373 projects show cost overruns of Rs 3.89 trillion
ECONOMY & POLICY

373 projects show cost overruns of Rs 3.89 trillion

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects.

Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months.

Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months. Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

Next Story
Resources

Gyproc India concludes ‘Beyond Dimensions’ design challenge

Gyproc India successfully hosted the finale of its flagship national design challenge, ‘Beyond Dimensions with Gyproc’, in Mumbai. Aimed at nurturing sustainability-focused innovation among young architects and designers, the event drew over 800 teams from 120 colleges across India. The Top 8 finalists presented forward-thinking concepts to a jury comprising Ar. Kavitha Selvaraj, Ar. Manish Dikshit, and Shailee Goswami. The top three winning teams—Anurag Singh & Kashish Gala (Rachana Sansad), Afeefah Hoda & Keerthi S, and Naveen Raja & Mohamed Yahya (RVS Padmavathy)—will now head to D..

Next Story
Infrastructure Energy

Stride Green raises US$3.5 million in seed round

Stride Green, a climate-tech asset financing and lifecycle management platform, has raised US$3.5 million in a seed funding round led by Micelio Technology Fund and Incubate Fund Asia, along with other strategic investors. The capital will help scale Stride Green’s tech-driven financing and leasing offerings across clean sectors like electric mobility, battery storage, and renewables. Funds will also support team expansion and future capability building. Founded by Ishpreet Gandhi and Vivek Jain, Stride Green aims to bridge financing gaps in early-stage clean technologies. Its proprietary ..

Next Story
Infrastructure Transport

CM Fadnavis opens last stretch of 701-km Samruddhi Mahamarg

Maharashtra Chief Minister Devendra Fadnavis inaugurated the final 76-km stretch of the Hinduhrudaysamrat Balasaheb Thackeray Maharashtra Samruddhi Mahamarg on 5th June 2025, marking the full commissioning of the 701-km Mumbai-Nagpur expressway. The inauguration ceremony, held in Thane district, was attended by Deputy Chief Ministers Eknath Shinde and Ajit Pawar, along with key officials linked to the project. The newly opened Igatpuri–Amane section completes the six-lane, access-controlled corridor designed to enhance high-speed connectivity across the state. With the expressway n..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?