373 projects show cost overruns of Rs 3.89 trillion
ECONOMY & POLICY

373 projects show cost overruns of Rs 3.89 trillion

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects.

Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months.

Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months. Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

Next Story
Infrastructure Transport

Cabinet Approves Key Highway and Rail Projects in Bihar Region

The Union Cabinet on Wednesday approved the four-laning of the 84.2-km Mokama-Munger section of the Buxar-Bhagalpur high-speed corridor, a key industrial region in poll-bound Bihar. The Cabinet also sanctioned the doubling of the 177-km Bhagalpur-Dumka-Rampurhat railway line, which passes through Bihar, Jharkhand, and West Bengal, at a cost of Rs 31.7 billion.The Rs 44.5 billion highway project will be constructed under the hybrid annuity model, a variant of public-private partnership. The Mokama-Munger stretch was the only remaining two-lane section of the 363-km Buxar-Bhagalpur corridor. Fou..

Next Story
Infrastructure Transport

NGT Issues Notice on Bengaluru Twin Tunnel Project

The National Green Tribunal (NGT) on Wednesday issued notices in response to a petition filed by Bengaluru Praja Vedike and others, challenging the Bengaluru twin tunnel road project. Petitioners claim the project was “hastily announced” and bypassed mandatory environmental impact assessment procedures.Notices have been served to the Karnataka Government, Greater Bengaluru Authority, State Environment Impact Assessment Authority (SEIAA), Bengaluru Smart Infrastructure Ltd (B-SMILE), the Union Ministry of Environment, Forest and Climate Change, and project consultants.The 16.74-km twin-tube..

Next Story
Real Estate

India’s Residential Sales to Dip Slightly in FY26

Residential sales in India’s seven major cities are projected to decline by up to 3 per cent year-on-year in FY26 to 620–640 million square feet (msf), amid a moderation in sales velocity, according to ratings agency Icra.In FY25, sales stood at 643 msf, down 8 per cent YoY, following a sharp contraction in new launches and moderated demand in the affordable and mid-income segments. This slowdown came after the sector posted a robust compound annual growth rate of 26 per cent in area sales between FY22 and FY24.Icra noted: “Having seen a strong upcycle, the sector entered an equilibrium ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?