All about the world’s tallest modular building!
Real Estate

All about the world’s tallest modular building!

Construction company Bouygues Bâtiment International has built the Clement Canopy, a pair of 140-m-high towers made of prefabricated concrete modules. The company claims that the development in Singapore has set a new record for the tallest modular buildings. Previously the title had been held by 101 George Street, a 135-m tower built in Croydon, England, by Tide Construction. Notably, the first high-rise modular tower was built in New York in 2016 by SHoP Architects. 

Recently, CONSTRUCTION WORLD conducted a webinar on how ‘Precast & Prefab Technology – The Answer to Fast Track Construction Industry Growth.’ Our esteemed panelists deliberated upon critical need to adopt latest construction technologies and standards. The webinar discussed various advantages of precast technology, including in areas of timely delivery and accurate project execution. 

The specs 

Clement Canopy is a residential condominium located along Clementi Avenue. The development has a gross floor area of 50,200 sq m, consisting of 505 dwelling units spread over two 40-storey blocks and a multi storey car park with one basement floor. The basement floor, multi-storey car park and first floor of the blocks are of conventional construction, while the typical floors from level 2 to 40 have adopted prefabricated prefinished volumetric construction (PPVC). The PPVC modules were designed as six-sided concrete PPVC modules. The weight of the modules range from 26 tonne to 31 tonne and have been installed using two 48-tonne capacity tower cranes. 

Clement Canopy's 1,899 prefabricated and pre-finished modules were built off-site whose weight ranged from 37,000 to 64,000 lbs. Each module is around 85 per cent finished off-site, before then being assembled onsite. The main contractor was able to install 10 to 12 modules per day with a floor cycle time of 7 days. The entire project was completed in 30 months, six months ahead of the scheduled date.

The architecture has been designed by ADDP Architects LLP, structural engineering by TW-Asia Consultants Pte Ltd and main contractor being Dragages Singapore Pte Ltd. The construction of the skyscraper started in 2016 and was completed in 2019.



Fast, reliable, flexible

The pioneer technique developed by MCT Italy to cast 3D modules in a fast, reliable, and flexible way thanks to the joint action of high-speed flying bucket and automatic casting machines increase the benefits of modular and prefabrication processes whereby:

Construction time can be reduced up to 50 per cent
On site labour can be reduced by 30 per cent
Reduction of jobsite noise, pollution and neighbourhood disruption
Improvements in jobsite safety and the quality of the finished product.

The module's structures are cast from concrete in a yard in Senai, Malaysia; then a factory in Tuas, West Singapore, carries out the fit-out in 15-days to a nearly finished stage. This includes, the painting, windows frame and glazing, doors, wardrobes, and MEP (mechanical, electrical and plumbing) including water and sanitary pipes, electrical conduits and ducting, which are all totally finished before the modules arrive on site. Clement Canopy's concrete core was built at the same time as the modules were stacked and installed, in a carefully choreographed sequence. This method helped reduce the time of construction and was more eco-friendly as the modules were built off-site in an eco-friendly environment. By industrialising and building 50 per cent of the project offsite, loss of time due to poor on-site weather conditions was mitigated. 

PPVC benefits

The adoption of PPVC at The Clement Canopy brought about many learning points in design, production and site works. While quality of workmanship was improved as the bulk of architectural works were carried out in a factory-controlled environment, strict site control and discipline had to be maintained to ensure minimal damages to the finishes. Early confirmation of drawings and materials represented one of the major hurdles towards ensuring a smooth production cycle. Another important decision to be made was the location of the heavy-duty tower crane to determine the crane’s foundation and its tie-back to the main tower. This affected the overall structural design of the residential towers and modules had to be strengthened to cater for this additional loading. The adoption of PPVC has helped all stakeholders of the project in achieving shorter construction duration, higher quality workmanship, safer construction site and lesser disruptions to the surroundings schools.

Construction company Bouygues Bâtiment International has built the Clement Canopy, a pair of 140-m-high towers made of prefabricated concrete modules. The company claims that the development in Singapore has set a new record for the tallest modular buildings. Previously the title had been held by 101 George Street, a 135-m tower built in Croydon, England, by Tide Construction. Notably, the first high-rise modular tower was built in New York in 2016 by SHoP Architects. Recently, CONSTRUCTION WORLD conducted a webinar on how ‘Precast & Prefab Technology – The Answer to Fast Track Construction Industry Growth.’ Our esteemed panelists deliberated upon critical need to adopt latest construction technologies and standards. The webinar discussed various advantages of precast technology, including in areas of timely delivery and accurate project execution. The specs Clement Canopy is a residential condominium located along Clementi Avenue. The development has a gross floor area of 50,200 sq m, consisting of 505 dwelling units spread over two 40-storey blocks and a multi storey car park with one basement floor. The basement floor, multi-storey car park and first floor of the blocks are of conventional construction, while the typical floors from level 2 to 40 have adopted prefabricated prefinished volumetric construction (PPVC). The PPVC modules were designed as six-sided concrete PPVC modules. The weight of the modules range from 26 tonne to 31 tonne and have been installed using two 48-tonne capacity tower cranes. Clement Canopy's 1,899 prefabricated and pre-finished modules were built off-site whose weight ranged from 37,000 to 64,000 lbs. Each module is around 85 per cent finished off-site, before then being assembled onsite. The main contractor was able to install 10 to 12 modules per day with a floor cycle time of 7 days. The entire project was completed in 30 months, six months ahead of the scheduled date.The architecture has been designed by ADDP Architects LLP, structural engineering by TW-Asia Consultants Pte Ltd and main contractor being Dragages Singapore Pte Ltd. The construction of the skyscraper started in 2016 and was completed in 2019.Fast, reliable, flexibleThe pioneer technique developed by MCT Italy to cast 3D modules in a fast, reliable, and flexible way thanks to the joint action of high-speed flying bucket and automatic casting machines increase the benefits of modular and prefabrication processes whereby:● Construction time can be reduced up to 50 per cent● On site labour can be reduced by 30 per cent● Reduction of jobsite noise, pollution and neighbourhood disruption● Improvements in jobsite safety and the quality of the finished product.The module's structures are cast from concrete in a yard in Senai, Malaysia; then a factory in Tuas, West Singapore, carries out the fit-out in 15-days to a nearly finished stage. This includes, the painting, windows frame and glazing, doors, wardrobes, and MEP (mechanical, electrical and plumbing) including water and sanitary pipes, electrical conduits and ducting, which are all totally finished before the modules arrive on site. Clement Canopy's concrete core was built at the same time as the modules were stacked and installed, in a carefully choreographed sequence. This method helped reduce the time of construction and was more eco-friendly as the modules were built off-site in an eco-friendly environment. By industrialising and building 50 per cent of the project offsite, loss of time due to poor on-site weather conditions was mitigated. PPVC benefitsThe adoption of PPVC at The Clement Canopy brought about many learning points in design, production and site works. While quality of workmanship was improved as the bulk of architectural works were carried out in a factory-controlled environment, strict site control and discipline had to be maintained to ensure minimal damages to the finishes. Early confirmation of drawings and materials represented one of the major hurdles towards ensuring a smooth production cycle. Another important decision to be made was the location of the heavy-duty tower crane to determine the crane’s foundation and its tie-back to the main tower. This affected the overall structural design of the residential towers and modules had to be strengthened to cater for this additional loading. The adoption of PPVC has helped all stakeholders of the project in achieving shorter construction duration, higher quality workmanship, safer construction site and lesser disruptions to the surroundings schools.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement