360 infrastructure projects report cost overruns of Rs 3.88 trillion
Real Estate

360 infrastructure projects report cost overruns of Rs 3.88 trillion

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019 according to which – out of the total 1608 projects, more than 360 have shown cost overruns to the cost of Rs 3.88 trillion. 

As reported, the report states that the original estimated cost of all the projects summed up to be approximately Rs 19.18 trillion. The completion cost is now expected to be around Rs 23.05 trillion. There have therefore been cost overruns of around 20.23 per cent of the original cost. 

Additionally, it also included the number of projects that had crossed their deadlines, these amounted to 550. However, reportedly, the number of time escalations decreases to 474 if the criteria for estimating the delay is done on the basis of the latest schedule of completion. The average time overrun for all 550 projects was reported to be 39.24 months. 

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints in regards to funding, geographical conditions, labour issues and court cases amongst other reasons. 

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019 according to which – out of the total 1608 projects, more than 360 have shown cost overruns to the cost of Rs 3.88 trillion. As reported, the report states that the original estimated cost of all the projects summed up to be approximately Rs 19.18 trillion. The completion cost is now expected to be around Rs 23.05 trillion. There have therefore been cost overruns of around 20.23 per cent of the original cost. Additionally, it also included the number of projects that had crossed their deadlines, these amounted to 550. However, reportedly, the number of time escalations decreases to 474 if the criteria for estimating the delay is done on the basis of the latest schedule of completion. The average time overrun for all 550 projects was reported to be 39.24 months. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints in regards to funding, geographical conditions, labour issues and court cases amongst other reasons. 

Next Story
Infrastructure Energy

Adani Power To Build 2,400 MW Plant in Bihar

Adani Power on Saturday (September 13, 2025) announced plans to set up a 2,400 MW ultra super-critical power plant in Bihar at an investment of $3 billion (around Rs 26.48 billion).The company has signed a 25-year Power Supply Agreement (PSA) with Bihar State Power Generation Company Ltd (BSPGCL) to supply electricity from the project, which will be located at Pirpainti in Bhagalpur district.The PSA follows a Letter of Award issued by BSPGCL to Adani Power on behalf of North Bihar Power Distribution Company Ltd (NBPDCL) and South Bihar Power Distribution Company Ltd (SBPDCL) in August. Adani P..

Next Story
Infrastructure Energy

NTPC Plans Nuclear Power Projects Via JV and Standalone Routes

Power major NTPC is planning to develop nuclear power projects both through joint ventures and on a standalone basis, CMD Gurdeep Singh has said.The company is collaborating with nuclear technology providers and state governments to explore individual nuclear projects, Singh added.Currently, the NTPC Group has an installed capacity of 82,926 MW across 53 NTPC-owned stations and 53 joint venture or subsidiary stations, drawing power from coal, liquid fuel, hydro, and solar sources.In December 2024, Singh had announced NTPC’s ambitious plan to enter the nuclear energy sector, a move expected t..

Next Story
Infrastructure Transport

RVNL Wins $21.6 Million Bhopal Division Traction Substation

Rail Vikas Nigam (RVNL) has been declared the lowest bidder for a $21.6 million traction substation contract awarded by the West Central Railway.The project covers the design, modification, supply, erection, testing, and commissioning of a 220/132kV/2×25kV Scott-connected traction substation, switching posts, Auto-Transformer installations, and Supervisory Control and Data Acquisition (SCADA) systems in the Bina–RTA section of the Bhopal Division. The execution period is set at 540 days.In a regulatory filing, RVNL stated that the order was secured in the ordinary course of business and doe..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?