TN to Add 2620 MW Power Capacity by Year-End
POWER & RENEWABLE ENERGY

TN to Add 2620 MW Power Capacity by Year-End

As demand for power continues to rise in Chennai, the Tamil Nadu Power Generation Corporation Ltd (TNPGCL) has announced that it plans to meet this demand by generating an additional 2620 MW from three key projects – Stage III of the North Chennai Thermal Power Station (800 MW), Stage I of the Udangudi Thermal Power Plant (1320 MW), and the Kundah Pumped Storage Hydro Electric Power Project (500 MW).

The TNPGCL plans to work with the Tamil Nadu Green Energy Corporation (TNGECL) on these projects. Both organisations spoke to the Tamil Nadu Electricity Regulatory Commission (TNERC) regarding the state of progress on the projects. They revealed that all three plants are expected to commence commercial production by the end of the year. They also announced their intention of using washed coal to increase the percentage of energy generated.

North Chennai Thermal Power Station Stage-III: This 800 MW unit, which is already synchronised with the Chennai grid, is undergoing final trials. Despite this seeming success, the plant has been plagued by difficulties, namely the quality of coal and boiler tube equipment. The poor boiler equipment caused the plant to stay under forced outage from January 31st to March 17th, 2025, being allowed to function on March 19th. Regardless, the plant is expected to be commissioned soon.

Udangudi Thermal Power Station Stage-I: This plant is expected to be synchronised by April 2025 and verified for safety regulations by May. A second round of synchronisation and verification is planned for July and August respectively. The plant has already made arrangements for the supply of coal and has evacuation infrastructure already in place. For Stage II and III of the station, the TN government has sanctioned the acquisition of 1500 acres of land, and the process of transfer is underway.

Kundah Pumped Storage Hydro Project (500 MW): This 500 MW project consists of 4, 125 MW units and has faced numerous delays. The third and fourth units will be verified in July and August respectively, while the first and second units will be verified in November. The overall plant, however, is currently awaiting forest clearance so that it can install transmission lines.

As demand for power continues to rise in Chennai, the Tamil Nadu Power Generation Corporation Ltd (TNPGCL) has announced that it plans to meet this demand by generating an additional 2620 MW from three key projects – Stage III of the North Chennai Thermal Power Station (800 MW), Stage I of the Udangudi Thermal Power Plant (1320 MW), and the Kundah Pumped Storage Hydro Electric Power Project (500 MW). The TNPGCL plans to work with the Tamil Nadu Green Energy Corporation (TNGECL) on these projects. Both organisations spoke to the Tamil Nadu Electricity Regulatory Commission (TNERC) regarding the state of progress on the projects. They revealed that all three plants are expected to commence commercial production by the end of the year. They also announced their intention of using washed coal to increase the percentage of energy generated. North Chennai Thermal Power Station Stage-III: This 800 MW unit, which is already synchronised with the Chennai grid, is undergoing final trials. Despite this seeming success, the plant has been plagued by difficulties, namely the quality of coal and boiler tube equipment. The poor boiler equipment caused the plant to stay under forced outage from January 31st to March 17th, 2025, being allowed to function on March 19th. Regardless, the plant is expected to be commissioned soon. Udangudi Thermal Power Station Stage-I: This plant is expected to be synchronised by April 2025 and verified for safety regulations by May. A second round of synchronisation and verification is planned for July and August respectively. The plant has already made arrangements for the supply of coal and has evacuation infrastructure already in place. For Stage II and III of the station, the TN government has sanctioned the acquisition of 1500 acres of land, and the process of transfer is underway. Kundah Pumped Storage Hydro Project (500 MW): This 500 MW project consists of 4, 125 MW units and has faced numerous delays. The third and fourth units will be verified in July and August respectively, while the first and second units will be verified in November. The overall plant, however, is currently awaiting forest clearance so that it can install transmission lines.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement