Centre projects costs rise to a 1 year high in April
ECONOMY & POLICY

Centre projects costs rise to a 1 year high in April

In April, cost overruns in central government projects surged to a 12-month peak, reaching 20.09%, as revealed by data released by the government on Tuesday. This marked an increase from 18.65% in the previous month. The total value of 1,838 projects, each valued at Rs 1.50 billion and above, amounted to Rs 33.2 trillion, exceeding the original cost by Rs 5.6 trillion.

Of these projects, 43% (792) were delayed compared to their original completion dates, while 514 experienced delays in both completion time and cost. In April, 61 projects were successfully completed, while 29 new projects were initiated, with completed projects costing Rs 466 billion and new projects estimated at Rs 1.3 trillion.

Despite the surge in cost overruns, the average time for project completion decreased to 35.4 months, down from 36.04 months in March. However, a concerning trend emerged, with 48% of projects experiencing delays of over two years. Notably, 54 projects, representing only 2.93% of the total, accounted for 43.39% of the total cost overrun and 21.34% of the total time overrun.

Among various sectors, railways encountered the highest cost overruns in April, standing at 126.5%, with more than half of its projects facing such issues. Meanwhile, road transport and highways, constituting nearly 60% of the projects, experienced a cost overrun ratio of 23.7%. Additionally, over one-third of railway projects and more than 10% of road projects reported time overruns, according to government data.

Despite these challenges, the government remains committed to infrastructure development, as recognised by international agencies as a key driver of economic growth. Projections suggest a growth rate of 7.8% for FY24, with an expected growth of 6.8% in the current fiscal year. (ET Infra)

In April, cost overruns in central government projects surged to a 12-month peak, reaching 20.09%, as revealed by data released by the government on Tuesday. This marked an increase from 18.65% in the previous month. The total value of 1,838 projects, each valued at Rs 1.50 billion and above, amounted to Rs 33.2 trillion, exceeding the original cost by Rs 5.6 trillion. Of these projects, 43% (792) were delayed compared to their original completion dates, while 514 experienced delays in both completion time and cost. In April, 61 projects were successfully completed, while 29 new projects were initiated, with completed projects costing Rs 466 billion and new projects estimated at Rs 1.3 trillion. Despite the surge in cost overruns, the average time for project completion decreased to 35.4 months, down from 36.04 months in March. However, a concerning trend emerged, with 48% of projects experiencing delays of over two years. Notably, 54 projects, representing only 2.93% of the total, accounted for 43.39% of the total cost overrun and 21.34% of the total time overrun. Among various sectors, railways encountered the highest cost overruns in April, standing at 126.5%, with more than half of its projects facing such issues. Meanwhile, road transport and highways, constituting nearly 60% of the projects, experienced a cost overrun ratio of 23.7%. Additionally, over one-third of railway projects and more than 10% of road projects reported time overruns, according to government data. Despite these challenges, the government remains committed to infrastructure development, as recognised by international agencies as a key driver of economic growth. Projections suggest a growth rate of 7.8% for FY24, with an expected growth of 6.8% in the current fiscal year. (ET Infra)

Next Story
Infrastructure Urban

Welspun Enterprises Wins 910 MLD Panjrapur WTP Contract

Welspun Enterprises (WEL), the infrastructure and energy arm of Welspun World, has secured a major contract from the Brihanmumbai Municipal Corporation (BMC) to design, build and operate a 910 million litres per day (MLD) Water Treatment Plant (WTP) at Panjrapur, Maharashtra.Valued at approximately Rs 31.45 billion, the project encompasses end-to-end civil, mechanical, electrical and instrumentation works, including the construction of a treated water sump and pumping station. Of the total value, nearly Rs 11.56 billion is allocated to Operations & Maintenance (O&M), with an additional..

Next Story
Infrastructure Energy

Mitsubishi Power Wins Boiler Upgrade Contract for O Mon 1 Plant

Mitsubishi Power, a power solutions brand of Mitsubishi Heavy Industries, (MHI), has been awarded a contract to support the oil-to-natural-gas fuel conversion at the O Mon 1 Thermal Power Plant in Can Tho, southern Vietnam. As the OEM of the plant’s existing boiler, Mitsubishi Power will supply key equipment—including new gas burners—and implement a selective catalytic reduction (SCR) system to reduce NOx emissions and help the plant meet stricter environmental standards.The O Mon 1 facility includes two 330 MW units that commenced operations in 2009 and 2015, with all major equipment or..

Next Story
Equipment

Liebherr’s 10,000th XPower Wheel Loader Joins BERGER’s Fleet

BERGER Rohstoffe GmbH has welcomed the 10,000th Liebherr XPower wheel loader to its operations at the Schlag granite quarry in Passau. The milestone machine, officially handed over at Liebherr’s Bischofshofen plant in May 2025, underscores the long-standing partnership between BERGER, Liebherr, and the Beutlhauser Group. Equipped with Liebherr’s signature power-split travel drive, the new L 580 XPower is already delivering strong results under demanding quarry conditions.At the Schlag quarry, BERGER Rohstoffe processes approximately 200,000 tonnes of Bayerwald granite annually into high-qu..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement