+
Vadhvan Port HAM Tender Deadline Extended By Three Months
ECONOMY & POLICY

Vadhvan Port HAM Tender Deadline Extended By Three Months

Vadhvan Port Project Ltd has extended the bid submission deadline for the Rs 223.235 billion Hybrid Annuity Model contract for offshore reclamation, dredging and construction of the port's protective bund by three months to May 18. The delay reflects ongoing statutory processes for land acquisition for road and rail connectivity. Officials said the extension aligns tendering with ground access timelines.

The Assam chief minister outlined that the award for land acquisition is expected soon but taking possession will require additional time. The planned 32-km highway linking NH 48 at Tawa Junction to the port has been notified as a national highway, with acquisition costs to be borne by Vadhvan Port Project Ltd. Authorities emphasised that the approach road is critical for transporting heavy materials and that construction cannot commence without it.

The mega-port comprises three components: near-shore reclamation with supporting infrastructure, a breakwater planned to be the longest for an Indian port, and offshore reclamation for the main port area. Near-shore reclamation was awarded in December 2024 to Cemindia Projects Limited, formerly ITD Cementation India Ltd, but work is limited to pre-construction surveys until land access is secured. There are four bidders for the breakwater while financial offers will be opened only after central security clearance.

The largest HAM component covering dredging, offshore reclamation and construction of the protective bund cannot start until the breakwater reaches 40 to 50 per cent completion to provide wave protection. Officials cautioned that premature awarding could lead to idle work, cost escalation and arbitration risks. Vadhvan Port Project Ltd, a joint venture between the Jawaharlal Nehru Port Authority with 74 per cent and the Maharashtra Maritime Board with 26 per cent, is implementing India’s largest public port project with a projected capacity of 298 million tonnes and 23.2 million TEUs. The port is expected to commence operations in 2029–30, underscoring the importance of coordinated execution and connectivity.

Vadhvan Port Project Ltd has extended the bid submission deadline for the Rs 223.235 billion Hybrid Annuity Model contract for offshore reclamation, dredging and construction of the port's protective bund by three months to May 18. The delay reflects ongoing statutory processes for land acquisition for road and rail connectivity. Officials said the extension aligns tendering with ground access timelines. The Assam chief minister outlined that the award for land acquisition is expected soon but taking possession will require additional time. The planned 32-km highway linking NH 48 at Tawa Junction to the port has been notified as a national highway, with acquisition costs to be borne by Vadhvan Port Project Ltd. Authorities emphasised that the approach road is critical for transporting heavy materials and that construction cannot commence without it. The mega-port comprises three components: near-shore reclamation with supporting infrastructure, a breakwater planned to be the longest for an Indian port, and offshore reclamation for the main port area. Near-shore reclamation was awarded in December 2024 to Cemindia Projects Limited, formerly ITD Cementation India Ltd, but work is limited to pre-construction surveys until land access is secured. There are four bidders for the breakwater while financial offers will be opened only after central security clearance. The largest HAM component covering dredging, offshore reclamation and construction of the protective bund cannot start until the breakwater reaches 40 to 50 per cent completion to provide wave protection. Officials cautioned that premature awarding could lead to idle work, cost escalation and arbitration risks. Vadhvan Port Project Ltd, a joint venture between the Jawaharlal Nehru Port Authority with 74 per cent and the Maharashtra Maritime Board with 26 per cent, is implementing India’s largest public port project with a projected capacity of 298 million tonnes and 23.2 million TEUs. The port is expected to commence operations in 2029–30, underscoring the importance of coordinated execution and connectivity.

Next Story
Equipment

Kabelschlepp India Installs Robotic VMC in Bengaluru

Kabelschlepp India, part of the Tsubaki Group, has installed a state-of-the-art Vertical Machining Center (VMC) integrated with robotic automation at its Bengaluru facility. The inauguration was held in the presence of Henning Preis, President & CEO, Kabelschlepp Group, Jörg Schulz, Vice President – Production, and Srinivas P. Kamisetty, Managing Director, Kabelschlepp India.The high-precision CNC VMC is designed for advanced milling, drilling, tapping and multi-axis machining. Equipped with a vertical spindle orientation, automatic tool changer and intelligent CNC control system, it en..

Next Story
Infrastructure Transport

Highway Delivery Reset!

Project delays and inefficiencies continue to bedevil the progress of India’s National Highways network. A multi-pronged reform agenda is needed to inject greater transparency and accountability at every stage – from planning and procurement to execution, maintenance and oversight. This article offers key recommendations and reform strategies that government stakeholders – from the Ministry of Road Transport & Highways (MoRTH) and the National Highways Authority of India (NHAI) to state agencies and oversight bodies – should pursue to put highway development on a better track.Decen..

Next Story
Infrastructure Transport

MSIDC Executes ₹37,000 Crore Road Programme

With Rs 37,000 crore worth of road projects under execution across Maharashtra, Maharashtra State Infrastructure Development Corporation (MSIDC) is driving one of the state’s largest infrastructure programmes. Dr Brijesh Dixit, Managing Director, discusses the institutional reforms, execution frameworks, financing strategies and technology adoption enabling timely, high-quality delivery, in conversation with PRATAP PADODE, Editor-in-Chief, CW.With over Rs 37,000 crore worth of road projects underway across districts – many under tight timelines – what institutional and executio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App