Subansiri Hydropower Project Begins Generation After 20 Years
POWER & RENEWABLE ENERGY

Subansiri Hydropower Project Begins Generation After 20 Years

The Subansiri Lower Hydroelectric Power Project has begun generating electricity after a two-decade journey, with its first unit synchronised to the national power grid at 6.12 pm on Wednesday. The 2,000 MW project, implemented by NHPC, comprises eight units of 250 MW each. A second unit has also begun generation, while three more units are expected to be commissioned this month. Full commissioning is targeted for March 2027.

Project consultant A.N. Mohammad told The Assam Tribune that synchronisation marked a defining moment in India’s hydropower progress. He said Unit 1 and Unit 2 completed mechanical runs on 26 October and 6 November, respectively. Units 1, 3 and 4 will be synchronised after wet commissioning tests, adding 1,000 MW by December 2025. The commercial operation date will be confirmed shortly. The final four units are scheduled for phased commissioning between 2026 and 2027. When fully operational, the plant is expected to supply 7.421 billion units of renewable energy annually, bolstering India’s clean-energy ambitions.

Mohammad highlighted the project’s turbulent history. Conceived in January 2005 at Gerukamukh on the Assam–Arunachal border, construction stalled for eight years—from 2011 to 2019—due to protests, litigation and concerns over dam safety and downstream ecological impact. Work resumed in October 2019 after the government introduced enhanced safeguards.

Several expert panels reviewed the project. The Technical Expert Committee (TEC) addressed hydrological concerns, while the Dam Design Review Panel (DDRP) mandated key safety upgrades, including widening the dam from 171 metres to 271 metres, adding upstream and downstream cut-off walls, improving foundation grouting and installing rock anchors. The National Committee for Seismic Design Parameters (NCSDP) approved seismic safety measures.

A major cumulative impact study by the Central Water Commission in December 2014 required an environmental flow of 240 cubic metres per second to protect aquatic ecosystems. The Subansiri River’s volatile history—including massive floods triggered by the 1950 earthquake—also shaped design decisions. The project’s 1,365 MCM reservoir incorporates a 15-metre flood cushion of 442 MCM and 60 km of downstream embankment fortifications, increasing river-carrying capacity by 15–20 per cent.

Downstream development works worth over Rs 4.7 billion have been undertaken, covering health, education, livelihoods and infrastructure for affected communities. Once operational, Assam will receive 208 MW as per hydropower norms, an additional preferential allocation of 300 MW, and 25 MW of free power. Arunachal Pradesh will receive 12 per cent free power as the host state, with the remaining electricity distributed to other regions, including the Northeast.

The project cost has risen from Rs 62.85 billion at 2002 prices to about Rs 260 billion today, primarily due to prolonged construction, cost escalation and interest during construction, Mohammad said.

The Subansiri Lower Hydroelectric Power Project has begun generating electricity after a two-decade journey, with its first unit synchronised to the national power grid at 6.12 pm on Wednesday. The 2,000 MW project, implemented by NHPC, comprises eight units of 250 MW each. A second unit has also begun generation, while three more units are expected to be commissioned this month. Full commissioning is targeted for March 2027. Project consultant A.N. Mohammad told The Assam Tribune that synchronisation marked a defining moment in India’s hydropower progress. He said Unit 1 and Unit 2 completed mechanical runs on 26 October and 6 November, respectively. Units 1, 3 and 4 will be synchronised after wet commissioning tests, adding 1,000 MW by December 2025. The commercial operation date will be confirmed shortly. The final four units are scheduled for phased commissioning between 2026 and 2027. When fully operational, the plant is expected to supply 7.421 billion units of renewable energy annually, bolstering India’s clean-energy ambitions. Mohammad highlighted the project’s turbulent history. Conceived in January 2005 at Gerukamukh on the Assam–Arunachal border, construction stalled for eight years—from 2011 to 2019—due to protests, litigation and concerns over dam safety and downstream ecological impact. Work resumed in October 2019 after the government introduced enhanced safeguards. Several expert panels reviewed the project. The Technical Expert Committee (TEC) addressed hydrological concerns, while the Dam Design Review Panel (DDRP) mandated key safety upgrades, including widening the dam from 171 metres to 271 metres, adding upstream and downstream cut-off walls, improving foundation grouting and installing rock anchors. The National Committee for Seismic Design Parameters (NCSDP) approved seismic safety measures. A major cumulative impact study by the Central Water Commission in December 2014 required an environmental flow of 240 cubic metres per second to protect aquatic ecosystems. The Subansiri River’s volatile history—including massive floods triggered by the 1950 earthquake—also shaped design decisions. The project’s 1,365 MCM reservoir incorporates a 15-metre flood cushion of 442 MCM and 60 km of downstream embankment fortifications, increasing river-carrying capacity by 15–20 per cent. Downstream development works worth over Rs 4.7 billion have been undertaken, covering health, education, livelihoods and infrastructure for affected communities. Once operational, Assam will receive 208 MW as per hydropower norms, an additional preferential allocation of 300 MW, and 25 MW of free power. Arunachal Pradesh will receive 12 per cent free power as the host state, with the remaining electricity distributed to other regions, including the Northeast. The project cost has risen from Rs 62.85 billion at 2002 prices to about Rs 260 billion today, primarily due to prolonged construction, cost escalation and interest during construction, Mohammad said.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code