Phase II Of Chennai Metro to be completed in 6 years
AVIATION & AIRPORTS

Phase II Of Chennai Metro to be completed in 6 years

Chennai Metro Rail Ltd (CMRL) aims to complete phase II of the metro rail project in six years, equipped with detailed design and lessons from past experiences.

With three corridors, SIPCOT-Madhavaram, Madhavaram-Sholinganallur, and Light House-Poonamallee, Phase II will stretch 118.9 km from the northernmost tip to the southernmost tip of the city of Chennai.

The extensive design component and land acquisition, according to CMRL officials, are the prime reasons for the delay. The design lists more refined information about how to construct a station, tunnel or viaduct. In the case of phase II, however, almost 90% of the detailed design has already been completed. A large portion of the land was bought, and officials said the task of obtaining the remaining portions is ongoing.

An official said the contractor had to design and develop the stations in Phase I, which resulted in a slowdown. Furthermore, in some areas, land acquisition was not easy. Thus, ahead of construction, they agreed to start with the detailed design and gave those firms contracts. Contractors have now done much of the work, and the remaining designs will be available soon. The official added that those designs would be handed over to the contractors so they can commence work immediately.

Another official said the Phase II project could face other challenges that would require good planning and execution. Underground stations have to be installed in congested areas, such as Purasawalkam, Perambur and Royapettah, in the Madhavaram-SIPCOT stretch, without impacting surrounding buildings.

The official said that diligent traffic preparation needs to be there so that passengers do not have to waste fuel and lose time. The moving of utility lines needs to be achieved in coordination with other departments. Even if one of them is not performed correctly, it will cause chaos, significantly hamper the execution, and make commuters' lives challenging. They should make sure the contractors adhere to deadlines of metro construction.

CMRL has floated civil work tenders with aims to issue contracts and construction is expected to begin next year.

Chennai Metro Rail Ltd (CMRL) aims to complete phase II of the metro rail project in six years, equipped with detailed design and lessons from past experiences.With three corridors, SIPCOT-Madhavaram, Madhavaram-Sholinganallur, and Light House-Poonamallee, Phase II will stretch 118.9 km from the northernmost tip to the southernmost tip of the city of Chennai. The extensive design component and land acquisition, according to CMRL officials, are the prime reasons for the delay. The design lists more refined information about how to construct a station, tunnel or viaduct. In the case of phase II, however, almost 90% of the detailed design has already been completed. A large portion of the land was bought, and officials said the task of obtaining the remaining portions is ongoing. An official said the contractor had to design and develop the stations in Phase I, which resulted in a slowdown. Furthermore, in some areas, land acquisition was not easy. Thus, ahead of construction, they agreed to start with the detailed design and gave those firms contracts. Contractors have now done much of the work, and the remaining designs will be available soon. The official added that those designs would be handed over to the contractors so they can commence work immediately. Another official said the Phase II project could face other challenges that would require good planning and execution. Underground stations have to be installed in congested areas, such as Purasawalkam, Perambur and Royapettah, in the Madhavaram-SIPCOT stretch, without impacting surrounding buildings. The official said that diligent traffic preparation needs to be there so that passengers do not have to waste fuel and lose time. The moving of utility lines needs to be achieved in coordination with other departments. Even if one of them is not performed correctly, it will cause chaos, significantly hamper the execution, and make commuters' lives challenging. They should make sure the contractors adhere to deadlines of metro construction. CMRL has floated civil work tenders with aims to issue contracts and construction is expected to begin next year.

Next Story
Infrastructure Urban

Jyoti Structures FY26 profit rises 56.5%

Jyoti Structures (JSL) recently reported strong financial results for the quarter and year ended 31 March 2026, driven by disciplined execution, cost management and steady progress across its order book.For Q4 FY2025-26, total income rose 44.2 per cent to Rs 2.41 billion from Rs 1.67 billion in Q4 FY2024-25. EBITDA increased 58.6 per cent to Rs 237 million, while EBITDA margin improved by 89 basis points to 9.84 per cent. Profit before tax grew 53.3 per cent to Rs 188.5 million, and net profit rose 51.9 per cent to Rs 181.4 million.For FY2025-26, total income grew 53.1 per cent to Rs 7.72 bill..

Next Story
Infrastructure Energy

Cat BEPU to Power Doppstadt Separator at IFAT 2026

Caterpillar’s Cat Battery Electric Power Unit (BEPU) has been selected by Doppstadt to power its SWS 6 Spiral Shaft Separator, which will be showcased for the first time at IFAT 2026 in Munich, Germany, from 4–7 May.The compact plug-and-play BEPU is designed to replace a diesel engine within the same space, using the same mounting locations and relative machine position. It integrates the battery, motor, inverter, onboard charging, cooling and controls, enabling OEMs to electrify existing chassis platforms without extensive redesign.Caterpillar and Cat dealer Zeppelin Power Systems have be..

Next Story
Infrastructure Urban

VECV sales rise 6.9% in April 2026

VE Commercial Vehicles, a joint venture between Volvo Group and Eicher Motors, recorded sales of 7,318 units in April 2026, compared to 6,846 units in April 2025, registering 6.9 per cent growth. The total included 7,159 units under the Eicher brand and 159 units under the Volvo brand.Eicher branded trucks and buses reported sales of 7,159 units during the month, up 6.6 per cent from 6,717 units in April 2025. In the domestic commercial vehicle market, Eicher sales rose 8.6 per cent to 6,797 units from 6,257 units a year earlier.Exports declined 21.3 per cent, with VECV recording 362 units in ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement