MahaRERA grants relief to over 70 Ruparel Skygreens buyers
Real Estate

MahaRERA grants relief to over 70 Ruparel Skygreens buyers

In a recent order, the MahaRERA granted relief to over 70 homebuyers who had booked flats in the Ruparel Skygreens project in Borivli. The promoter had failed to deliver possession to the allottees, including those who had booked under the subvention scheme and the construction link plan scheme, by the agreed dates as well as by the MahaRERA completion date of December 2021.

MahaRERA Chairman Ajoy Mehta directed the promoter to refund the entire amounts received to some of the allottees with interest, while others would receive refunds without interest. He also instructed the promoter to execute and register cancellation deeds, cancel allotment letters and agreements for sale, and refund the amounts paid by the allottees. Additionally, possession with an occupancy certificate (OC) was to be handed over to certain allottees, along with interest for the delay, depending on the various reliefs sought.

However, the regulatory authority dismissed some complaints due to maintainability and lack of evidence. MahaRERA vacated a previous order that had restrained Piramal Capital & Housing Finance Limited from taking any coercive action, stating that it had determined the rights of the allottees and fixed the obligations of the promoter. The authority clarified that it did not have the mandate to adjudicate on the tripartite agreement binding the allottee, promoter, and lender, but directed the parties to strictly adhere to the terms of that agreement. The allottees had complained that the finance company had initiated proceedings under the SARFAESI Act.

The MahaRERA order acknowledged the complexities involved in executing a real estate project but noted that developers undertaking such projects are well aware of these issues. One of the allottees filed a complaint seeking a refund of amounts paid to the promoter due to the significant delay in handing over possession of a flat booked in 2017. The complainant stated that, according to the agreement, possession was to be delivered on or before December 2021.

The promoter had informed the complainant about the subvention scheme, which stipulated that the liability for payment until the physical possession of the flat would rest with the promoter, thereby ensuring that the complainants would not be burdened with any payment obligations until that time.

In a recent order, the MahaRERA granted relief to over 70 homebuyers who had booked flats in the Ruparel Skygreens project in Borivli. The promoter had failed to deliver possession to the allottees, including those who had booked under the subvention scheme and the construction link plan scheme, by the agreed dates as well as by the MahaRERA completion date of December 2021. MahaRERA Chairman Ajoy Mehta directed the promoter to refund the entire amounts received to some of the allottees with interest, while others would receive refunds without interest. He also instructed the promoter to execute and register cancellation deeds, cancel allotment letters and agreements for sale, and refund the amounts paid by the allottees. Additionally, possession with an occupancy certificate (OC) was to be handed over to certain allottees, along with interest for the delay, depending on the various reliefs sought. However, the regulatory authority dismissed some complaints due to maintainability and lack of evidence. MahaRERA vacated a previous order that had restrained Piramal Capital & Housing Finance Limited from taking any coercive action, stating that it had determined the rights of the allottees and fixed the obligations of the promoter. The authority clarified that it did not have the mandate to adjudicate on the tripartite agreement binding the allottee, promoter, and lender, but directed the parties to strictly adhere to the terms of that agreement. The allottees had complained that the finance company had initiated proceedings under the SARFAESI Act. The MahaRERA order acknowledged the complexities involved in executing a real estate project but noted that developers undertaking such projects are well aware of these issues. One of the allottees filed a complaint seeking a refund of amounts paid to the promoter due to the significant delay in handing over possession of a flat booked in 2017. The complainant stated that, according to the agreement, possession was to be delivered on or before December 2021. The promoter had informed the complainant about the subvention scheme, which stipulated that the liability for payment until the physical possession of the flat would rest with the promoter, thereby ensuring that the complainants would not be burdened with any payment obligations until that time.

Next Story
Real Estate

Dubai Real Estate Sales Reach AED48 Billion

Dubai’s real estate market recorded 13,977 sales transactions worth AED48 billion in April 2026, reflecting continued resilience across residential and commercial segments.According to a market update by fäm Properties, sales volume rose 3.5 per cent month-on-month compared to March, while total sales value increased by 10.7 per cent. The commercial sector, including offices and shops, recorded the strongest growth, with 561 transactions valued at AED4 billion, up 33.9 per cent year-on-year and 36.2 per cent month-on-month.Apartment sales rose 6.5 per cent month-on-month to 11,377 transacti..

Next Story
Real Estate

Casagrand Launches 35-Acre Hyderabad Project

Casagrand has launched Casagrand Vybe, its largest residential project in Hyderabad, spread across 35 acres in Rajendra Nagar. The launch marks the company’s fifth residential rollout in 2026 and strengthens its expansion momentum in the city.As part of its Hyderabad growth strategy, Casagrand is adding 3.98 million sq ft of residential space to its portfolio. Since entering the Hyderabad residential market in 2023, the company has scaled its presence with projects across key micro-markets. In 2025, it launched four projects — Casagrand Evon, Casagrand Windsor Court, Casagrand Belair and C..

Next Story
Technology

Bentley Event Spotlights AI Infrastructure

Bentley Systems recently hosted Illuminate Mumbai 2026, bringing together infrastructure leaders, policymakers, technology experts and academia to discuss how AI-driven engineering and digital twins can accelerate India’s journey towards Viksit Bharat 2047.The event focused on scaling intelligent and connected infrastructure ecosystems beyond digital adoption. Discussions covered the use of infrastructure AI, open data environments and digital twin technologies to improve project delivery, sustainability and long-term asset performance across key sectors.Kamalakannan Thiruvadi, Regional Exec..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement