APTEL Orders Tariff Review For 10 MW Punjab Rooftop Solar
ECONOMY & POLICY

APTEL Orders Tariff Review For 10 MW Punjab Rooftop Solar

The Appellate Tribunal for Electricity (APTEL) granted partial relief to Radiance Punjab Renewable Private Limited in a dispute over its 10 megawatt (MW) rooftop solar project in Punjab. The Punjab State Electricity Regulatory Commission (PSERC) had reduced the contracted tariff from Rs seven point five nine per kWh to Rs five point zero nine per kWh after recognising only a 29-day delay in achieving the Commercial Operation Date (COD). The developer contested the order and sought recognition of further delays as Force Majeure.

The project began in March 2015 when the developer's predecessor won a competitive bid by the Punjab Energy Development Agency (PEDA) and signed an Implementation Agreement and a Power Purchase Agreement (PPA) with the Punjab State Power Corporation Limited (PSPCL). The PPA required commissioning within 10 months. The company said factors beyond its control caused the delays.

In its appeal the company identified three delay periods: a 41-day lapse in regulatory approval of the PPA, 127 days lost to site finalisation and grid connectivity, and a 10-day disruption from the Jat agitation. The state utilities argued the developer failed to issue a formal Force Majeure notice, but APTEL observed that a PPA becomes enforceable only after State Commission approval and that the delay in approval was the responsibility of the state utility, so it allowed the 41-day extension. The Tribunal upheld PSERC's calculation on the site and grid delays.

APTEL declined relief for the 10-day Jat agitation period because the developer had not served the mandatory contractual notice. The tribunal partly allowed the appeal and directed PSERC to recalculate delays for each of the nine rooftop solar sites and to determine the applicable tariff on the revised timelines. Regulators will therefore revisit tariff outcomes for the affected projects.

The Appellate Tribunal for Electricity (APTEL) granted partial relief to Radiance Punjab Renewable Private Limited in a dispute over its 10 megawatt (MW) rooftop solar project in Punjab. The Punjab State Electricity Regulatory Commission (PSERC) had reduced the contracted tariff from Rs seven point five nine per kWh to Rs five point zero nine per kWh after recognising only a 29-day delay in achieving the Commercial Operation Date (COD). The developer contested the order and sought recognition of further delays as Force Majeure. The project began in March 2015 when the developer's predecessor won a competitive bid by the Punjab Energy Development Agency (PEDA) and signed an Implementation Agreement and a Power Purchase Agreement (PPA) with the Punjab State Power Corporation Limited (PSPCL). The PPA required commissioning within 10 months. The company said factors beyond its control caused the delays. In its appeal the company identified three delay periods: a 41-day lapse in regulatory approval of the PPA, 127 days lost to site finalisation and grid connectivity, and a 10-day disruption from the Jat agitation. The state utilities argued the developer failed to issue a formal Force Majeure notice, but APTEL observed that a PPA becomes enforceable only after State Commission approval and that the delay in approval was the responsibility of the state utility, so it allowed the 41-day extension. The Tribunal upheld PSERC's calculation on the site and grid delays. APTEL declined relief for the 10-day Jat agitation period because the developer had not served the mandatory contractual notice. The tribunal partly allowed the appeal and directed PSERC to recalculate delays for each of the nine rooftop solar sites and to determine the applicable tariff on the revised timelines. Regulators will therefore revisit tariff outcomes for the affected projects.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code