360 infrastructure projects report cost overruns of Rs 3.88 trillion
Real Estate

360 infrastructure projects report cost overruns of Rs 3.88 trillion

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019 according to which – out of the total 1608 projects, more than 360 have shown cost overruns to the cost of Rs 3.88 trillion. 

As reported, the report states that the original estimated cost of all the projects summed up to be approximately Rs 19.18 trillion. The completion cost is now expected to be around Rs 23.05 trillion. There have therefore been cost overruns of around 20.23 per cent of the original cost. 

Additionally, it also included the number of projects that had crossed their deadlines, these amounted to 550. However, reportedly, the number of time escalations decreases to 474 if the criteria for estimating the delay is done on the basis of the latest schedule of completion. The average time overrun for all 550 projects was reported to be 39.24 months. 

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints in regards to funding, geographical conditions, labour issues and court cases amongst other reasons. 

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019 according to which – out of the total 1608 projects, more than 360 have shown cost overruns to the cost of Rs 3.88 trillion. As reported, the report states that the original estimated cost of all the projects summed up to be approximately Rs 19.18 trillion. The completion cost is now expected to be around Rs 23.05 trillion. There have therefore been cost overruns of around 20.23 per cent of the original cost. Additionally, it also included the number of projects that had crossed their deadlines, these amounted to 550. However, reportedly, the number of time escalations decreases to 474 if the criteria for estimating the delay is done on the basis of the latest schedule of completion. The average time overrun for all 550 projects was reported to be 39.24 months. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints in regards to funding, geographical conditions, labour issues and court cases amongst other reasons. 

Next Story
Infrastructure Urban

ABB to Invest Rs 6.25 Billion to Expand India Manufacturing

ABB recently announced plans to invest approximately Rs 6.25 billion ($75 million) in India during 2026 to expand its manufacturing footprint and research and development capabilities. The investment follows more than $35 million spent in 2025 and reflects the company’s continued focus on strengthening its ‘local-for-local’ strategy in the country.The investment will support ABB’s Electrification, Motion and Automation businesses and expand manufacturing capacity for infrastructure sectors such as renewable energy, metro rail, data centres and industrial applications. Approximately 300..

Next Story
Equipment

Six WOLFF Cranes Handle 60,000 m³ Concrete for German Hospital

Six WOLFF tower cranes are playing a key role in constructing a new hospital complex in Memmingen, Germany, supporting large-scale material handling for the project. The facility is being built on a 7.7-hectare site and will feature six floors, around 480 beds and a gross floor area exceeding 75,000 sq m.Building shell works began recently in February 2025. One WOLFF 6531.12 Cross crane supported early site preparation before being dismantled in autumn 2025, while five remaining cranes continue operations. Over an average deployment period of 16 months, the cranes are expected to move approxim..

Next Story
Equipment

REC Funds Rs 115.6 Million CSR Support for Bihar Eye Hospital

REC recently committed Rs 115.6 million under its Corporate Social Responsibility (CSR) programme for the procurement of clinical and non-clinical equipment at Sankara Eye Hospital in Saharsa, Bihar. The initiative aims to strengthen healthcare infrastructure and improve access to specialised eye care services in the region.A Memorandum of Agreement (MoA) was recently signed between Pradeep Fellows, Executive Director (CSR), REC Limited, and Wg Cdr V. Shankar (Retd), Trustee and Executive Director of Sankara Eye Hospital, at the REC office in the SCOPE Complex, New Delhi.The support is expecte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement