Tenders should mandate at least 30-40% use of precast or prefab components
Real Estate

Tenders should mandate at least 30-40% use of precast or prefab components

- MV Satish, Whole-Time Director & Senior Executive Vice-President  (Buildings, Minerals & Metals), Larsen & Toubro

With the aim to construct 1.2 crore homes to ensure Housing for All by 2022, the Pradhan Mantri Awas Yojana-Urban (PMAY-U) calls for out-of-the-box, innovative thinking. And so, the government has launched the Global Housing Technology Challenge (GHTC) to look for new, emerging, disaster-resilient, environment-friendly, cost-effective and speedy construction technologies. “As it is important to bring in a technology transition to avail of the best technologies globally, GHTC will help bridge the demand-supply gap in the affordable housing sector,” says MV Satish, Whole-Time Director & Senior Executive Vice President (Buildings, Minerals & Metals), Larsen & Toubro (L&T). In this segment, the company is constructing about 89,300 flats or apartments of varying sizes – 300 sq ft, 365 sq ft and 435 sq ft over a total built-up area of 31 million sq ft – across several districts in Andhra Pradesh. L&T is also actively looking at a few emerging technologies to hasten this process, adds Satish, as he shares his thoughts on the affordable housing segment with SERAPHINA D’SOUZA.

What is the average time currently taken for per square feet development of affordable housing units?
Aluminium formwork is one of the construction methods being increasingly used to reduce execution time and costs. Time taken using aluminium formwork is not measured in square feet completed but in time taken to cast floor slabs. This is called cycle time, which includes the time to set up the formwork for casting, tying reinforcement, pouring concrete, concrete setting and removal of formwork. At present, we are executing residential projects at a rate of seven days per floor slab for RCC works. All these jobs have stringent delivery schedules of 
15 months. 

What are your requirements in terms of technologies for constructing houses in a shorter period of time for faster project delivery? 
L&T has been at the forefront of adopting frontier technologies, having been first to introduce tunnel formwork and aluminium system formwork in India, in residential construction, over a decade and a half ago. With these, an entire floor slab can be cast monolithically to significantly decrease execution time. There is definitely a need to mechanise construction activities offsite to reduce construction time, but that will be affordable only when the volume of construction 
is high.While various technologies are available from across the globe to quicken the pace of construction, the need for a more enabling environment is critical, in which technology transfer and adoption can be easier. 

Specific focus is now on prefabricated construction, where not only is the structural system precast but the overall building finishing and MEP works completed in a factory, with the finished units being assembled at site. A similar approach has recently been adopted by the Singapore Government, which has mandated the use of precast prefabricated volumetric construction (PPVC) for finished kitchens, bedrooms and bathroom units.

With reference to government-funded projects, the first requirement is for tenders to be based on technology, rather than leaving them technology-neutral. This will create a level playing field for contractors who are willing and capable of adopting superior technologies without being outpriced in the bidding process. 
At the same time, prequalification criteria need to be relaxed to promote new technologies. 

Tenders should mandate at least 30-40 per cent use of precast or prefab structural components.
The government should sponsor or subsidise research programmes of technology providers and offer incentives to contractors to adopt new technologies. From the perspective of the Bureau of Indian Standards (BIS), there is a need to customise codal requirements for affordable housing to reduce material consumption (which is a major contributor to increasing construction costs) and for the adoption of international standards in the absence of equivalent Indian codes or their extremely old versions. Even from an architectural standpoint, it is imperative to lay down standard specifications for modular units, their dimensions, for doors, windows and the like, to enable modular construction.

Are there any global technologies India should adopt to hasten the construction of affordable housing?
The precast large concrete panel system is widely regarded as a technology to hasten construction of affordable housing. Globally, the precast construction market is expected to reach $185.23 billion by 2022 at a CAGR of 6.3 per cent according to Allied Market Research. This technology has already been well accepted and adopted in the Middle East, Southeast Asia, China and Europe. It is being introduced in India, too, and we foresee its widespread use in the country soon.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

