Subansiri Hydropower Project Begins Generation After 20 Years
POWER & RENEWABLE ENERGY

Subansiri Hydropower Project Begins Generation After 20 Years

The Subansiri Lower Hydroelectric Power Project has begun generating electricity after a two-decade journey, with its first unit synchronised to the national power grid at 6.12 pm on Wednesday. The 2,000 MW project, implemented by NHPC, comprises eight units of 250 MW each. A second unit has also begun generation, while three more units are expected to be commissioned this month. Full commissioning is targeted for March 2027.

Project consultant A.N. Mohammad told The Assam Tribune that synchronisation marked a defining moment in India’s hydropower progress. He said Unit 1 and Unit 2 completed mechanical runs on 26 October and 6 November, respectively. Units 1, 3 and 4 will be synchronised after wet commissioning tests, adding 1,000 MW by December 2025. The commercial operation date will be confirmed shortly. The final four units are scheduled for phased commissioning between 2026 and 2027. When fully operational, the plant is expected to supply 7.421 billion units of renewable energy annually, bolstering India’s clean-energy ambitions.

Mohammad highlighted the project’s turbulent history. Conceived in January 2005 at Gerukamukh on the Assam–Arunachal border, construction stalled for eight years—from 2011 to 2019—due to protests, litigation and concerns over dam safety and downstream ecological impact. Work resumed in October 2019 after the government introduced enhanced safeguards.

Several expert panels reviewed the project. The Technical Expert Committee (TEC) addressed hydrological concerns, while the Dam Design Review Panel (DDRP) mandated key safety upgrades, including widening the dam from 171 metres to 271 metres, adding upstream and downstream cut-off walls, improving foundation grouting and installing rock anchors. The National Committee for Seismic Design Parameters (NCSDP) approved seismic safety measures.

A major cumulative impact study by the Central Water Commission in December 2014 required an environmental flow of 240 cubic metres per second to protect aquatic ecosystems. The Subansiri River’s volatile history—including massive floods triggered by the 1950 earthquake—also shaped design decisions. The project’s 1,365 MCM reservoir incorporates a 15-metre flood cushion of 442 MCM and 60 km of downstream embankment fortifications, increasing river-carrying capacity by 15–20 per cent.

Downstream development works worth over Rs 4.7 billion have been undertaken, covering health, education, livelihoods and infrastructure for affected communities. Once operational, Assam will receive 208 MW as per hydropower norms, an additional preferential allocation of 300 MW, and 25 MW of free power. Arunachal Pradesh will receive 12 per cent free power as the host state, with the remaining electricity distributed to other regions, including the Northeast.

The project cost has risen from Rs 62.85 billion at 2002 prices to about Rs 260 billion today, primarily due to prolonged construction, cost escalation and interest during construction, Mohammad said.

The Subansiri Lower Hydroelectric Power Project has begun generating electricity after a two-decade journey, with its first unit synchronised to the national power grid at 6.12 pm on Wednesday. The 2,000 MW project, implemented by NHPC, comprises eight units of 250 MW each. A second unit has also begun generation, while three more units are expected to be commissioned this month. Full commissioning is targeted for March 2027. Project consultant A.N. Mohammad told The Assam Tribune that synchronisation marked a defining moment in India’s hydropower progress. He said Unit 1 and Unit 2 completed mechanical runs on 26 October and 6 November, respectively. Units 1, 3 and 4 will be synchronised after wet commissioning tests, adding 1,000 MW by December 2025. The commercial operation date will be confirmed shortly. The final four units are scheduled for phased commissioning between 2026 and 2027. When fully operational, the plant is expected to supply 7.421 billion units of renewable energy annually, bolstering India’s clean-energy ambitions. Mohammad highlighted the project’s turbulent history. Conceived in January 2005 at Gerukamukh on the Assam–Arunachal border, construction stalled for eight years—from 2011 to 2019—due to protests, litigation and concerns over dam safety and downstream ecological impact. Work resumed in October 2019 after the government introduced enhanced safeguards. Several expert panels reviewed the project. The Technical Expert Committee (TEC) addressed hydrological concerns, while the Dam Design Review Panel (DDRP) mandated key safety upgrades, including widening the dam from 171 metres to 271 metres, adding upstream and downstream cut-off walls, improving foundation grouting and installing rock anchors. The National Committee for Seismic Design Parameters (NCSDP) approved seismic safety measures. A major cumulative impact study by the Central Water Commission in December 2014 required an environmental flow of 240 cubic metres per second to protect aquatic ecosystems. The Subansiri River’s volatile history—including massive floods triggered by the 1950 earthquake—also shaped design decisions. The project’s 1,365 MCM reservoir incorporates a 15-metre flood cushion of 442 MCM and 60 km of downstream embankment fortifications, increasing river-carrying capacity by 15–20 per cent. Downstream development works worth over Rs 4.7 billion have been undertaken, covering health, education, livelihoods and infrastructure for affected communities. Once operational, Assam will receive 208 MW as per hydropower norms, an additional preferential allocation of 300 MW, and 25 MW of free power. Arunachal Pradesh will receive 12 per cent free power as the host state, with the remaining electricity distributed to other regions, including the Northeast. The project cost has risen from Rs 62.85 billion at 2002 prices to about Rs 260 billion today, primarily due to prolonged construction, cost escalation and interest during construction, Mohammad said.

Next Story
Infrastructure Urban

9th India–Myanmar Joint Trade Committee Meeting Held in Nay Pyi Taw

The ninth meeting of the India–Myanmar Joint Trade Committee (JTC) was held in Nay Pyi Taw, Myanmar, with a focus on strengthening bilateral trade and deepening economic cooperation. The meeting was co-chaired by U Minn Minn, Deputy Minister, Ministry of Commerce of the Republic of the Union of Myanmar, and Nitin Kumar Yadav, Additional Secretary, Department of Commerce, Ministry of Commerce and Industry, Government of India.Representatives from relevant ministries and stakeholder departments from both countries participated in the discussions. The meeting covered a broad range of issues aim..

Next Story
Infrastructure Urban

DGCA Launches Digital Pilot Licence Services for ATPL

The Directorate General of Civil Aviation (DGCA) has launched Electronic Personnel Licence (EPL) services for the Airline Transport Pilot Licence (ATPL), marking a significant step in the regulator’s ongoing digital transformation of aviation licensing in India. The service was inaugurated at an event held at the DGCA headquarters.Inaugurating the EPL ATPL service, Director General of Civil Aviation Faiz Ahmed Kidwai said the initiative represents a major advancement in strengthening India’s civil aviation regulatory framework through secure, modern and future-ready digital systems. He con..

Next Story
Infrastructure Urban

Cabinet Extends Atal Pension Yojana and Support Till 2030–31

The Union Cabinet, chaired by Prime Minister Narendra Modi, has approved the continuation of the Atal Pension Yojana (APY) up to the financial year 2030–31, along with the extension of government funding support for promotional and developmental activities and gap funding to ensure the scheme’s long-term sustainability.Under the approved framework, APY will continue to receive government support aimed at expanding its reach among unorganised and low-income workers. This includes funding for awareness campaigns, capacity-building initiatives and other developmental activities to strengthen ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App