K-RERA warns developers for not meeting project completion deadlines
Real Estate

K-RERA warns developers for not meeting project completion deadlines

Real estate developers in Bengaluru have completed only 51 out of 424 housing projects even after the deadline was extended.

The Karnataka Real Estate Regulatory Authority (K-RERA) has planned to take action against defaulting developers. According to the developers, the pandemic was the main reason for the delay, due to which the deadline was extended further by another six months.

K-RERA had extended the deadline for the apartment projects from April to 30 September as a relief to the real estate sector after being affected by the Covid-19 pandemic.

According to data, only some projects were completed within the extended deadline. K-RERA officials said that they would wait for a month before acting against the defaulting developers.

H C Kishore Chandra, Chairman of K-RERA, said that the developer would have to face legal actions if they fail to deliver the apartments to the customers within the deadline.

If a developer fails to deliver a project within the deadline mentioned in the sale agreement, he will have to pay 9% interest on the apartment value for the delayed period apart from the compensation fixed by K-RERA.

It is the third extended deadline given to the developers after getting hit by the Covid-19 pandemic. K-RERA initially extended the deadline by six months from 15 March 2020 and then extended it by another three months.

Total 525 out of 4,378 approved projects were not completed within the deadline, while the deadline was extended for 241 projects due to the Covid-19 pandemic. While 284 applications seeking extension are still under process, the completion date has expired for 976 projects.

M S Shankar, general secretary of Forum for People's Collective Efforts, said that homebuyers would have to wait for more for the possession but should continue to repay the home loans. But the developers argue that the extension was not beneficial because it was non-uniform towards all the projects.

Image Source

Real estate developers in Bengaluru have completed only 51 out of 424 housing projects even after the deadline was extended. The Karnataka Real Estate Regulatory Authority (K-RERA) has planned to take action against defaulting developers. According to the developers, the pandemic was the main reason for the delay, due to which the deadline was extended further by another six months. K-RERA had extended the deadline for the apartment projects from April to 30 September as a relief to the real estate sector after being affected by the Covid-19 pandemic. According to data, only some projects were completed within the extended deadline. K-RERA officials said that they would wait for a month before acting against the defaulting developers. H C Kishore Chandra, Chairman of K-RERA, said that the developer would have to face legal actions if they fail to deliver the apartments to the customers within the deadline. If a developer fails to deliver a project within the deadline mentioned in the sale agreement, he will have to pay 9% interest on the apartment value for the delayed period apart from the compensation fixed by K-RERA. It is the third extended deadline given to the developers after getting hit by the Covid-19 pandemic. K-RERA initially extended the deadline by six months from 15 March 2020 and then extended it by another three months. Total 525 out of 4,378 approved projects were not completed within the deadline, while the deadline was extended for 241 projects due to the Covid-19 pandemic. While 284 applications seeking extension are still under process, the completion date has expired for 976 projects. M S Shankar, general secretary of Forum for People's Collective Efforts, said that homebuyers would have to wait for more for the possession but should continue to repay the home loans. But the developers argue that the extension was not beneficial because it was non-uniform towards all the projects. Image Source

Next Story
Real Estate

Mahindra Lifespaces Bags Rs 12.5 billion Redevelopment in Mulund

Mahindra Lifespace Developers (MLDL), the real estate and infrastructure development arm of the Mahindra Group, has been appointed as the preferred developer for the redevelopment of a premium housing society in Mulund (West), Mumbai. The project will be developed across a 3.08-acre land parcel, with an estimated development value of approximately Rs 12.5 billion. Strategically located, the site enjoys proximity to major connectivity points—just 1.4 km from the upcoming Mumbai Metro Line 5 and 0.8 km from the Goregaon-Mulund Link Road. It also offers seamless access to the Eastern Expre..

Next Story
Infrastructure Urban

Snowman Adds Warehouses in Kolkata and Krishnapatnam

Snowman Logistics, India’s leading integrated temperature-controlled logistics company, has announced the commencement of operations at its two new state-of-the-art, owned cold storage facilities in Kolkata and Krishnapatnam. With these additions, the company’s total pallet capacity has reached 1,50,754, spanning 43 warehouses in 20 cities across the country. The newly operational Kolkata facility offers a storage capacity of 5,630 pallets, while the Krishnapatnam facility holds 3,927 pallets. These warehouses are equipped with advanced automation and infrastructure designed to enhanc..

Next Story
Resources

Noesis Enables IHCL Hotel Deal in Udupi–Manipal Corridor

NOESIS Capital Advisors, India’s leading hotel investment advisory firm, has successfully facilitated a landmark hospitality transaction in the Udupi–Manipal region of Karnataka. The deal involves the acquisition of a nearly completed, 130-key upscale hotel that will operate under one of the premium brands of IHCL, reinforcing NOESIS’ position as a preferred partner for strategic hospitality transactions across India. Strategically located on the Udupi–Manipal Highway, the 1.03-acre property will cater to business travellers, pilgrims and families visiting Manipal University. With..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?