TN to Add 2620 MW Power Capacity by Year-End
POWER & RENEWABLE ENERGY

TN to Add 2620 MW Power Capacity by Year-End

As demand for power continues to rise in Chennai, the Tamil Nadu Power Generation Corporation Ltd (TNPGCL) has announced that it plans to meet this demand by generating an additional 2620 MW from three key projects – Stage III of the North Chennai Thermal Power Station (800 MW), Stage I of the Udangudi Thermal Power Plant (1320 MW), and the Kundah Pumped Storage Hydro Electric Power Project (500 MW).

The TNPGCL plans to work with the Tamil Nadu Green Energy Corporation (TNGECL) on these projects. Both organisations spoke to the Tamil Nadu Electricity Regulatory Commission (TNERC) regarding the state of progress on the projects. They revealed that all three plants are expected to commence commercial production by the end of the year. They also announced their intention of using washed coal to increase the percentage of energy generated.

North Chennai Thermal Power Station Stage-III: This 800 MW unit, which is already synchronised with the Chennai grid, is undergoing final trials. Despite this seeming success, the plant has been plagued by difficulties, namely the quality of coal and boiler tube equipment. The poor boiler equipment caused the plant to stay under forced outage from January 31st to March 17th, 2025, being allowed to function on March 19th. Regardless, the plant is expected to be commissioned soon.

Udangudi Thermal Power Station Stage-I: This plant is expected to be synchronised by April 2025 and verified for safety regulations by May. A second round of synchronisation and verification is planned for July and August respectively. The plant has already made arrangements for the supply of coal and has evacuation infrastructure already in place. For Stage II and III of the station, the TN government has sanctioned the acquisition of 1500 acres of land, and the process of transfer is underway.

Kundah Pumped Storage Hydro Project (500 MW): This 500 MW project consists of 4, 125 MW units and has faced numerous delays. The third and fourth units will be verified in July and August respectively, while the first and second units will be verified in November. The overall plant, however, is currently awaiting forest clearance so that it can install transmission lines.

As demand for power continues to rise in Chennai, the Tamil Nadu Power Generation Corporation Ltd (TNPGCL) has announced that it plans to meet this demand by generating an additional 2620 MW from three key projects – Stage III of the North Chennai Thermal Power Station (800 MW), Stage I of the Udangudi Thermal Power Plant (1320 MW), and the Kundah Pumped Storage Hydro Electric Power Project (500 MW). The TNPGCL plans to work with the Tamil Nadu Green Energy Corporation (TNGECL) on these projects. Both organisations spoke to the Tamil Nadu Electricity Regulatory Commission (TNERC) regarding the state of progress on the projects. They revealed that all three plants are expected to commence commercial production by the end of the year. They also announced their intention of using washed coal to increase the percentage of energy generated. North Chennai Thermal Power Station Stage-III: This 800 MW unit, which is already synchronised with the Chennai grid, is undergoing final trials. Despite this seeming success, the plant has been plagued by difficulties, namely the quality of coal and boiler tube equipment. The poor boiler equipment caused the plant to stay under forced outage from January 31st to March 17th, 2025, being allowed to function on March 19th. Regardless, the plant is expected to be commissioned soon. Udangudi Thermal Power Station Stage-I: This plant is expected to be synchronised by April 2025 and verified for safety regulations by May. A second round of synchronisation and verification is planned for July and August respectively. The plant has already made arrangements for the supply of coal and has evacuation infrastructure already in place. For Stage II and III of the station, the TN government has sanctioned the acquisition of 1500 acres of land, and the process of transfer is underway. Kundah Pumped Storage Hydro Project (500 MW): This 500 MW project consists of 4, 125 MW units and has faced numerous delays. The third and fourth units will be verified in July and August respectively, while the first and second units will be verified in November. The overall plant, however, is currently awaiting forest clearance so that it can install transmission lines.

Next Story
Infrastructure Transport

Railways Completes Odisha’s Longest Tunnel on Khurda–Balangir Line

Indian Railways has completed the construction of Tunnel T-4, the longest tunnel on the Khurda Road–Balangir railway line, marking a significant milestone in Odisha’s railway infrastructure. The 4,185-metre tunnel connects Adenigarh and Charichhak in Boudh district and is now the longest in the state. Railway officials confirmed the successful breakthrough of the tunnel on 16 April, an event referred to as "daylighting", indicating full excavation from one end to the other. The Khurda Road–Balangir rail line spans 301 kilometres, of which 226 kilometres have been completed. Existing op..

Next Story
Infrastructure Urban

Centre May Target Rs Two Trillion Asset Monetisation in FY 2025–26

The Central government is likely to set an asset monetisation target of Rs 1.9 to two trillion for the financial year 2025–26 under Phase Two of the National Monetisation Pipeline (NMP), with a strong emphasis on sectors such as roads, power, railways, and coal and mines. According to officials, development of vacant public land will also emerge as a key pillar of asset recycling in this phase. NMP Phase Two aims to build on the success of NMP 1.0 (FY 2022–25), which achieved Rs 5.65 trillion of the Rs six trillion target. Monetisation formats will include upfront lease revenues, reven..

Next Story
Infrastructure Transport

Joint DPR Proposed for Road And Rail Projects Through ShiradiGhat

Dakshina Kannada MP Captain Brijesh Chowta has called on the Karnataka Chief Secretary to initiate joint planning between the National Highways Authority of India and the Ministry of Railways for road and rail infrastructure through the ecologically sensitive ShiradiGhat corridor. During a meeting with Chief Secretary Dr Shalini Rajneesh, Chowta emphasised the need for a coordinated Detailed Project Report to reduce environmental impact, streamline inter-departmental approvals, and avoid duplication of efforts. Currently, the two agencies are independently preparing DPRs for National Highway..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?