Rs 4,517.50 billion worth of housing stuck in stages of non-completion
Real Estate

Rs 4,517.50 billion worth of housing stuck in stages of non-completion

Despite the establishment of a regulatory mechanism, countless homebuyers have been left in the lurch by their builders. In fact, Rs 4,517.50 billion worth of housing is currently stuck in various stages of non-completion across top seven cities, according to data from real-estate services company ANAROCK.

Most of these projects do not fall within the ambit of RERA as they were launched years before it was implemented. Also, with many states having diluted the Centre's original RERA rules, homebuyers have only the courts to approach, which is a notoriously tedious task in India.
  
Areas like the National Capital Region (NCR) and Mumbai Metropolitan Region (MMR) collectively account for 72 per cent of the total stuck housing units across the top seven cities worth Rs 3490.1 billion—nearly 77 per cent of the total worth of the stuck projects. In comparison, the main southern cities of Bengaluru, Chennai and Hyderabad together account for a mere 10 per cent of the overall stuck housing units with a total worth of Rs 417.7 billion. Bengaluru has less than half the total delayed stock in Pune (86,700 units), while Chennai has the least project delays during this period, with around 8,650 units worth Rs 56.20 billion.
 
“Besides the lack of will of some developers to complete their projects and preference for funds diversion, the tightening credit crunch has been a major factor contributing to this mounting problem,” observes Anuj Puri, Chairman, ANAROCK Property Consultants. “Also, every delayed project results in cost overruns, which compound the funding crunch even further. Lack of project clearances, for whatever reason, also contributes to the piling up of housing stock. In the pre-RERA era, many builders launched greenfield projects without requisite approvals in place, resulting in their projects getting stuck.” 
 
As one of the possible solutions to this problem, the government-owned NBCC has been roped in to complete some stalled projects in NCR. This is a significant move that, if applied in larger numbers, can have a real impact. “Moreover, even if NBCC picks up 50 per cent of overall stalled projects, the resultant construction activities would create significant employment for the EWS and LIG segments, which are also the key target segment for affordable housing,” he adds.
 
Additionally, with NBCC undertaking construction, the apprehensions of banks about funding construction would ease. With this provision, even when builders opt for bankruptcy, state authorities would intervene to safeguard the investments of homebuyers. However, buyers are still awaiting their final outcome of these interventions.

Despite the establishment of a regulatory mechanism, countless homebuyers have been left in the lurch by their builders. In fact, Rs 4,517.50 billion worth of housing is currently stuck in various stages of non-completion across top seven cities, according to data from real-estate services company ANAROCK.Most of these projects do not fall within the ambit of RERA as they were launched years before it was implemented. Also, with many states having diluted the Centre's original RERA rules, homebuyers have only the courts to approach, which is a notoriously tedious task in India.  Areas like the National Capital Region (NCR) and Mumbai Metropolitan Region (MMR) collectively account for 72 per cent of the total stuck housing units across the top seven cities worth Rs 3490.1 billion—nearly 77 per cent of the total worth of the stuck projects. In comparison, the main southern cities of Bengaluru, Chennai and Hyderabad together account for a mere 10 per cent of the overall stuck housing units with a total worth of Rs 417.7 billion. Bengaluru has less than half the total delayed stock in Pune (86,700 units), while Chennai has the least project delays during this period, with around 8,650 units worth Rs 56.20 billion. “Besides the lack of will of some developers to complete their projects and preference for funds diversion, the tightening credit crunch has been a major factor contributing to this mounting problem,” observes Anuj Puri, Chairman, ANAROCK Property Consultants. “Also, every delayed project results in cost overruns, which compound the funding crunch even further. Lack of project clearances, for whatever reason, also contributes to the piling up of housing stock. In the pre-RERA era, many builders launched greenfield projects without requisite approvals in place, resulting in their projects getting stuck.”  As one of the possible solutions to this problem, the government-owned NBCC has been roped in to complete some stalled projects in NCR. This is a significant move that, if applied in larger numbers, can have a real impact. “Moreover, even if NBCC picks up 50 per cent of overall stalled projects, the resultant construction activities would create significant employment for the EWS and LIG segments, which are also the key target segment for affordable housing,” he adds. Additionally, with NBCC undertaking construction, the apprehensions of banks about funding construction would ease. With this provision, even when builders opt for bankruptcy, state authorities would intervene to safeguard the investments of homebuyers. However, buyers are still awaiting their final outcome of these interventions.

Next Story
Real Estate

Shriram Properties Launches ‘Codename: The One’ in Bengaluru

Shriram Properties (SPL), a leading real estate developer focused on the mid-market and mid-premium segments, has announced the launch of its latest residential project under the banner “Codename: The One” in Bengaluru’s Electronic City corridor. This feature-rich gated community will offer 340 spacious 2- and 3-BHK residences, with a total saleable area of approximately 5 lakh square feet and an estimated revenue potential of over Rs 3.5 billion. The project is expected to be developed over a span of more than three years.  Strategically located near the Bommasandra Metro stat..

Next Story
Resources

India Warehousing Show 2025 Closes with Strong Global Presence

The 14th edition of the India Warehousing Show (IWS) 2025 concluded successfully at Yashobhoomi (IICC), Dwarka, drawing participation from over 300 exhibitors across 15 countries and welcoming 15,000+ visitors. Recognised as India’s leading platform for warehousing and logistics excellence, IWS 2025 offered a comprehensive display of cutting-edge automation, sustainable warehousing solutions, and next-gen supply chain technologies. The show was inaugurated by Shri Pankaj Kumar, Joint Secretary – Logistics, DPIIT, Ministry of Commerce and Industry, Government of India. In his opening a..

Next Story
Equipment

MHIET Launches 450kW Gas Cogeneration System with H₂ Co-Firing

Mitsubishi Heavy Industries Engine & Turbocharger (MHIET), part of the Mitsubishi Heavy Industries Group, has launched a new 450kW gas cogeneration system, the SGP M450, jointly developed with Toho Gas Co.,. The system supports hydrogen co-firing at up to 15 vol per cent, with no loss in performance or reliability.  The system is currently available in the Japanese market, and has been developed from the existing GS6R2 city gas engine platform. Key modifications were made to the fuel gas and engine control systems to enable hydrogen co-firing.   Verified through de..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?