- MV Satish, Whole-Time Director & Senior Executive Vice-President  (Buildings, Minerals & Metals), Larsen & ToubroWith the aim to construct 1.2 crore homes to ensure Housing for All by 2022, the Pradhan Mantri Awas Yojana-Urban (PMAY-U) calls for out-of-the-box, innovative thinking. And so, the government has launched the Global Housing Technology Challenge (GHTC) to look for new, emerging, disaster-resilient, environment-friendly, cost-effective and speedy construction technologies. “As it is important to bring in a technology transition to avail of the best technologies globally, GHTC will help bridge the demand-supply gap in the affordable housing sector,” says MV Satish, Whole-Time Director & Senior Executive Vice President (Buildings, Minerals & Metals), Larsen & Toubro (L&T). In this segment, the company is constructing about 89,300 flats or apartments of varying sizes – 300 sq ft, 365 sq ft and 435 sq ft over a total built-up area of 31 million sq ft – across several districts in Andhra Pradesh. L&T is also actively looking at a few emerging technologies to hasten this process, adds Satish, as he shares his thoughts on the affordable housing segment with SERAPHINA D’SOUZA.What is the average time currently taken for per square feet development of affordable housing units?Aluminium formwork is one of the construction methods being increasingly used to reduce execution time and costs. Time taken using aluminium formwork is not measured in square feet completed but in time taken to cast floor slabs. This is called cycle time, which includes the time to set up the formwork for casting, tying reinforcement, pouring concrete, concrete setting and removal of formwork. At present, we are executing residential projects at a rate of seven days per floor slab for RCC works. All these jobs have stringent delivery schedules of 15 months. What are your requirements in terms of technologies for constructing houses in a shorter period of time for faster project delivery? L&T has been at the forefront of adopting frontier technologies, having been first to introduce tunnel formwork and aluminium system formwork in India, in residential construction, over a decade and a half ago. With these, an entire floor slab can be cast monolithically to significantly decrease execution time. There is definitely a need to mechanise construction activities offsite to reduce construction time, but that will be affordable only when the volume of construction is high.While various technologies are available from across the globe to quicken the pace of construction, the need for a more enabling environment is critical, in which technology transfer and adoption can be easier. Specific focus is now on prefabricated construction, where not only is the structural system precast but the overall building finishing and MEP works completed in a factory, with the finished units being assembled at site. A similar approach has recently been adopted by the Singapore Government, which has mandated the use of precast prefabricated volumetric construction (PPVC) for finished kitchens, bedrooms and bathroom units.With reference to government-funded projects, the first requirement is for tenders to be based on technology, rather than leaving them technology-neutral. This will create a level playing field for contractors who are willing and capable of adopting superior technologies without being outpriced in the bidding process. At the same time, prequalification criteria need to be relaxed to promote new technologies. Tenders should mandate at least 30-40 per cent use of precast or prefab structural components.The government should sponsor or subsidise research programmes of technology providers and offer incentives to contractors to adopt new technologies. From the perspective of the Bureau of Indian Standards (BIS), there is a need to customise codal requirements for affordable housing to reduce material consumption (which is a major contributor to increasing construction costs) and for the adoption of international standards in the absence of equivalent Indian codes or their extremely old versions. Even from an architectural standpoint, it is imperative to lay down standard specifications for modular units, their dimensions, for doors, windows and the like, to enable modular construction.Are there any global technologies India should adopt to hasten the construction of affordable housing?The precast large concrete panel system is widely regarded as a technology to hasten construction of affordable housing. Globally, the precast construction market is expected to reach $185.23 billion by 2022 at a CAGR of 6.3 per cent according to Allied Market Research. This technology has already been well accepted and adopted in the Middle East, Southeast Asia, China and Europe. It is being introduced in India, too, and we foresee its widespread use in the country soon.

Next Story
Real Estate

Pecan Realty Completes Rs 1.5 Billion Transactions

Pecan Realty has recently completed four institutional transactions worth over Rs 1.5 billion over the past two years, strengthening its position as an execution-led real estate platform. The deals include resolution-led acquisitions, structured finance transactions and capital partnerships across its development portfolio.The transactions covered acquisitions through the National Company Law Tribunal process and helped provide repayment or exits to both private and public sector lenders. The company said the deals demonstrate its ability to resolve complex project situations, work with instit..

Next Story
Real Estate

SNN Estates Expands North Bengaluru Housing Project

SNN Estates has announced an expansion of its SNN Estates Felicity residential project in North Bengaluru following strong buyer demand, with 75 per cent of the first-phase inventory sold within three days of launch.The developer will add 76 apartments in the new phase, taking the project's estimated revenue potential to around Rs 1,000 crore upon completion of Phase 2.Spread across 6.5 acres in Rachenahalli, near Manyata Tech Park, the project comprises 604 apartments in 1.5, 2, 2.5, 3 and 4 BHK configurations. The development includes a 50,000-sq-ft clubhouse with amenities such as sports co..

Next Story
Infrastructure Urban

SCG Drives ASEAN Industrial Transformation Strategy

SCG is strengthening its focus on ASEAN as a key growth region by advancing industrial transformation, enhancing competitiveness and building resilient regional value chains. Thammasak Sethaudom, President and Chief Executive Officer, SCG, highlighted the need for industries to continuously develop capabilities, strengthen resilience and deepen regional cooperation to achieve sustainable long-term growth.SCG views ASEAN as an important growth engine alongside China, supported by favourable demographics, trade connectivity and investment flows. With ASEAN’s GDP projected to grow by around 4.7..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement