+
TN to Add 2620 MW Power Capacity by Year-End
POWER & RENEWABLE ENERGY

TN to Add 2620 MW Power Capacity by Year-End

As demand for power continues to rise in Chennai, the Tamil Nadu Power Generation Corporation Ltd (TNPGCL) has announced that it plans to meet this demand by generating an additional 2620 MW from three key projects – Stage III of the North Chennai Thermal Power Station (800 MW), Stage I of the Udangudi Thermal Power Plant (1320 MW), and the Kundah Pumped Storage Hydro Electric Power Project (500 MW).

The TNPGCL plans to work with the Tamil Nadu Green Energy Corporation (TNGECL) on these projects. Both organisations spoke to the Tamil Nadu Electricity Regulatory Commission (TNERC) regarding the state of progress on the projects. They revealed that all three plants are expected to commence commercial production by the end of the year. They also announced their intention of using washed coal to increase the percentage of energy generated.

North Chennai Thermal Power Station Stage-III: This 800 MW unit, which is already synchronised with the Chennai grid, is undergoing final trials. Despite this seeming success, the plant has been plagued by difficulties, namely the quality of coal and boiler tube equipment. The poor boiler equipment caused the plant to stay under forced outage from January 31st to March 17th, 2025, being allowed to function on March 19th. Regardless, the plant is expected to be commissioned soon.

Udangudi Thermal Power Station Stage-I: This plant is expected to be synchronised by April 2025 and verified for safety regulations by May. A second round of synchronisation and verification is planned for July and August respectively. The plant has already made arrangements for the supply of coal and has evacuation infrastructure already in place. For Stage II and III of the station, the TN government has sanctioned the acquisition of 1500 acres of land, and the process of transfer is underway.

Kundah Pumped Storage Hydro Project (500 MW): This 500 MW project consists of 4, 125 MW units and has faced numerous delays. The third and fourth units will be verified in July and August respectively, while the first and second units will be verified in November. The overall plant, however, is currently awaiting forest clearance so that it can install transmission lines.

As demand for power continues to rise in Chennai, the Tamil Nadu Power Generation Corporation Ltd (TNPGCL) has announced that it plans to meet this demand by generating an additional 2620 MW from three key projects – Stage III of the North Chennai Thermal Power Station (800 MW), Stage I of the Udangudi Thermal Power Plant (1320 MW), and the Kundah Pumped Storage Hydro Electric Power Project (500 MW). The TNPGCL plans to work with the Tamil Nadu Green Energy Corporation (TNGECL) on these projects. Both organisations spoke to the Tamil Nadu Electricity Regulatory Commission (TNERC) regarding the state of progress on the projects. They revealed that all three plants are expected to commence commercial production by the end of the year. They also announced their intention of using washed coal to increase the percentage of energy generated. North Chennai Thermal Power Station Stage-III: This 800 MW unit, which is already synchronised with the Chennai grid, is undergoing final trials. Despite this seeming success, the plant has been plagued by difficulties, namely the quality of coal and boiler tube equipment. The poor boiler equipment caused the plant to stay under forced outage from January 31st to March 17th, 2025, being allowed to function on March 19th. Regardless, the plant is expected to be commissioned soon. Udangudi Thermal Power Station Stage-I: This plant is expected to be synchronised by April 2025 and verified for safety regulations by May. A second round of synchronisation and verification is planned for July and August respectively. The plant has already made arrangements for the supply of coal and has evacuation infrastructure already in place. For Stage II and III of the station, the TN government has sanctioned the acquisition of 1500 acres of land, and the process of transfer is underway. Kundah Pumped Storage Hydro Project (500 MW): This 500 MW project consists of 4, 125 MW units and has faced numerous delays. The third and fourth units will be verified in July and August respectively, while the first and second units will be verified in November. The overall plant, however, is currently awaiting forest clearance so that it can install transmission lines.

Next Story
Equipment

Company showcases North America-certified machinery and secures new deals

Zoomlion Heavy Industry Science & Technology Co., recently showcased a wide portfolio of North America-certified and customised construction equipment at CONEXPO-CON/AGG 2026 in Las Vegas. The display included engineering hoisting machinery, concrete equipment, earthmoving machinery, mining equipment and construction hoisting solutions tailored to regional operational requirements.All equipment presented at the exhibition complies with North American certification standards, with several models specifically developed to meet local regulatory requirements and site conditions. One of the hig..

Next Story
Technology

Sinoboom Launches Dual-ETM Smart Technology

Sinoboom recently introduced its Dual-ETM Smart Technology at CONEXPO-CON/AGG 2026, designed to enhance battery endurance and operational efficiency in electric boom lifts.The new technology integrates advanced components that enable real-time optimisation of power usage during equipment operation. By calculating the precise power requirement instantly, the system delivers only the energy needed for each movement, reducing the inefficiencies associated with conventional maximum-demand power systems.The solution incorporates multiple sensors—including pressure, weight, length and level sensor..

Next Story
Infrastructure Transport

Ramky Infra Wins Rs 14.01 Bn DMIC Project

Ramky Infrastructure has secured an engineering, procurement and construction (EPC) contract worth Rs 14.01 billion from Maharashtra Industrial Township Limited (MITL) for infrastructure development in Phase 1 of the Dighi Port Industrial Area (DPIA) under the Delhi–Mumbai Industrial Corridor (DMIC).The project, located in Raigad district of Maharashtra, involves comprehensive infrastructure works including design, engineering, construction, testing and commissioning, along with operations and maintenance. The contract includes a four-year operations and maintenance period after commissionin..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement