that the power generated from the project would be procured by Madhya Pradesh Power Management Company (MPPMCL) and West Central Railway (WCR). The deadline to submit bids was mentioned as June 07, 2024, with bids set to be opened on the same day. It was specified that RUMSL / Government of Madhya Pradesh (GoMP) would provide land for the project?s development, adhering to the terms and conditions outlined in the relevant land use agreement. Additionally, it was stated that RUMSL would provide bidders with the land layout within Neemuch Solar Park, identifying approximately 341 hectares of land for the project, which would then be handed over to the solar project developer. Further details indicated that RUMSL would provide the power evacuation infrastructure, known as RUMSL Internal Evacuation Infrastructure, which included a 33/220 kV outdoor sub-station dedicated to the project at the Neemuch Solar Park site (Project Substation). This substation was to comprise two 110 MVA transformers, five 220 kV bays, nine 33 kV circuit terminals, and a single circuit 220 kV transmission line connecting the project substation to the bay at the 220/400 kV substation. Regarding financial requirements, bidders were instructed to furnish an earnest money deposit equal to Rs 157.8 million as part of their Qualification Proposal. The selected bidder was also required to provide performance securities of Rs 2.32 million per MW within three days of accepting the letter of award. Additionally, bidders were mandated to have a minimum net worth of Rs 9.28 million per MW of the quoted capacity. Consequences for project delays were outlined, stating that if the project?s commissioning exceeded six months from the Schedule Commencement of Supply Date (SCSD), and if 90% of the project?s capacity mentioned in the power purchase agreement had not been commissioned by that date, the developer would be excluded from participating in future bids issued by the procurers. Furthermore, it was specified that bidders or any of their associates/affiliates should not have failed to perform any contract exceeding a contract value of Rs 3.94 billion, or had any contract terminated by any government or government instrumentality for breach by the bidder in the three years immediately preceding the Proposal Due Date.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Infrastructure Opportunity Outlook by IMPACCT.Info

India’s infrastructure pipeline is witnessing dynamic activity across stages — from immediate bidding to future planning. IMPACCT segments these into three categories: Immediate, 3–6 Month, and Future Opportunities, enabling businesses to identify, prepare, and participate in high-value tenders and projects across sectors.To read full article Click Here ..

Next Story
Real Estate

Glass, Reframed!

Glass façades, quintessential aesthetic building envelopes globally, have been widely adopted in India as well. But when the focus is high-performance building systems that deliver energy efficiency, comfort and architectural identity, glass isn’t the only preference. Combination solutions, involving glass and some other material, improve façade outcomes. Some combinations come at comparable prices, some at a higher price. Here is a selection of performance-oriented solutions...To read the full story Click Here ..

Next Story
Infrastructure Urban

Beyond Building Faster

India’s cities are expanding at an unprecedented pace, bringing new infrastructure and development opportunities while also intensifying challenges around mobility, public spaces, liveability and supporting infrastructure. The question, therefore, is not simply whether India can build faster, but whether it can build cities that work better.At a CW webinar, Are We Designing Better Cities – or Just Building Faster?, moderator Ar. Samir Shaikh, Founding Principal, AR&UD Studio, brought together perspectives from design, development, master planning and technology...To read the full artic..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code