+
Supply chain management at Bogibeel Bridge
Real Estate

Supply chain management at Bogibeel Bridge

India recently welcomed one of its biggest landmarks! The country’s longest rail-cum-road bridge—Bogibeel Bridge over river Brahmaputra in Assam—was recently inaugurated, after having encountered several engineering and other challenges, almost 22 years after its foundation stone was laid in January 1997.

HCC follows the Just-In-Time (JIT) inventory system where it produces or acquires materials and products as per demand. This is a key component of its supply chain. At the Bogibeel Bridge project, the team used a combination of rail and road transport to deliver 80,000 tonne of steel plates from various parts of the country to the remote project site in Assam. The orders for extra wide plates were placed in advance as per the design of the superstructure. In this way, the team avoided any possible mismatch of material and ensured qualitative and timely execution of the job.

“The steel used in the construction of the bridge is special grade, confined to E410CBC,” says RVR Kishore, Project Director, HCC. Steel plates and sections were procured mainly from three sources: JSPL, Essar and SAIL. Of these 80,000 mt, about 20,000 mt (25 per cent scope) was categorised as ODC (over dimension cargo) and attracted special measures for transport to the project site from the sources in Hazira and Angul.

A procurement plan was made according to minimum order quantity required thickness-wise, also estimating future market price trends as the order lot sizes range from 3,500 mt to 10,000 mt. Also, for the construction of the bridge, Kishore adds, “Plasma cutting machines for the cutting of material, automated-box making machines, levelling machines and robotic welding machines were imported from Canada.”

India recently welcomed one of its biggest landmarks! The country’s longest rail-cum-road bridge—Bogibeel Bridge over river Brahmaputra in Assam—was recently inaugurated, after having encountered several engineering and other challenges, almost 22 years after its foundation stone was laid in January 1997. HCC follows the Just-In-Time (JIT) inventory system where it produces or acquires materials and products as per demand. This is a key component of its supply chain. At the Bogibeel Bridge project, the team used a combination of rail and road transport to deliver 80,000 tonne of steel plates from various parts of the country to the remote project site in Assam. The orders for extra wide plates were placed in advance as per the design of the superstructure. In this way, the team avoided any possible mismatch of material and ensured qualitative and timely execution of the job. “The steel used in the construction of the bridge is special grade, confined to E410CBC,” says RVR Kishore, Project Director, HCC. Steel plates and sections were procured mainly from three sources: JSPL, Essar and SAIL. Of these 80,000 mt, about 20,000 mt (25 per cent scope) was categorised as ODC (over dimension cargo) and attracted special measures for transport to the project site from the sources in Hazira and Angul. A procurement plan was made according to minimum order quantity required thickness-wise, also estimating future market price trends as the order lot sizes range from 3,500 mt to 10,000 mt. Also, for the construction of the bridge, Kishore adds, “Plasma cutting machines for the cutting of material, automated-box making machines, levelling machines and robotic welding machines were imported from Canada.”

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code