APTEL Orders Tariff Review For 10 MW Punjab Rooftop Solar
ECONOMY & POLICY

APTEL Orders Tariff Review For 10 MW Punjab Rooftop Solar

The Appellate Tribunal for Electricity (APTEL) granted partial relief to Radiance Punjab Renewable Private Limited in a dispute over its 10 megawatt (MW) rooftop solar project in Punjab. The Punjab State Electricity Regulatory Commission (PSERC) had reduced the contracted tariff from Rs seven point five nine per kWh to Rs five point zero nine per kWh after recognising only a 29-day delay in achieving the Commercial Operation Date (COD). The developer contested the order and sought recognition of further delays as Force Majeure.

The project began in March 2015 when the developer's predecessor won a competitive bid by the Punjab Energy Development Agency (PEDA) and signed an Implementation Agreement and a Power Purchase Agreement (PPA) with the Punjab State Power Corporation Limited (PSPCL). The PPA required commissioning within 10 months. The company said factors beyond its control caused the delays.

In its appeal the company identified three delay periods: a 41-day lapse in regulatory approval of the PPA, 127 days lost to site finalisation and grid connectivity, and a 10-day disruption from the Jat agitation. The state utilities argued the developer failed to issue a formal Force Majeure notice, but APTEL observed that a PPA becomes enforceable only after State Commission approval and that the delay in approval was the responsibility of the state utility, so it allowed the 41-day extension. The Tribunal upheld PSERC's calculation on the site and grid delays.

APTEL declined relief for the 10-day Jat agitation period because the developer had not served the mandatory contractual notice. The tribunal partly allowed the appeal and directed PSERC to recalculate delays for each of the nine rooftop solar sites and to determine the applicable tariff on the revised timelines. Regulators will therefore revisit tariff outcomes for the affected projects.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Appellate Tribunal for Electricity (APTEL) granted partial relief to Radiance Punjab Renewable Private Limited in a dispute over its 10 megawatt (MW) rooftop solar project in Punjab. The Punjab State Electricity Regulatory Commission (PSERC) had reduced the contracted tariff from Rs seven point five nine per kWh to Rs five point zero nine per kWh after recognising only a 29-day delay in achieving the Commercial Operation Date (COD). The developer contested the order and sought recognition of further delays as Force Majeure. The project began in March 2015 when the developer's predecessor won a competitive bid by the Punjab Energy Development Agency (PEDA) and signed an Implementation Agreement and a Power Purchase Agreement (PPA) with the Punjab State Power Corporation Limited (PSPCL). The PPA required commissioning within 10 months. The company said factors beyond its control caused the delays. In its appeal the company identified three delay periods: a 41-day lapse in regulatory approval of the PPA, 127 days lost to site finalisation and grid connectivity, and a 10-day disruption from the Jat agitation. The state utilities argued the developer failed to issue a formal Force Majeure notice, but APTEL observed that a PPA becomes enforceable only after State Commission approval and that the delay in approval was the responsibility of the state utility, so it allowed the 41-day extension. The Tribunal upheld PSERC's calculation on the site and grid delays. APTEL declined relief for the 10-day Jat agitation period because the developer had not served the mandatory contractual notice. The tribunal partly allowed the appeal and directed PSERC to recalculate delays for each of the nine rooftop solar sites and to determine the applicable tariff on the revised timelines. Regulators will therefore revisit tariff outcomes for the affected projects.

Next Story
Infrastructure Transport

Railways To Operate Over 300 Special Trains For Rath Yatra

Union Railway Minister Ashwini Vaishnaw announced that Indian Railways (IR) will operate more than 300 special trains for the annual Jagannath Rath Yatra in Odisha and over 100 special trains during the Onam festival in Keralam. He flagged off the Nanded–Mumbai and Tanakpur–Nanded Express trains and inaugurated the extension of the Tanakpur–Pilibhit service up to Shahjahanpur via video conference from Rail Sadan in Bhubaneswar. He noted that the summer season, which concluded on 30 June, had seen a record 15,000 special trains. Vaishnaw stated that the newly launched services are intende..

Next Story
Infrastructure Transport

Vande Bharat Express To Start From Tripura Soon

Tripura Chief Minister Manik Saha said the Vande Bharat Express will commence operations from Tripura in the coming days after he flagged off the Agartala–Karimganj MEMU service at Agartala Railway Station. He recalled the rail history of the state, noting that a metre-gauge service first arrived in 1964 and that broad gauge reached Agartala in 2008 following national projects and later upgrades under the Act East policy. The event was described as a milestone for regional connectivity and the MEMU was presented as the first electric passenger train to originate from Tripura.\n\nSaha said he..

Next Story
Infrastructure Urban

MEMU Suspension Disrupts Commuters Between Vadodara And Dahod

The Vadodara–Dahod Mainline Electric Multiple Unit (MEMU) service has been temporarily suspended for 26 days after its rake was diverted to Odisha to manage the surge in passenger traffic during the annual Rath Yatra in Puri. Indian Railways redeployed several MEMU rakes from different zones to meet the additional travel demand for the festival scheduled from the seventh of July to the second of August. As a result, train numbers 69233 and 69234 operating between Vadodara and Dahod will remain cancelled for the duration. Railway authorities advised passengers to use alternative train service..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement