CAG Audit Reveals Lapses in YEIDA's Policies
ECONOMY & POLICY

CAG Audit Reveals Lapses in YEIDA's Policies

The Yamuna Expressway Industrial Development Authority (YEIDA), which is responsible for developing the area around the upcoming Noida International Airport, has faced criticism from the Comptroller and Auditor General (CAG) for major lapses in policy and procedures during the 16-year period from 2005 to 2021. These issues have contributed to the country’s biggest stalled project problems, particularly when considering the combined challenges faced by YEIDA, Noida, and Greater Noida, despite various government and court interventions.

One of the key irregularities highlighted by the CAG was YEIDA's allotment of residential township and group housing plots, which led to financial losses of Rs 42.26 billion. The CAG found that the eligibility criteria for these schemes were insufficient, allowing applicants with minimal financial capacity to bid for high-value plots, resulting in a mismatch between the scale of projects and the bidders' capabilities. In some instances, developers secured plots valued up to 18 times their declared net worth. These issues mirrored those found in previous audits of the Noida Authority.

YEIDA had allotted 14 residential township plots, ranging from 2.5 lakh square meters to 8 lakh square meters, under three schemes for the construction of plotted and flatted residential dwellings between 2010 and 2011. After subdividing one plot into two, sub-leases were granted by four allottees to 11 sub-lessees, and by one sub-lessee to three others, resulting in a total of 29 allottees. Of these, 16 plots were either cancelled or surrendered, and 13 experienced delays, leading to overdue amounts of Rs 41.85 billion as of September 30, 2022.

Additionally, between February 2011 and September 2014, YEIDA allotted five group housing plots under three schemes, with sizes ranging from 82,346 square meters to 1.37 lakh square meters. Three of these plots were cancelled, and one plot was partially surrendered by the allottee. The projects on the remaining plots, including the partially surrendered one, faced delays.

The CAG pointed out that YEIDA’s eligibility conditions were inconsistent with the size and value of the plots, applying the same technical and financial criteria to both smaller and larger plots. This allowed applicants with insufficient capabilities to secure high-value projects. For example, Greenbay Infrastructure obtained a 4 lakh square meter plot in Sector 22D worth Rs 1.92 billion, despite showing minimal completed construction, resulting in long delays and dues of Rs 7.03 billion by September 30, 2022. Similarly, Orris Developers secured an 8 lakh square meter plot in Sector 22D valued at Rs 3.88 billion, despite not meeting technical eligibility criteria, and faced delays with dues amounting to Rs 9.89 billion.

In several cases, minor consortium members were allowed to meet 100 per cent of the eligibility criteria, even when the lead members did not meet the requirements. One example was Sunworld City, which was allotted a 4 lakh square meter plot in Sector 22D worth Rs 1.95 billion, despite none of the lead members meeting the financial or technical requirements. This project was delayed by more than five years, with dues exceeding Rs 7.03 billion.

The CAG also criticized YEIDA for permitting sub-leases without evaluating the capabilities of sub-lessees to execute projects or pay dues, which resulted in financial losses. For instance, Orris Developers sub-leased land to ATS Realty in Sector 22D at a significantly higher price than the original allotment, resulting in undue profit of at least Rs 1.03 billion. YEIDA did not levy transfer charges in such cases, leading to a direct revenue loss of Rs 280 million.

The auditor highlighted YEIDA’s leniency toward defaulting allottees, pointing out that penalties for delayed lease deed execution were insufficient to cover lease rent losses. YEIDA also failed to cancel allotments despite significant delays in submitting layout plans, completing development work, and adhering to floor area ratio. For example, Supertech Township Project secured a 4 lakh square meter plot in Sector 22D worth Rs 1.93 billion by submitting "tampered documents," resulting in prolonged delays and unpaid dues.

YEIDA was also found to have granted unwarranted benefits to allottees, including allowing them to retain excess land, not forfeiting prescribed amounts on cancelled allotments, and granting "zero periods" without justification. Furthermore, the scheme brochures lacked safeguards, such as provisions for recovering post-allotment cost increases, opening escrow accounts, or obtaining performance bank guarantees, leaving YEIDA financially vulnerable.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Yamuna Expressway Industrial Development Authority (YEIDA), which is responsible for developing the area around the upcoming Noida International Airport, has faced criticism from the Comptroller and Auditor General (CAG) for major lapses in policy and procedures during the 16-year period from 2005 to 2021. These issues have contributed to the country’s biggest stalled project problems, particularly when considering the combined challenges faced by YEIDA, Noida, and Greater Noida, despite various government and court interventions. One of the key irregularities highlighted by the CAG was YEIDA's allotment of residential township and group housing plots, which led to financial losses of Rs 42.26 billion. The CAG found that the eligibility criteria for these schemes were insufficient, allowing applicants with minimal financial capacity to bid for high-value plots, resulting in a mismatch between the scale of projects and the bidders' capabilities. In some instances, developers secured plots valued up to 18 times their declared net worth. These issues mirrored those found in previous audits of the Noida Authority. YEIDA had allotted 14 residential township plots, ranging from 2.5 lakh square meters to 8 lakh square meters, under three schemes for the construction of plotted and flatted residential dwellings between 2010 and 2011. After subdividing one plot into two, sub-leases were granted by four allottees to 11 sub-lessees, and by one sub-lessee to three others, resulting in a total of 29 allottees. Of these, 16 plots were either cancelled or surrendered, and 13 experienced delays, leading to overdue amounts of Rs 41.85 billion as of September 30, 2022. Additionally, between February 2011 and September 2014, YEIDA allotted five group housing plots under three schemes, with sizes ranging from 82,346 square meters to 1.37 lakh square meters. Three of these plots were cancelled, and one plot was partially surrendered by the allottee. The projects on the remaining plots, including the partially surrendered one, faced delays. The CAG pointed out that YEIDA’s eligibility conditions were inconsistent with the size and value of the plots, applying the same technical and financial criteria to both smaller and larger plots. This allowed applicants with insufficient capabilities to secure high-value projects. For example, Greenbay Infrastructure obtained a 4 lakh square meter plot in Sector 22D worth Rs 1.92 billion, despite showing minimal completed construction, resulting in long delays and dues of Rs 7.03 billion by September 30, 2022. Similarly, Orris Developers secured an 8 lakh square meter plot in Sector 22D valued at Rs 3.88 billion, despite not meeting technical eligibility criteria, and faced delays with dues amounting to Rs 9.89 billion. In several cases, minor consortium members were allowed to meet 100 per cent of the eligibility criteria, even when the lead members did not meet the requirements. One example was Sunworld City, which was allotted a 4 lakh square meter plot in Sector 22D worth Rs 1.95 billion, despite none of the lead members meeting the financial or technical requirements. This project was delayed by more than five years, with dues exceeding Rs 7.03 billion. The CAG also criticized YEIDA for permitting sub-leases without evaluating the capabilities of sub-lessees to execute projects or pay dues, which resulted in financial losses. For instance, Orris Developers sub-leased land to ATS Realty in Sector 22D at a significantly higher price than the original allotment, resulting in undue profit of at least Rs 1.03 billion. YEIDA did not levy transfer charges in such cases, leading to a direct revenue loss of Rs 280 million. The auditor highlighted YEIDA’s leniency toward defaulting allottees, pointing out that penalties for delayed lease deed execution were insufficient to cover lease rent losses. YEIDA also failed to cancel allotments despite significant delays in submitting layout plans, completing development work, and adhering to floor area ratio. For example, Supertech Township Project secured a 4 lakh square meter plot in Sector 22D worth Rs 1.93 billion by submitting tampered documents, resulting in prolonged delays and unpaid dues. YEIDA was also found to have granted unwarranted benefits to allottees, including allowing them to retain excess land, not forfeiting prescribed amounts on cancelled allotments, and granting zero periods without justification. Furthermore, the scheme brochures lacked safeguards, such as provisions for recovering post-allotment cost increases, opening escrow accounts, or obtaining performance bank guarantees, leaving YEIDA financially vulnerable.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement