MahaRERA lists 1,824 housing projects as expired
Real Estate

MahaRERA lists 1,824 housing projects as expired

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has listed down 1,824 housing projects across the state as ‘expired’ for exceeding completion deadlines set by the regulatory body.

The projects would now require approval from 51% buyers for obtaining an extension of the completion dates. 103 such projects overshot the completion deadline in 2017, 541 in 2018 and 1,180 in 2019.

According to Section 6 of the Real Estate (Regulation and Development) Act, many projects had failed to achieve even after an extension of one year.

As per the Act, the project developers are restricted from selling, advertising or marketing them before asking for an extension. Of the total 1,824 projects declared as expired by MahaRERA, extension applications of 350 projects have been presented.

MahaRERA had granted an extension to the deadlines till September for the projects that were supposed to be completed in March.

A MahaRERA official told the media that the remaining projects had deadlines before the pandemic year of 2020. Most of the projects are in Mumbai, Thane, Pune and Raigad. Another 1,500 projects might be under the scanner since their deadline got over in March 2021. The developers of these projects can now avail of a one-year extension under Section 6 of RERA.

Developers felt that the officials should take a considerate approach since the market had been down and there were challenges in getting documents within the deadline.

Anuj Puri, Anarock Property consultants chairman, told the media that the MahaRERA’s decision sent a strong signal to the errant developers delaying the projects.

Homebuyers have been waiting to get ownership of projects for the last three years.

Sunil Furde, CREDAI Maharashtra president, told the media that MahaRERA was correct in pointing out the status of the unfinished projects. However, many projects are displayed as incomplete due to technical errors.

He said projects of CREDAI members declared on the portal had been completed on time. The project completion certificate has been received from the municipal corporations before the listed dates. Some projects were achieved but the completion certificates were received later, he said.

Image Source


Also read: Out of 644 blacklisted realty projects in Maharashtra, 189 in Pune

Also read: More than 90 unfinished realty projects to shut down in UP: UP-RERA

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has listed down 1,824 housing projects across the state as ‘expired’ for exceeding completion deadlines set by the regulatory body. The projects would now require approval from 51% buyers for obtaining an extension of the completion dates. 103 such projects overshot the completion deadline in 2017, 541 in 2018 and 1,180 in 2019. According to Section 6 of the Real Estate (Regulation and Development) Act, many projects had failed to achieve even after an extension of one year. As per the Act, the project developers are restricted from selling, advertising or marketing them before asking for an extension. Of the total 1,824 projects declared as expired by MahaRERA, extension applications of 350 projects have been presented. MahaRERA had granted an extension to the deadlines till September for the projects that were supposed to be completed in March. A MahaRERA official told the media that the remaining projects had deadlines before the pandemic year of 2020. Most of the projects are in Mumbai, Thane, Pune and Raigad. Another 1,500 projects might be under the scanner since their deadline got over in March 2021. The developers of these projects can now avail of a one-year extension under Section 6 of RERA. Developers felt that the officials should take a considerate approach since the market had been down and there were challenges in getting documents within the deadline. Anuj Puri, Anarock Property consultants chairman, told the media that the MahaRERA’s decision sent a strong signal to the errant developers delaying the projects. Homebuyers have been waiting to get ownership of projects for the last three years. Sunil Furde, CREDAI Maharashtra president, told the media that MahaRERA was correct in pointing out the status of the unfinished projects. However, many projects are displayed as incomplete due to technical errors. He said projects of CREDAI members declared on the portal had been completed on time. The project completion certificate has been received from the municipal corporations before the listed dates. Some projects were achieved but the completion certificates were received later, he said. Image Source Also read: Out of 644 blacklisted realty projects in Maharashtra, 189 in Pune Also read: More than 90 unfinished realty projects to shut down in UP: UP-RERA

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code