Form Follows Function!
Real Estate

Form Follows Function!

The Council on Tall Buildings and Urban Habitats defines a tall building as one having more than 14 storeys, or being 50 metres high, and a supertall building as one that is over 300 metres high. In that context, India’s major metros are gradually becoming home to more tall and supertall buildings, especially residential buildings.

Building taller necessitates advanced technologies including formwork systems and scaffolding. Forms that worked for a shorter building may prove unsuitable for a tall building for consuming too much time or not be amenable to the use of safety systems and so on. What forms work best? A few experts share their preference and the reasons for them.

“We used Doka formwork for Tridhaatu Kshitij at Matunga (W), Mumbai, which is 33 floors high,” says Govind Krishnan Muthukumar, Co-Founder & Director, Tridhaatu Realty. “Doka formwork uses prefabricated steel frames and plywood sheets to form a mould for the concrete. It is designed for different types of structural members such as columns, beams, slabs, walls, etc. While our initial investment was huge, Doka formwork can be reused multiple times for different projects, which makes it cost-effective in the long term. Doka formwork is efficient, reliable, quicker and safe.”

“We used a combination of the coupler system (H-frame scaffolding) to construct Omkar Altamonte,” says Madan Mistry, Head - EPC (Engineering Procurement Construction), Omkar Realtors & Developers. “Cup-lock system scaffolding is renowned for its versatility and robustness, providing a secure platform for construction activities. It also offers stability and ease of assembly, ensuring the safety of workers at great heights. This strategic combination allowed for efficient and safe construction operations throughout the project. Omkar Altamonte utilised aluminium formwork, which is environment-friendly, engineered for precision and speed, offers benefits such as exceptional durability, reduced construction time and enhanced concrete finish quality, and contributes significantly to cost savings over the life of a project.”

To read the full story, CLICK HERE.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Council on Tall Buildings and Urban Habitats defines a tall building as one having more than 14 storeys, or being 50 metres high, and a supertall building as one that is over 300 metres high. In that context, India’s major metros are gradually becoming home to more tall and supertall buildings, especially residential buildings.Building taller necessitates advanced technologies including formwork systems and scaffolding. Forms that worked for a shorter building may prove unsuitable for a tall building for consuming too much time or not be amenable to the use of safety systems and so on. What forms work best? A few experts share their preference and the reasons for them.“We used Doka formwork for Tridhaatu Kshitij at Matunga (W), Mumbai, which is 33 floors high,” says Govind Krishnan Muthukumar, Co-Founder & Director, Tridhaatu Realty. “Doka formwork uses prefabricated steel frames and plywood sheets to form a mould for the concrete. It is designed for different types of structural members such as columns, beams, slabs, walls, etc. While our initial investment was huge, Doka formwork can be reused multiple times for different projects, which makes it cost-effective in the long term. Doka formwork is efficient, reliable, quicker and safe.”“We used a combination of the coupler system (H-frame scaffolding) to construct Omkar Altamonte,” says Madan Mistry, Head - EPC (Engineering Procurement Construction), Omkar Realtors & Developers. “Cup-lock system scaffolding is renowned for its versatility and robustness, providing a secure platform for construction activities. It also offers stability and ease of assembly, ensuring the safety of workers at great heights. This strategic combination allowed for efficient and safe construction operations throughout the project. Omkar Altamonte utilised aluminium formwork, which is environment-friendly, engineered for precision and speed, offers benefits such as exceptional durability, reduced construction time and enhanced concrete finish quality, and contributes significantly to cost savings over the life of a project.”To read the full story, CLICK HERE.

Next Story
Resources

Jyoti Structures Launches Heat Safety Drive Across Sites

Jyoti Structures (JSL) has strengthened heat safety measures across its project sites and manufacturing facilities as temperatures rise across India. The company has implemented a Summer Safety Plan covering all transmission line projects to address risks related to heat stress, dehydration and worker fatigue.The initiative includes rescheduling work away from peak afternoon temperatures, provision of drinking water, ORS and lemon-salt solutions, and installation of rest shelters near work areas. Daily toolbox talks, worker health monitoring, first-aid preparedness, emergency transport arrange..

Next Story
Real Estate

MHADA Declares 82 Buildings Most Dangerous in Central and South Mumbai

The Maharashtra Housing and Area Development Authority (MHADA) has declared 82 buildings as most dangerous across Central and South Mumbai and has appealed to residents to vacate immediately. The list, prepared after structural assessments by the authority, identifies buildings judged to pose imminent risk to occupants and to passersby. Local civic bodies have been asked to coordinate evacuations and to make arrangements for temporary shelter and rehabilitation for displaced households. Officials said the authority prioritised buildings with visible structural distress, severe cracking, tiltin..

Next Story
Infrastructure Transport

Damage Reported At Halwara Airport Terminal After First Rains

Severe damage was reported at the terminal of Halwara Airport during the first major rain spell of the season, prompting immediate concern among aviation and local authorities. Images from the site showed water ingress and visible deterioration of the terminal interior, affecting passenger areas and ancillary services. The airport authority suspended certain operations temporarily to assess structural safety and ensure passenger wellbeing. Preliminary inspections have prioritised electrical systems and roof seals to prevent further water ingress. State aviation officials ordered a formal inqui..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement