TNGECL Plans Online Portal for Renewable Energy Projects
POWER & RENEWABLE ENERGY

TNGECL Plans Online Portal for Renewable Energy Projects

The Tamil Nadu Green Energy Corporation (TNGECL) is planning to launch an online portal on October 1 to receive applications for new renewable energy projects, as the state seeks to expand clean power capacity and improve electricity availability. The move comes amid continuing power outage concerns and rising demand during periods of fluctuating renewable generation.

TNGECL held an online meeting with associations representing renewable energy developers and investors on Monday to discuss the proposed portal and application procedure. The process will have 10 stages, beginning with the submission of basic project details, payment of the application fee and furnishing of a security deposit.

The Superintending Engineer (Solar) will validate a proposed project within 10 days. Applicants will have 30 days to respond to any clarifications sought during scrutiny, after which an accepted proposal will move to the preparation of a feasibility report. Developers will then be required to submit land-related documents within six months.

Following the required clearances and completion of the connectivity process, developers will be allowed to begin construction. A senior official said the state was planning to add at least 1,500 MW of solar power capacity along with battery energy storage systems (BESS) by the end of the current financial year.

Renewable Energy Producers Association representative K Venkatachalam said the procedure had been formalised for uploading connectivity proposals for wind, solar and hybrid projects with BESS. He raised questions over whether TNGECL would use application formats already prescribed by the Tamil Nadu Electricity Regulatory Commission (TNERC) or introduce new ones.

Venkatachalam also said the proposed requirement for Ministry of Environment, Forest and Climate Change approvals for Environmental Impact Assessment and consent orders from the Tamil Nadu Pollution Control Board appeared inconsistent with existing exemptions for renewable energy projects. He further noted that a Unique ID from the Central Electricity Authority is issued after commissioning, making its use as a precondition an anomaly.

The Tamil Nadu Green Energy Corporation (TNGECL) is planning to launch an online portal on October 1 to receive applications for new renewable energy projects, as the state seeks to expand clean power capacity and improve electricity availability. The move comes amid continuing power outage concerns and rising demand during periods of fluctuating renewable generation. TNGECL held an online meeting with associations representing renewable energy developers and investors on Monday to discuss the proposed portal and application procedure. The process will have 10 stages, beginning with the submission of basic project details, payment of the application fee and furnishing of a security deposit. The Superintending Engineer (Solar) will validate a proposed project within 10 days. Applicants will have 30 days to respond to any clarifications sought during scrutiny, after which an accepted proposal will move to the preparation of a feasibility report. Developers will then be required to submit land-related documents within six months. Following the required clearances and completion of the connectivity process, developers will be allowed to begin construction. A senior official said the state was planning to add at least 1,500 MW of solar power capacity along with battery energy storage systems (BESS) by the end of the current financial year. Renewable Energy Producers Association representative K Venkatachalam said the procedure had been formalised for uploading connectivity proposals for wind, solar and hybrid projects with BESS. He raised questions over whether TNGECL would use application formats already prescribed by the Tamil Nadu Electricity Regulatory Commission (TNERC) or introduce new ones. Venkatachalam also said the proposed requirement for Ministry of Environment, Forest and Climate Change approvals for Environmental Impact Assessment and consent orders from the Tamil Nadu Pollution Control Board appeared inconsistent with existing exemptions for renewable energy projects. He further noted that a Unique ID from the Central Electricity Authority is issued after commissioning, making its use as a precondition an anomaly.

Related Stories

Gold Stories

Next Story
Real Estate

Japanese companies expand GCC operations in India

More than 100 Japanese companies have established or are expanding Global Capability Centres (GCCs) in India, with a growing focus on artificial intelligence (AI), engineering, digital innovation, product development, cybersecurity and advanced analytics. The shift marks an expansion beyond traditional back-office and operational support functions towards higher-value technology and innovation activities.Japanese companies are increasingly using their Indian GCCs to support digital transformation, address talent shortages and contribute to global business strategies. These centres are taking o..

Next Story
Real Estate

India’s flexible office stock projected to reach 160 million sq ft by 2030

India retained its position as the world's most mature flexible office market, scoring 100 per cent on Cushman & Wakefield's Flexible Office Market Maturity Index, according to the firm's Global Trends in Flexible Office 2026 report.India's flexible office inventory reached 88.7 million sq ft (MSF) in H1 2026, accounting for 10.5 per cent of the country's total office stock. The report projects this to exceed 100 MSF in 2026 and reach approximately 160 MSF by 2030.Flexible office operators leased 8.5 MSF across India's top eight cities in H1 2026, their strongest first-half performance to ..

Next Story
Infrastructure Urban

K2 Infragen appoints Abhishek Sharma as DGM, supply chain

K2 Infragen has appointed Abhishek Sharma as Deputy General Manager, Supply Chain Management. He will oversee procurement planning, vendor partnerships and coordination with project teams.Sharma brings nearly two decades of experience in infrastructure procurement across railways, highways, expressways and hydropower. His experience includes procurement responsibilities associated with the Delhi–Meerut Expressway and the Delhi–Vadodara greenfield corridor. ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code