Around 425 infra projects note cost overruns worth Rs 4.83 lakh cr
ECONOMY & POLICY

Around 425 infra projects note cost overruns worth Rs 4.83 lakh cr

According to a report, around 425 infrastructure projects, each entailing a Rs 150 crore or more investment, have been hit by cost overruns of over Rs 4.83 lakh crore.

According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and above, out of 1,579 projects, 425 projects declared cost overruns, and around 664 projects were delayed.

The ministry's latest report for March 2022 said, the total original cost of execution of the 1,579 projects was Rs 21,95,196.72 crore, and their expected completion cost is likely to be Rs 26,78,365.62 crore, which reflects total cost overruns of Rs 4,83,168.90 crore.

According to the report, the cost incurred on these projects till March 2022 stood at Rs 13,88,760.73 crore, which is 51.85 % of the expected cost of the projects.

However, the number of delayed projects is reduced to 561 if the delay is estimated based on the latest completion schedule.

Further, for 606 projects, neither the year of commissioning nor the tentative gestation period has been notified.

Out of the 664 delayed projects, 124 have been delayed for 13-24 months, 331 projects for 25-60 months, 94 for 1-12 months, 115 projects for 61 months, and more.

In these 664 delayed projects, the average time overrun was 42.41 months.

Reasons for time overruns as informed by various project executing agencies include delay in land acquisition, lack of infrastructure support and linkages, and delay in obtaining forest and environment clearances.

Delay in tendering, ordering, and equipment supply, delay in tie-up for project financing, change in scope, delay in finalisation of detailed engineering, and law and order problems are among the other reasons.

The report also mentioned state-wise lockdowns due to Covid-19 as a reason for the delay in execution of these projects.

It has also been observed that project agencies are not reporting revised cost estimations and commissioning schedules for many projects, which indicates that time and cost overrun figures are under-reported.

Image Source

Also read: 443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report

According to a report, around 425 infrastructure projects, each entailing a Rs 150 crore or more investment, have been hit by cost overruns of over Rs 4.83 lakh crore. According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and above, out of 1,579 projects, 425 projects declared cost overruns, and around 664 projects were delayed. The ministry's latest report for March 2022 said, the total original cost of execution of the 1,579 projects was Rs 21,95,196.72 crore, and their expected completion cost is likely to be Rs 26,78,365.62 crore, which reflects total cost overruns of Rs 4,83,168.90 crore. According to the report, the cost incurred on these projects till March 2022 stood at Rs 13,88,760.73 crore, which is 51.85 % of the expected cost of the projects. However, the number of delayed projects is reduced to 561 if the delay is estimated based on the latest completion schedule. Further, for 606 projects, neither the year of commissioning nor the tentative gestation period has been notified. Out of the 664 delayed projects, 124 have been delayed for 13-24 months, 331 projects for 25-60 months, 94 for 1-12 months, 115 projects for 61 months, and more. In these 664 delayed projects, the average time overrun was 42.41 months. Reasons for time overruns as informed by various project executing agencies include delay in land acquisition, lack of infrastructure support and linkages, and delay in obtaining forest and environment clearances. Delay in tendering, ordering, and equipment supply, delay in tie-up for project financing, change in scope, delay in finalisation of detailed engineering, and law and order problems are among the other reasons. The report also mentioned state-wise lockdowns due to Covid-19 as a reason for the delay in execution of these projects. It has also been observed that project agencies are not reporting revised cost estimations and commissioning schedules for many projects, which indicates that time and cost overrun figures are under-reported. Image Source Also read: 443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report

Related Stories

Gold Stories

Next Story
Infrastructure Energy

Asian Energy Services Q1 FY27 PAT Rises 129 Per Cent

Asian Energy Services Limited reported a 129 per cent year-on-year rise in net profit to Rs 128 million for Q1 FY27, compared with the corresponding quarter last year.Revenue increased 135 per cent year-on-year to Rs 2.71 billion, supported by continued momentum across its services business, disciplined execution and contributions from domestic and international operations. EBITDA grew 81 per cent year-on-year during the quarter.As of June 30, 2026, the company’s standalone order book stood at Rs 17.54 billion, with around 60 per cent coming from oil and gas services and 40 per cent from min..

Next Story
Infrastructure Urban

BioBTX to Build First Commercial-Scale Circular Chemicals Plant

Dutch circular chemistry technology developer BioBTX is building what it says will be the world’s first commercial-scale plant to convert mixed plastic waste into high-quality aromatic chemicals using its proprietary Integrated Catalytic Cracking Process (ICCP) technology.The facility will be built at Chemical Park Delfzijl on the northern coast of the Netherlands and is expected to create 35 jobs. Covestro, which has been a shareholder and strategic partner of BioBTX since 2024, holds a mid-single-digit million-euro investment in the company.BioBTX’s ICCP technology uses catalytic pyrolys..

Next Story
Real Estate

Awfis Q1 FY27 PAT Jumps 140% as Revenue Rises 27%

Awfis Space Solutions reported a 140 per cent year-on-year rise in consolidated profit after tax (PAT) to Rs 240 million for Q1 FY27, compared with Rs 100 million in the corresponding quarter last year.Revenue from operations increased 27 per cent to Rs 4.25 billion from Rs 3.35 billion, while EBITDA rose 28 per cent to Rs 1.62 billion. EBITDA margin improved to 38.2 per cent from 37.8 per cent. Profit before tax increased 135 per cent to Rs 240 million.The company's co-working business recorded 27 per cent year-on-year growth, supported by demand from enterprises, Global Capability Centres (G..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement