MahaRERA lists 1,824 housing projects as expired
Real Estate

MahaRERA lists 1,824 housing projects as expired

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has listed down 1,824 housing projects across the state as ‘expired’ for exceeding completion deadlines set by the regulatory body.

The projects would now require approval from 51% buyers for obtaining an extension of the completion dates. 103 such projects overshot the completion deadline in 2017, 541 in 2018 and 1,180 in 2019.

According to Section 6 of the Real Estate (Regulation and Development) Act, many projects had failed to achieve even after an extension of one year.

As per the Act, the project developers are restricted from selling, advertising or marketing them before asking for an extension. Of the total 1,824 projects declared as expired by MahaRERA, extension applications of 350 projects have been presented.

MahaRERA had granted an extension to the deadlines till September for the projects that were supposed to be completed in March.

A MahaRERA official told the media that the remaining projects had deadlines before the pandemic year of 2020. Most of the projects are in Mumbai, Thane, Pune and Raigad. Another 1,500 projects might be under the scanner since their deadline got over in March 2021. The developers of these projects can now avail of a one-year extension under Section 6 of RERA.

Developers felt that the officials should take a considerate approach since the market had been down and there were challenges in getting documents within the deadline.

Anuj Puri, Anarock Property consultants chairman, told the media that the MahaRERA’s decision sent a strong signal to the errant developers delaying the projects.

Homebuyers have been waiting to get ownership of projects for the last three years.

Sunil Furde, CREDAI Maharashtra president, told the media that MahaRERA was correct in pointing out the status of the unfinished projects. However, many projects are displayed as incomplete due to technical errors.

He said projects of CREDAI members declared on the portal had been completed on time. The project completion certificate has been received from the municipal corporations before the listed dates. Some projects were achieved but the completion certificates were received later, he said.

Image Source


Also read: Out of 644 blacklisted realty projects in Maharashtra, 189 in Pune

Also read: More than 90 unfinished realty projects to shut down in UP: UP-RERA

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has listed down 1,824 housing projects across the state as ‘expired’ for exceeding completion deadlines set by the regulatory body. The projects would now require approval from 51% buyers for obtaining an extension of the completion dates. 103 such projects overshot the completion deadline in 2017, 541 in 2018 and 1,180 in 2019. According to Section 6 of the Real Estate (Regulation and Development) Act, many projects had failed to achieve even after an extension of one year. As per the Act, the project developers are restricted from selling, advertising or marketing them before asking for an extension. Of the total 1,824 projects declared as expired by MahaRERA, extension applications of 350 projects have been presented. MahaRERA had granted an extension to the deadlines till September for the projects that were supposed to be completed in March. A MahaRERA official told the media that the remaining projects had deadlines before the pandemic year of 2020. Most of the projects are in Mumbai, Thane, Pune and Raigad. Another 1,500 projects might be under the scanner since their deadline got over in March 2021. The developers of these projects can now avail of a one-year extension under Section 6 of RERA. Developers felt that the officials should take a considerate approach since the market had been down and there were challenges in getting documents within the deadline. Anuj Puri, Anarock Property consultants chairman, told the media that the MahaRERA’s decision sent a strong signal to the errant developers delaying the projects. Homebuyers have been waiting to get ownership of projects for the last three years. Sunil Furde, CREDAI Maharashtra president, told the media that MahaRERA was correct in pointing out the status of the unfinished projects. However, many projects are displayed as incomplete due to technical errors. He said projects of CREDAI members declared on the portal had been completed on time. The project completion certificate has been received from the municipal corporations before the listed dates. Some projects were achieved but the completion certificates were received later, he said. Image Source Also read: Out of 644 blacklisted realty projects in Maharashtra, 189 in Pune Also read: More than 90 unfinished realty projects to shut down in UP: UP-RERA

Next Story
Real Estate

Pecan Realty Completes Rs 1.5 Billion Transactions

Pecan Realty has recently completed four institutional transactions worth over Rs 1.5 billion over the past two years, strengthening its position as an execution-led real estate platform. The deals include resolution-led acquisitions, structured finance transactions and capital partnerships across its development portfolio.The transactions covered acquisitions through the National Company Law Tribunal process and helped provide repayment or exits to both private and public sector lenders. The company said the deals demonstrate its ability to resolve complex project situations, work with instit..

Next Story
Real Estate

SNN Estates Expands North Bengaluru Housing Project

SNN Estates has announced an expansion of its SNN Estates Felicity residential project in North Bengaluru following strong buyer demand, with 75 per cent of the first-phase inventory sold within three days of launch.The developer will add 76 apartments in the new phase, taking the project's estimated revenue potential to around Rs 1,000 crore upon completion of Phase 2.Spread across 6.5 acres in Rachenahalli, near Manyata Tech Park, the project comprises 604 apartments in 1.5, 2, 2.5, 3 and 4 BHK configurations. The development includes a 50,000-sq-ft clubhouse with amenities such as sports co..

Next Story
Infrastructure Urban

SCG Drives ASEAN Industrial Transformation Strategy

SCG is strengthening its focus on ASEAN as a key growth region by advancing industrial transformation, enhancing competitiveness and building resilient regional value chains. Thammasak Sethaudom, President and Chief Executive Officer, SCG, highlighted the need for industries to continuously develop capabilities, strengthen resilience and deepen regional cooperation to achieve sustainable long-term growth.SCG views ASEAN as an important growth engine alongside China, supported by favourable demographics, trade connectivity and investment flows. With ASEAN’s GDP projected to grow by around 4.7..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement