+
TN to Add 2620 MW Power Capacity by Year-End
POWER & RENEWABLE ENERGY

TN to Add 2620 MW Power Capacity by Year-End

As demand for power continues to rise in Chennai, the Tamil Nadu Power Generation Corporation Ltd (TNPGCL) has announced that it plans to meet this demand by generating an additional 2620 MW from three key projects – Stage III of the North Chennai Thermal Power Station (800 MW), Stage I of the Udangudi Thermal Power Plant (1320 MW), and the Kundah Pumped Storage Hydro Electric Power Project (500 MW).

The TNPGCL plans to work with the Tamil Nadu Green Energy Corporation (TNGECL) on these projects. Both organisations spoke to the Tamil Nadu Electricity Regulatory Commission (TNERC) regarding the state of progress on the projects. They revealed that all three plants are expected to commence commercial production by the end of the year. They also announced their intention of using washed coal to increase the percentage of energy generated.

North Chennai Thermal Power Station Stage-III: This 800 MW unit, which is already synchronised with the Chennai grid, is undergoing final trials. Despite this seeming success, the plant has been plagued by difficulties, namely the quality of coal and boiler tube equipment. The poor boiler equipment caused the plant to stay under forced outage from January 31st to March 17th, 2025, being allowed to function on March 19th. Regardless, the plant is expected to be commissioned soon.

Udangudi Thermal Power Station Stage-I: This plant is expected to be synchronised by April 2025 and verified for safety regulations by May. A second round of synchronisation and verification is planned for July and August respectively. The plant has already made arrangements for the supply of coal and has evacuation infrastructure already in place. For Stage II and III of the station, the TN government has sanctioned the acquisition of 1500 acres of land, and the process of transfer is underway.

Kundah Pumped Storage Hydro Project (500 MW): This 500 MW project consists of 4, 125 MW units and has faced numerous delays. The third and fourth units will be verified in July and August respectively, while the first and second units will be verified in November. The overall plant, however, is currently awaiting forest clearance so that it can install transmission lines.

As demand for power continues to rise in Chennai, the Tamil Nadu Power Generation Corporation Ltd (TNPGCL) has announced that it plans to meet this demand by generating an additional 2620 MW from three key projects – Stage III of the North Chennai Thermal Power Station (800 MW), Stage I of the Udangudi Thermal Power Plant (1320 MW), and the Kundah Pumped Storage Hydro Electric Power Project (500 MW). The TNPGCL plans to work with the Tamil Nadu Green Energy Corporation (TNGECL) on these projects. Both organisations spoke to the Tamil Nadu Electricity Regulatory Commission (TNERC) regarding the state of progress on the projects. They revealed that all three plants are expected to commence commercial production by the end of the year. They also announced their intention of using washed coal to increase the percentage of energy generated. North Chennai Thermal Power Station Stage-III: This 800 MW unit, which is already synchronised with the Chennai grid, is undergoing final trials. Despite this seeming success, the plant has been plagued by difficulties, namely the quality of coal and boiler tube equipment. The poor boiler equipment caused the plant to stay under forced outage from January 31st to March 17th, 2025, being allowed to function on March 19th. Regardless, the plant is expected to be commissioned soon. Udangudi Thermal Power Station Stage-I: This plant is expected to be synchronised by April 2025 and verified for safety regulations by May. A second round of synchronisation and verification is planned for July and August respectively. The plant has already made arrangements for the supply of coal and has evacuation infrastructure already in place. For Stage II and III of the station, the TN government has sanctioned the acquisition of 1500 acres of land, and the process of transfer is underway. Kundah Pumped Storage Hydro Project (500 MW): This 500 MW project consists of 4, 125 MW units and has faced numerous delays. The third and fourth units will be verified in July and August respectively, while the first and second units will be verified in November. The overall plant, however, is currently awaiting forest clearance so that it can install transmission lines.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App