LYSAGHT delivers high performance leak-proof roofing solution
Real Estate

LYSAGHT delivers high performance leak-proof roofing solution

Project: Re-roofing of damaged roof with double skin TRIMDEK and KLIP-LOK 700 roof system. Variable height supporting brackets were also provided to ensure perfect alignment to the existing undulated roof.
Client: Salcomp Manufacturing India.
Location: Sriperumbudur, Chennai.

Purpose
Salcomp wanted to set up a manufacturing unit for mobile accessories for a global brand Nokia, within an area of 12,000 sq mt with re-roofing of total 160 tonne.

Background
Finland-based Salcomp, one of the global leaders in the mobile phone charger market, with an existing capacity of manufacturing 150-200 million chargers annually, wanted to further expand their manufacturing capacity by another 100 million chargers per annum. The existing site had a 10-year-old PEB building. There were severe leakages from several locations, which were amounting to huge production losses. The structure required a comprehensive inspection by a reliable roofing consultant. Salcomp approached Tata BlueScope Steel, who implemented an in-depth study of the existing structure.

Customer requirement
After a comprehensive investigation, Tata BlueScope Steel's team identified the root cause of the problem. It was evident through investigations that the existing structure had many collateral loads, hanging from purlins and rafters. Many rafters were already deflected leading to further deflecting the main purlins, resulting in several undulations in the existing roof, which was Single Skin Screw Down System. Undulations caused rainwater stagnation ensuing huge leakages at many places.

Solution offered
To address customer's primary concern for leak-proofness, Tata BlueScope Steel suggested LYSAGHT KLIP-LOK 700 widest concealed roof system with LYSAGHT TRIMDEK as the liner panel. LYSAGHT KLIP-LOK made from high strength ZINCALUME steel has long been a design favourite for prestigious commercial, industrial and architectural projects across the globe. Not only performance, but with bold rib geometry rising from wide, flat pans, LYSAGHT KLIP-LOK roof provides a strong visual statement and its flat pans also offer excellent water carrying capacity. It is one of the strongest profiles with longer spanning capability. Absence of piercing and its special clip locking ensures zero chances of roof leakage. Tried and tested at NATA Lab (Australia), under rigorous cyclonic and non-cyclonic applications, LYSAGHT KLIP-LOK offers on-site roll forming preventing step joints and end laps. While the solution seemed straightforward, there were a few onsite challenges that had to be addressed going beyond standardisation, ensuring customer-centric solutions.

Design challenge
There were too many undulations along the slope length of roof due to deflections in the main frame rafters and purlins. These undulations needed to be rectified to achieve leak-proof roof system.

Solution
Contour layout was conducted to measure the undulations at every 5 m along the roof length. Accordingly, supporting brackets with heights varying from 40 mm to 140 mm were designed and detailed to get the same level or plane of top sheet.

Operational challenge
Fixing of LYSAGHT KLIP-LOK clip was a challenge, since sub-purlin line was not straight due to longitudinal misalignments of main purlins.

Solution
Supporting brackets were designed and detailed to support sub-purlins. Alignment was made to bring the sub-purlins in line, parallel to building length to achieve KLIP-LOK clips in straight line.

Conclusion
Project completed with zero harm: New age construction technology from LYSAGHT team was put into place to enable the workforce to execute the job seamlessly. Due to safety training and regular supervision, the project was completed without any unsafe incidence.

Right solution with on-time delivery: LYSAGHT team proposed the technically correct offer, which was eventually accepted by the customer. Furthermore, on site roll forming and excellent project management ensured on-time delivery.

100 per cent leak-proof solution: Single length sheet of 60 m from ridge to eve avoided any joints and eliminated any kind of leakage. This also helped savings in lap lengths, thus reducing the input material and installation time. Since the customer was looking for a leak-proof roof, installation support and best quality workmanship were provided to achieve the desired objective. Inspections were undertaken on a daily basis to achieve the highest quality of installation.

With collaborative team work, design optimisation and an efficient supply chain management, the project was successfully delivered to customer’s satisfaction.

Project: Re-roofing of damaged roof with double skin TRIMDEK and KLIP-LOK 700 roof system. Variable height supporting brackets were also provided to ensure perfect alignment to the existing undulated roof.Client: Salcomp Manufacturing India.Location: Sriperumbudur, Chennai.PurposeSalcomp wanted to set up a manufacturing unit for mobile accessories for a global brand Nokia, within an area of 12,000 sq mt with re-roofing of total 160 tonne.BackgroundFinland-based Salcomp, one of the global leaders in the mobile phone charger market, with an existing capacity of manufacturing 150-200 million chargers annually, wanted to further expand their manufacturing capacity by another 100 million chargers per annum. The existing site had a 10-year-old PEB building. There were severe leakages from several locations, which were amounting to huge production losses. The structure required a comprehensive inspection by a reliable roofing consultant. Salcomp approached Tata BlueScope Steel, who implemented an in-depth study of the existing structure.Customer requirementAfter a comprehensive investigation, Tata BlueScope Steel's team identified the root cause of the problem. It was evident through investigations that the existing structure had many collateral loads, hanging from purlins and rafters. Many rafters were already deflected leading to further deflecting the main purlins, resulting in several undulations in the existing roof, which was Single Skin Screw Down System. Undulations caused rainwater stagnation ensuing huge leakages at many places.Solution offeredTo address customer's primary concern for leak-proofness, Tata BlueScope Steel suggested LYSAGHT KLIP-LOK 700 widest concealed roof system with LYSAGHT TRIMDEK as the liner panel. LYSAGHT KLIP-LOK made from high strength ZINCALUME steel has long been a design favourite for prestigious commercial, industrial and architectural projects across the globe. Not only performance, but with bold rib geometry rising from wide, flat pans, LYSAGHT KLIP-LOK roof provides a strong visual statement and its flat pans also offer excellent water carrying capacity. It is one of the strongest profiles with longer spanning capability. Absence of piercing and its special clip locking ensures zero chances of roof leakage. Tried and tested at NATA Lab (Australia), under rigorous cyclonic and non-cyclonic applications, LYSAGHT KLIP-LOK offers on-site roll forming preventing step joints and end laps. While the solution seemed straightforward, there were a few onsite challenges that had to be addressed going beyond standardisation, ensuring customer-centric solutions.Design challengeThere were too many undulations along the slope length of roof due to deflections in the main frame rafters and purlins. These undulations needed to be rectified to achieve leak-proof roof system.SolutionContour layout was conducted to measure the undulations at every 5 m along the roof length. Accordingly, supporting brackets with heights varying from 40 mm to 140 mm were designed and detailed to get the same level or plane of top sheet.Operational challengeFixing of LYSAGHT KLIP-LOK clip was a challenge, since sub-purlin line was not straight due to longitudinal misalignments of main purlins.SolutionSupporting brackets were designed and detailed to support sub-purlins. Alignment was made to bring the sub-purlins in line, parallel to building length to achieve KLIP-LOK clips in straight line.ConclusionProject completed with zero harm: New age construction technology from LYSAGHT team was put into place to enable the workforce to execute the job seamlessly. Due to safety training and regular supervision, the project was completed without any unsafe incidence.Right solution with on-time delivery: LYSAGHT team proposed the technically correct offer, which was eventually accepted by the customer. Furthermore, on site roll forming and excellent project management ensured on-time delivery.100 per cent leak-proof solution: Single length sheet of 60 m from ridge to eve avoided any joints and eliminated any kind of leakage. This also helped savings in lap lengths, thus reducing the input material and installation time. Since the customer was looking for a leak-proof roof, installation support and best quality workmanship were provided to achieve the desired objective. Inspections were undertaken on a daily basis to achieve the highest quality of installation.With collaborative team work, design optimisation and an efficient supply chain management, the project was successfully delivered to customer’s satisfaction.

Next Story
Infrastructure Energy

Vedanta Aluminium Uses 1.57 bn Units of Green Energy in FY25

Vedanta Aluminium, India’s largest aluminium producer, recently reported consumption of 1.57 billion units of renewable energy in FY25, marking a significant milestone in its 2030 decarbonisation roadmap. The company also achieved an 8.96 per cent reduction in greenhouse gas (GHG) emissions intensity compared to FY21, reinforcing its leadership in India’s low-carbon manufacturing transition. During FY25, Vedanta Aluminium expanded its renewable energy portfolio through long-term power purchase agreements, strengthening its strategy to source nearly 1,500 MW of renewable power over the lon..

Next Story
Real Estate

Oberoi Group to Develop Luxury Resort at Makaibari Tea Estate

EIH Limited, the flagship company of The Oberoi Group, has announced the signing of a management agreement to develop an Oberoi luxury resort at the iconic Makaibari Tea Estate in Darjeeling. The project marks a key milestone in the Group’s long-term strategy of creating distinctive hospitality experiences in rare and environmentally significant locations. Established in 1859, Makaibari is one of the world’s oldest tea estates and is globally recognised for its Himalayan landscape, primary forests and exceptional biodiversity. Spread across 1,236 acres, the estate houses one of the world..

Next Story
Real Estate

GHV Infra Secures Rs 1.09 Bn EPC Order in Jamshedpur

GHV Infra Projects Ltd, a fast-growing EPC company in India’s infrastructure and construction sector, has recently secured a Rs 1.09 billion work order in Jamshedpur, Jharkhand. Awarded by a reputed group entity, the contract covers end-to-end civil construction, mechanical, electrical and plumbing (MEP) systems, along with high-quality finishing works for a large building development. The project will be executed over a 30-month period, with defined benchmarks for quality, safety and timely delivery. The order strengthens GHV Infra’s footprint in Jamshedpur, a key industrial hub known fo..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App