COVID-19 lockdown stalls construction activities
Real Estate

COVID-19 lockdown stalls construction activities

Image courtesy: Hindustan Times

  • More than 15.62 lakh units (launched between 2013 till 2019) are under construction in the top 7 cities.
  • Of this, MMR and NCR together comprise 57 per cent or approximately 8.90 lakh units.
  • Pune has nearly 2.62 lakh units under construction, followed by Bengaluru with 2.02 lakh units and Kolkata with approximately 90,670 units.
  • Chennai and Hyderabad together comprise just 8 per cent (approximately 1.18 lakh units) share of overall under-construction units.
  • With most top cities announcing a lockdown till at least March 31, homebuyers must brace themselves for project delays.
  • A lot is currently at stake for Indian residential real estate as cities go into complete lockdown mode to battle the spread of Covid-19. Developers tend to schedule project launches during the auspicious festivals of Gudi Padwa, Akshaya Tritiya, Navratri and Ugadi. The strict advisories for complete lockdown across cities will impact housing sales during the upcoming festivals, usually considered auspicious by several homebuyers to buy homes.


    Prashant Thakur, Director & Head-Research, Anarock Property Consultants, says, “Another fallout of the lockdown is that many key markets will have almost zero construction activity at the project sites. This will further strain several developers’ financial health. As many as 15.62 lakh units across the top 7 cities were in various stages of construction as on 2019 end, reveals Anarock research. These include all under-construction units launched between 2013 till 2019-end. Even this figure is conservative – the number of units will be higher once Q1 2020 data comes in.”

    “Further analysis reveals that out of these 15.62 lakh units under construction, nearly 57 per cent or nearly 8.90 lakh units are in MMR and NCR alone. Both these regions already have a backlog of lakhs of delayed or stalled units. With construction activity almost coming to a standstill, homebuyers will have to brace themselves for another wave of delayed project deliveries.”

    Under-construction stock - city-wise

  • MMR currently has the highest under-construction stock with nearly 4.65 lakh units – 30 per cent of the overall under-construction stock across the top 7 cities.
  • NCR is close behind with 27 per cent or over 4.25 lakh units in various stages of construction. All these units were launched between 2013 till 2019-end.
  • Pune has close to 2.62 lakh units in various stages of construction.
  • Among the three southern cities, Bengaluru has the maximum under-construction stock as on 2019-end with nearly 2.02 lakh units, followed by Hyderabad with nearly 64,250 units and Chennai with the least stock of nearly 54,200 units.
  • Kolkata currently has more than 90,650 units under construction.
  • The road to recovery
    Once the crisis is under control, the government will have to dole out various economic measures to bail out severely-hit sectors, reconsider its fiscal deficit targets and start spending. That said, since this is a crisis with pan-India ramifications, all impacted projects will have to be excused from construction delay penalties under the respective state RERA.

    Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

    Image courtesy: Hindustan Times More than 15.62 lakh units (launched between 2013 till 2019) are under construction in the top 7 cities. Of this, MMR and NCR together comprise 57 per cent or approximately 8.90 lakh units. Pune has nearly 2.62 lakh units under construction, followed by Bengaluru with 2.02 lakh units and Kolkata with approximately 90,670 units. Chennai and Hyderabad together comprise just 8 per cent (approximately 1.18 lakh units) share of overall under-construction units. With most top cities announcing a lockdown till at least March 31, homebuyers must brace themselves for project delays. A lot is currently at stake for Indian residential real estate as cities go into complete lockdown mode to battle the spread of Covid-19. Developers tend to schedule project launches during the auspicious festivals of Gudi Padwa, Akshaya Tritiya, Navratri and Ugadi. The strict advisories for complete lockdown across cities will impact housing sales during the upcoming festivals, usually considered auspicious by several homebuyers to buy homes. Prashant Thakur, Director & Head-Research, Anarock Property Consultants, says, “Another fallout of the lockdown is that many key markets will have almost zero construction activity at the project sites. This will further strain several developers’ financial health. As many as 15.62 lakh units across the top 7 cities were in various stages of construction as on 2019 end, reveals Anarock research. These include all under-construction units launched between 2013 till 2019-end. Even this figure is conservative – the number of units will be higher once Q1 2020 data comes in.” “Further analysis reveals that out of these 15.62 lakh units under construction, nearly 57 per cent or nearly 8.90 lakh units are in MMR and NCR alone. Both these regions already have a backlog of lakhs of delayed or stalled units. With construction activity almost coming to a standstill, homebuyers will have to brace themselves for another wave of delayed project deliveries.” Under-construction stock - city-wise MMR currently has the highest under-construction stock with nearly 4.65 lakh units – 30 per cent of the overall under-construction stock across the top 7 cities. NCR is close behind with 27 per cent or over 4.25 lakh units in various stages of construction. All these units were launched between 2013 till 2019-end. Pune has close to 2.62 lakh units in various stages of construction. Among the three southern cities, Bengaluru has the maximum under-construction stock as on 2019-end with nearly 2.02 lakh units, followed by Hyderabad with nearly 64,250 units and Chennai with the least stock of nearly 54,200 units. Kolkata currently has more than 90,650 units under construction. The road to recovery Once the crisis is under control, the government will have to dole out various economic measures to bail out severely-hit sectors, reconsider its fiscal deficit targets and start spending. That said, since this is a crisis with pan-India ramifications, all impacted projects will have to be excused from construction delay penalties under the respective state RERA.

    Next Story
    Real Estate

    Mumbai Records 11,230 Property Deals in August 2025

    Mumbai’s property market remained resilient in August 2025, with 11,230 property registrations recorded under the Brihanmumbai Municipal Corporation (BMC) jurisdiction, according to data released by Knight Frank India. While this marks a 3 per cent year-on-year (YoY) decline compared to 11,631 registrations in August 2024, activity stayed robust despite the marginal dip.On a month-on-month (MoM) basis, registrations fell 11 per cent from 12,579 deals in July 2025, indicating seasonal moderation. However, the city’s stamp duty collections still reached Rs 10 billion, reflecting a 6 per cent..

    Next Story
    Infrastructure Transport

    68 Jammu-Katra Trains Cancelled Amid Rain Damage

    Jammu and Katra railway services remain severely affected as Northern Railway announced the cancellation of 68 trains—both incoming and outgoing—until 30 September, due to extensive track damage caused by heavy rains and flash floods. Meanwhile, 24 trains are scheduled to resume operations gradually.The Jammu railway division has experienced a complete halt in services for the past eight days, following track misalignment and breaches at several points along the Pathankot–Jammu section. Torrential rainfall since 26 August led to widespread flooding and damage, stranding hundreds of passe..

    Next Story
    Infrastructure Transport

    Bangalore Metro MD Reviews Reach 6 and Phase 2A Progress

    Bangalore Metro Rail Corporation Limited (BMRCL) Managing Director, Dr J Ravishankar, IAS, conducted inspections of key metro corridors on 29 and 30 August, reviewing the progress of Reach 6 (Pink Line) and Phase 2A (Blue Line).On 30 August, the inspection covered Reach 6, a 21.39-km corridor stretching from Kalena Agrahara to Nagawara, with 18 stations. This stretch is part of Phase 2 of the Bangalore Metro project. Dr Ravishankar assessed the status of civil works, finishing, track laying, and system integration between Kalena Agrahara and MG Road.Earlier, on 29 August, the MD inspected Phas..