Project: Re-roofing of damaged roof with double skin TRIMDEK and KLIP-LOK 700 roof system. Variable height supporting brackets were also provided to ensure perfect alignment to the existing undulated roof.
Client: Salcomp Manufacturing India.
Location: Sriperumbudur, Chennai.

Purpose
Salcomp wanted to set up a manufacturing unit for mobile accessories for a global brand Nokia, within an area of 12,000 sq mt with re-roofing of total 160 tonne.

Background
Finland-based Salcomp, one of the global leaders in the mobile phone charger market, with an existing capacity of manufacturing 150-200 million chargers annually, wanted to further expand their manufacturing capacity by another 100 million chargers per annum. The existing site had a 10-year-old PEB building. There were severe leakages from several locations, which were amounting to huge production losses. The structure required a comprehensive inspection by a reliable roofing consultant. Salcomp approached Tata BlueScope Steel, who implemented an in-depth study of the existing structure.

Customer requirement
After a comprehensive investigation, Tata BlueScope Steel's team identified the root cause of the problem. It was evident through investigations that the existing structure had many collateral loads, hanging from purlins and rafters. Many rafters were already deflected leading to further deflecting the main purlins, resulting in several undulations in the existing roof, which was Single Skin Screw Down System. Undulations caused rainwater stagnation ensuing huge leakages at many places.

Solution offered
To address customer's primary concern for leak-proofness, Tata BlueScope Steel suggested LYSAGHT KLIP-LOK 700 widest concealed roof system with LYSAGHT TRIMDEK as the liner panel. LYSAGHT KLIP-LOK made from high strength ZINCALUME steel has long been a design favourite for prestigious commercial, industrial and architectural projects across the globe. Not only performance, but with bold rib geometry rising from wide, flat pans, LYSAGHT KLIP-LOK roof provides a strong visual statement and its flat pans also offer excellent water carrying capacity. It is one of the strongest profiles with longer spanning capability. Absence of piercing and its special clip locking ensures zero chances of roof leakage. Tried and tested at NATA Lab (Australia), under rigorous cyclonic and non-cyclonic applications, LYSAGHT KLIP-LOK offers on-site roll forming preventing step joints and end laps. While the solution seemed straightforward, there were a few onsite challenges that had to be addressed going beyond standardisation, ensuring customer-centric solutions.

Design challenge
There were too many undulations along the slope length of roof due to deflections in the main frame rafters and purlins. These undulations needed to be rectified to achieve leak-proof roof system.

Solution
Contour layout was conducted to measure the undulations at every 5 m along the roof length. Accordingly, supporting brackets with heights varying from 40 mm to 140 mm were designed and detailed to get the same level or plane of top sheet.

Operational challenge
Fixing of LYSAGHT KLIP-LOK clip was a challenge, since sub-purlin line was not straight due to longitudinal misalignments of main purlins.

Solution
Supporting brackets were designed and detailed to support sub-purlins. Alignment was made to bring the sub-purlins in line, parallel to building length to achieve KLIP-LOK clips in straight line.

Conclusion
Project completed with zero harm: New age construction technology from LYSAGHT team was put into place to enable the workforce to execute the job seamlessly. Due to safety training and regular supervision, the project was completed without any unsafe incidence.

Right solution with on-time delivery: LYSAGHT team proposed the technically correct offer, which was eventually accepted by the customer. Furthermore, on site roll forming and excellent project management ensured on-time delivery.

100 per cent leak-proof solution: Single length sheet of 60 m from ridge to eve avoided any joints and eliminated any kind of leakage. This also helped savings in lap lengths, thus reducing the input material and installation time. Since the customer was looking for a leak-proof roof, installation support and best quality workmanship were provided to achieve the desired objective. Inspections were undertaken on a daily basis to achieve the highest quality of installation.

With collaborative team work, design optimisation and an efficient supply chain management, the project was successfully delivered to customer’s satisfaction.

