MahaRERA lists 1,824 housing projects as expired
Real Estate

MahaRERA lists 1,824 housing projects as expired

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has listed down 1,824 housing projects across the state as ‘expired’ for exceeding completion deadlines set by the regulatory body.

The projects would now require approval from 51% buyers for obtaining an extension of the completion dates. 103 such projects overshot the completion deadline in 2017, 541 in 2018 and 1,180 in 2019.

According to Section 6 of the Real Estate (Regulation and Development) Act, many projects had failed to achieve even after an extension of one year.

As per the Act, the project developers are restricted from selling, advertising or marketing them before asking for an extension. Of the total 1,824 projects declared as expired by MahaRERA, extension applications of 350 projects have been presented.

MahaRERA had granted an extension to the deadlines till September for the projects that were supposed to be completed in March.

A MahaRERA official told the media that the remaining projects had deadlines before the pandemic year of 2020. Most of the projects are in Mumbai, Thane, Pune and Raigad. Another 1,500 projects might be under the scanner since their deadline got over in March 2021. The developers of these projects can now avail of a one-year extension under Section 6 of RERA.

Developers felt that the officials should take a considerate approach since the market had been down and there were challenges in getting documents within the deadline.

Anuj Puri, Anarock Property consultants chairman, told the media that the MahaRERA’s decision sent a strong signal to the errant developers delaying the projects.

Homebuyers have been waiting to get ownership of projects for the last three years.

Sunil Furde, CREDAI Maharashtra president, told the media that MahaRERA was correct in pointing out the status of the unfinished projects. However, many projects are displayed as incomplete due to technical errors.

He said projects of CREDAI members declared on the portal had been completed on time. The project completion certificate has been received from the municipal corporations before the listed dates. Some projects were achieved but the completion certificates were received later, he said.

Image Source


Also read: Out of 644 blacklisted realty projects in Maharashtra, 189 in Pune

Also read: More than 90 unfinished realty projects to shut down in UP: UP-RERA

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has listed down 1,824 housing projects across the state as ‘expired’ for exceeding completion deadlines set by the regulatory body. The projects would now require approval from 51% buyers for obtaining an extension of the completion dates. 103 such projects overshot the completion deadline in 2017, 541 in 2018 and 1,180 in 2019. According to Section 6 of the Real Estate (Regulation and Development) Act, many projects had failed to achieve even after an extension of one year. As per the Act, the project developers are restricted from selling, advertising or marketing them before asking for an extension. Of the total 1,824 projects declared as expired by MahaRERA, extension applications of 350 projects have been presented. MahaRERA had granted an extension to the deadlines till September for the projects that were supposed to be completed in March. A MahaRERA official told the media that the remaining projects had deadlines before the pandemic year of 2020. Most of the projects are in Mumbai, Thane, Pune and Raigad. Another 1,500 projects might be under the scanner since their deadline got over in March 2021. The developers of these projects can now avail of a one-year extension under Section 6 of RERA. Developers felt that the officials should take a considerate approach since the market had been down and there were challenges in getting documents within the deadline. Anuj Puri, Anarock Property consultants chairman, told the media that the MahaRERA’s decision sent a strong signal to the errant developers delaying the projects. Homebuyers have been waiting to get ownership of projects for the last three years. Sunil Furde, CREDAI Maharashtra president, told the media that MahaRERA was correct in pointing out the status of the unfinished projects. However, many projects are displayed as incomplete due to technical errors. He said projects of CREDAI members declared on the portal had been completed on time. The project completion certificate has been received from the municipal corporations before the listed dates. Some projects were achieved but the completion certificates were received later, he said. Image Source Also read: Out of 644 blacklisted realty projects in Maharashtra, 189 in Pune Also read: More than 90 unfinished realty projects to shut down in UP: UP-RERA

Next Story
Infrastructure Transport

Modi Launches Rs 318.5 Billion Projects in Maharashtra

Prime Minister Narendra Modi on Wednesday launched infrastructure projects worth Rs 318.5 billion during his two-day visit to Maharashtra, including two landmark developments — the first phase of the Rs 196.5 billion Navi Mumbai International Airport (NMIA) and the second phase of the Rs 122 billion Mumbai Metro Line 3. India’s first fully digitised airport, NMIA, has been designed for multimodal connectivity and is being developed under a public-private partnership between Adani Airport Holdings, which holds a 74 per cent stake, and the City and Industrial Development Corporation of Maha..

Next Story
Real Estate

Tata Housing Sells Rs 10 Billion Homes in Bengaluru

Real estate developer Tata Housing on Wednesday announced that it has achieved home sales worth over Rs 10 billion in its newly launched residential project in Bengaluru, driven by strong demand. In a statement, the company said Tata Housing Varnam Phase I — part of the 135-acre integrated township Carnatica in North Bengaluru — has surpassed Rs 10 billion in sales since its launch in August 2025. Spread across 20 acres, Varnam Phase I has recorded sales of 377 units out of 582 apartments, along with 48 townhouses and row houses. The project has attracted substantial interest from both e..

Next Story
Infrastructure Transport

OMRON to Train 1,000 Graduates Annually at Bengaluru Centre

Japanese industrial automation giant OMRON announced on Wednesday that it will train and skill 1,000 fresh engineering graduates annually at its newly launched Automation Centre in Bengaluru. The initiative aims to enhance India’s employable manufacturing talent and build a resilient, future-ready industrial ecosystem. Motohiro Yamanishi, President of the Industrial Automation Company at OMRON Corporation, said, “We see immense potential in the dynamism of India’s manufacturing sector. The new Automation Centre underscores India’s vital role in our global and Asia-Pacific vision. It i..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?