373 projects show cost overruns of Rs 3.89 trillion
ECONOMY & POLICY

373 projects show cost overruns of Rs 3.89 trillion

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects.

Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months.

Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months. Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

Next Story
Infrastructure Urban

India Spent Rs 1.5 Tn on Smart Cities in Past 10 Years

The Indian government launched the Smart Cities Mission on June 15, 2015, with the goal of transforming urban infrastructure across the country. As of April 11, 2025, ten years since its inception, over Rs 1.5 trillion has been spent on 7,504 completed projects, representing 94 per cent of the total planned projects valued at more than Rs 1.64 trillion. An additional Rs 131.42 billion worth of projects are currently under implementation. According to data from SBI Research, 92 per cent of the funds were utilised across 21 major states, with Uttar Pradesh, Tamil Nadu, and Maharashtra together ..

Next Story
Infrastructure Energy

Hyundai’s EcoGram Converts Gurugram’s Waste to Clean Energy

Hyundai’s EcoGram, a biogas plant and material recovery facility located in Gurugram, Haryana, has been established to support circular economy initiatives. The facility collects both wet and dry waste from 20 bulk waste generators, including residential welfare associations (RWAs), corporate offices, and commercial complexes, with assistance from the Municipal Corporation of Gurugram (MCG). At the facility, the collected waste undergoes processing—wet waste is converted into biogas, which is then used to generate electricity, while dry waste is sorted for recycling. Since its inception,..

Next Story
Infrastructure Transport

Metro Line 8 DPR Nears Completion; CIDCO to Float Rs 200 Bn Tenders

The City and Industrial Development Corporation (CIDCO) is nearing completion of the Detailed Project Report (DPR) for Metro Line 8, commonly known as the Gold Line. This strategic 34.9-kilometre corridor is set to link Mumbai’s Chhatrapati Shivaji Maharaj International Airport (CSMIA) with the upcoming Navi Mumbai International Airport (NMIA). Estimated to cost around Rs 200 billion, the project is being developed under the Public-Private Partnership (PPP) model. Once completed, Metro Line 8 will become Mumbai's second such corridor after Metro Line 1. CIDCO plans to float tenders once ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?