Project: Re-roofing of damaged roof with double skin TRIMDEK and KLIP-LOK 700 roof system. Variable height supporting brackets were also provided to ensure perfect alignment to the existing undulated roof.Client: Salcomp Manufacturing India.Location: Sriperumbudur, Chennai.PurposeSalcomp wanted to set up a manufacturing unit for mobile accessories for a global brand Nokia, within an area of 12,000 sq mt with re-roofing of total 160 tonne.BackgroundFinland-based Salcomp, one of the global leaders in the mobile phone charger market, with an existing capacity of manufacturing 150-200 million chargers annually, wanted to further expand their manufacturing capacity by another 100 million chargers per annum. The existing site had a 10-year-old PEB building. There were severe leakages from several locations, which were amounting to huge production losses. The structure required a comprehensive inspection by a reliable roofing consultant. Salcomp approached Tata BlueScope Steel, who implemented an in-depth study of the existing structure.Customer requirementAfter a comprehensive investigation, Tata BlueScope Steel's team identified the root cause of the problem. It was evident through investigations that the existing structure had many collateral loads, hanging from purlins and rafters. Many rafters were already deflected leading to further deflecting the main purlins, resulting in several undulations in the existing roof, which was Single Skin Screw Down System. Undulations caused rainwater stagnation ensuing huge leakages at many places.Solution offeredTo address customer's primary concern for leak-proofness, Tata BlueScope Steel suggested LYSAGHT KLIP-LOK 700 widest concealed roof system with LYSAGHT TRIMDEK as the liner panel. LYSAGHT KLIP-LOK made from high strength ZINCALUME steel has long been a design favourite for prestigious commercial, industrial and architectural projects across the globe. Not only performance, but with bold rib geometry rising from wide, flat pans, LYSAGHT KLIP-LOK roof provides a strong visual statement and its flat pans also offer excellent water carrying capacity. It is one of the strongest profiles with longer spanning capability. Absence of piercing and its special clip locking ensures zero chances of roof leakage. Tried and tested at NATA Lab (Australia), under rigorous cyclonic and non-cyclonic applications, LYSAGHT KLIP-LOK offers on-site roll forming preventing step joints and end laps. While the solution seemed straightforward, there were a few onsite challenges that had to be addressed going beyond standardisation, ensuring customer-centric solutions.Design challengeThere were too many undulations along the slope length of roof due to deflections in the main frame rafters and purlins. These undulations needed to be rectified to achieve leak-proof roof system.SolutionContour layout was conducted to measure the undulations at every 5 m along the roof length. Accordingly, supporting brackets with heights varying from 40 mm to 140 mm were designed and detailed to get the same level or plane of top sheet.Operational challengeFixing of LYSAGHT KLIP-LOK clip was a challenge, since sub-purlin line was not straight due to longitudinal misalignments of main purlins.SolutionSupporting brackets were designed and detailed to support sub-purlins. Alignment was made to bring the sub-purlins in line, parallel to building length to achieve KLIP-LOK clips in straight line.ConclusionProject completed with zero harm: New age construction technology from LYSAGHT team was put into place to enable the workforce to execute the job seamlessly. Due to safety training and regular supervision, the project was completed without any unsafe incidence.Right solution with on-time delivery: LYSAGHT team proposed the technically correct offer, which was eventually accepted by the customer. Furthermore, on site roll forming and excellent project management ensured on-time delivery.100 per cent leak-proof solution: Single length sheet of 60 m from ridge to eve avoided any joints and eliminated any kind of leakage. This also helped savings in lap lengths, thus reducing the input material and installation time. Since the customer was looking for a leak-proof roof, installation support and best quality workmanship were provided to achieve the desired objective. Inspections were undertaken on a daily basis to achieve the highest quality of installation.With collaborative team work, design optimisation and an efficient supply chain management, the project was successfully delivered to customer’s satisfaction.

Next Story
Real Estate

Capacit’e Infraprojects Wins Rs 6.21 billion order from Saifee Burhani Upliftment Trust

Capacit’e Infraprojects has secured a Letter of Intent (LOI) worth Rs 6.21 billion (excluding GST) from Saifee Burhani Upliftment Trust (SBUT) for the execution of core and shell works, finishing, MEPF services, and other associated components of the redevelopment project—Sector 07 of the Saifee Burhani Upliftment Project—located at Ward ‘C’, Bhendi Bazaar, Mumbai. This is the third repeat order from SBUT to Capacit’e Infraprojects, underscoring the trust and satisfaction of a long-standing client in the company’s project delivery capabilities. Commenting on the develop..

Next Story
Resources

K Raheja Corp's Volunteering Drive Brings Back-to-School Cheer for Underprivileged Kids

Real estate major K Raheja Corp concluded its latest community initiative under the ‘Time Off for Volunteering’ programme, titled Paint a Pair, Show You Care. Held in association with NGO ConnectFor, the campaign was part of a larger 'Back to School' drive aimed at supporting underprivileged students from the Jhanvi Charitable Trust. More than 45 employees from across group companies—Mindspace Business Parks, Chalet Hotels Ltd., K Raheja Corp Homes, and Inorbit Malls—came together to hand-paint over 60 pairs of canvas shoes for children preparing to return to school. Volunteers al..

Next Story
Infrastructure Urban

CCI Worldwide Logistics Launches ‘Trans Africa’ Freight Service

CCI Worldwide Logistics, the international freight forwarding arm of the CCI Group, has launched ‘Trans Africa’—a technology-led logistics platform aimed at streamlining cross-border trade across Africa. The company is investing Rs 1.06 billion in the initiative, targeting an annual freight volume of 5,000 TEUs by air and sea, with an estimated 15 per cent return on investment. The service is being rolled out in key markets such as Nigeria, Kenya, South Africa, Ghana, and Egypt, with planned expansion into Francophone West Africa, Central Africa, and landlocked nations including Uga..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?