Supply chain management at Bogibeel Bridge
Real Estate

Supply chain management at Bogibeel Bridge

India recently welcomed one of its biggest landmarks! The country’s longest rail-cum-road bridge—Bogibeel Bridge over river Brahmaputra in Assam—was recently inaugurated, after having encountered several engineering and other challenges, almost 22 years after its foundation stone was laid in January 1997.

HCC follows the Just-In-Time (JIT) inventory system where it produces or acquires materials and products as per demand. This is a key component of its supply chain. At the Bogibeel Bridge project, the team used a combination of rail and road transport to deliver 80,000 tonne of steel plates from various parts of the country to the remote project site in Assam. The orders for extra wide plates were placed in advance as per the design of the superstructure. In this way, the team avoided any possible mismatch of material and ensured qualitative and timely execution of the job.

“The steel used in the construction of the bridge is special grade, confined to E410CBC,” says RVR Kishore, Project Director, HCC. Steel plates and sections were procured mainly from three sources: JSPL, Essar and SAIL. Of these 80,000 mt, about 20,000 mt (25 per cent scope) was categorised as ODC (over dimension cargo) and attracted special measures for transport to the project site from the sources in Hazira and Angul.

A procurement plan was made according to minimum order quantity required thickness-wise, also estimating future market price trends as the order lot sizes range from 3,500 mt to 10,000 mt. Also, for the construction of the bridge, Kishore adds, “Plasma cutting machines for the cutting of material, automated-box making machines, levelling machines and robotic welding machines were imported from Canada.”

India recently welcomed one of its biggest landmarks! The country’s longest rail-cum-road bridge—Bogibeel Bridge over river Brahmaputra in Assam—was recently inaugurated, after having encountered several engineering and other challenges, almost 22 years after its foundation stone was laid in January 1997. HCC follows the Just-In-Time (JIT) inventory system where it produces or acquires materials and products as per demand. This is a key component of its supply chain. At the Bogibeel Bridge project, the team used a combination of rail and road transport to deliver 80,000 tonne of steel plates from various parts of the country to the remote project site in Assam. The orders for extra wide plates were placed in advance as per the design of the superstructure. In this way, the team avoided any possible mismatch of material and ensured qualitative and timely execution of the job. “The steel used in the construction of the bridge is special grade, confined to E410CBC,” says RVR Kishore, Project Director, HCC. Steel plates and sections were procured mainly from three sources: JSPL, Essar and SAIL. Of these 80,000 mt, about 20,000 mt (25 per cent scope) was categorised as ODC (over dimension cargo) and attracted special measures for transport to the project site from the sources in Hazira and Angul. A procurement plan was made according to minimum order quantity required thickness-wise, also estimating future market price trends as the order lot sizes range from 3,500 mt to 10,000 mt. Also, for the construction of the bridge, Kishore adds, “Plasma cutting machines for the cutting of material, automated-box making machines, levelling machines and robotic welding machines were imported from Canada.”

Next Story
Infrastructure Transport

JNPA Becomes First Indian Port to Cross 10 Million TEU Capacity

The Jawaharlal Nehru Port Authority (JNPA), located at Uran in Navi Mumbai, has become the first port in India to achieve over 10 million TEUs (twenty-foot equivalent units) in container handling capacity.With the recent expansion, the port now operates five container terminals with a combined capacity of 10.4 million TEUs, alongside two liquid and two general cargo terminals.Handling more than half of India’s container traffic, JNPA processed 7.05 million TEUs in 2024 and has moved 15.39 million tonnes of containers and 16.64 million tonnes of total cargo in the first two months of FY 2025..

Next Story
Infrastructure Transport

Nod for Rs. 36.26 billion Expansion of Pune Metro Line 2

The Union Cabinet has approved the Rs.36.26 billion expansion of Pune Metro Line 2, adding 12.75 km of track and 13 new stations to improve east–west connectivity across the city.The project aims to link Pune’s urban core with rapidly growing suburbs, supporting the city’s rising demand for efficient and sustainable transport solutions. This expansion is part of Corridor 2 of the Pune Metro and includes two key routes: Vanaz to Chandani Chowk (Corridor 2A) and Ramwadi to Wagholi/Vitthalwadi (Corridor 2B).It will connect residential, IT, and educational hubs in areas such as Bavdhan, Koth..

Next Story
Infrastructure Transport

Assembly begins for ‘Nayak’ TBM on Thane– Borivali Twin Tunnel Project

The assembly of ‘Nayak’, the first of four Tunnel Boring Machines (TBMs) for the Thane–Borivali Twin Tube Tunnel Project, has commenced at the Thane site. Built by German firm Herrenknecht AG and deployed by Megha Engineering & Infrastructure (MEIL), the TBM marks a key milestone in Mumbai’s ambitious 11.8-km underground road corridor beneath Sanjay Gandhi National Park.The twin tunnels will reduce the Thane–Borivali travel distance by 12 km and decongest Thane Ghodbunder Road. ‘Nayak’, with a 13.2-metre diameter, is designed to bore through challenging geological conditions ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?