‘Sudarshan’ bores 1.5-km tunnel for Delhi-Meerut RRTS
ROADS & HIGHWAYS

‘Sudarshan’ bores 1.5-km tunnel for Delhi-Meerut RRTS

The tunnelling work for the country's first Regional Rapid Transit System (RRTS) has moved into the next phase with the construction of a tunnel of around 1.5 km length from Anand Vihar to New Ashok Nagar, according to an official statement.

The National Capital Region Transport Corporation (NCRTC) is implementing India's first Regional Rapid Transit System between Delhi and Meerut. The Delhi-Ghaziabad-Meerut corridor is 82 km long, of which 14 km is in Delhi. The Delhi section has four stations: Jangpura, Sarai Kale Khan, New Ashok Nagar and Anand Vihar, with only the Anand Vihar station being underground.

Two 'Sudarshan' tunnel boring machines are in operation to construct two three-km-long parallel tunnels from Anand Vihar station to New Ashok Nagar. The first Sudarshan 4.1 has already bored 1.5 km tunnel, while the second Sudarshan 4.2 has also constructed about 1km of tunnel so far.

To retrieve these Sudarshan machines after the completion of the construction of the tunnels, a retrieving shaft has been built near the New Ashok Nagar station, from where the corridor gets elevated.

The tunnel segments are being manufactured at NCRTC's casting yard. Due to the large rolling stock and a high design speed of 180 mph, the width of RRTS tunnels is being constructed as 6.5 metre diameter, the statement said.

See also:
TBMs to begin working on Chennai Metro Phase II in Oct
PMC, MahaMetro hold review of DPR for Pune Metro Phase 2


The tunnelling work for the country's first Regional Rapid Transit System (RRTS) has moved into the next phase with the construction of a tunnel of around 1.5 km length from Anand Vihar to New Ashok Nagar, according to an official statement. The National Capital Region Transport Corporation (NCRTC) is implementing India's first Regional Rapid Transit System between Delhi and Meerut. The Delhi-Ghaziabad-Meerut corridor is 82 km long, of which 14 km is in Delhi. The Delhi section has four stations: Jangpura, Sarai Kale Khan, New Ashok Nagar and Anand Vihar, with only the Anand Vihar station being underground. Two 'Sudarshan' tunnel boring machines are in operation to construct two three-km-long parallel tunnels from Anand Vihar station to New Ashok Nagar. The first Sudarshan 4.1 has already bored 1.5 km tunnel, while the second Sudarshan 4.2 has also constructed about 1km of tunnel so far. To retrieve these Sudarshan machines after the completion of the construction of the tunnels, a retrieving shaft has been built near the New Ashok Nagar station, from where the corridor gets elevated. The tunnel segments are being manufactured at NCRTC's casting yard. Due to the large rolling stock and a high design speed of 180 mph, the width of RRTS tunnels is being constructed as 6.5 metre diameter, the statement said. See also: TBMs to begin working on Chennai Metro Phase II in OctPMC, MahaMetro hold review of DPR for Pune Metro Phase 2

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD Holds Seminar on Vigilance, Integrity and Good Governance

National Bank for Agriculture and Rural Development (NABARD) organised a seminar on “Vigilance: Strengthening Integrity and Good Governance” on 25 August 2026 at its Head Office in Mumbai as part of the ongoing Vigilance Awareness Campaign 2026 being observed from 17 August to 16 November 2026, with the theme “Probity for Prosperity."" The seminar was graced by Suresh N Patel, Former Central Vigilance Commissioner, Government of India, as the chief guest and keynote speaker.  The programme was attended by G S Rawat, Deputy Managing Director, Dr Ajay K Sood, Deputy Managing Dire..

Next Story
Equipment

XCMG Unveils World's First 14,000-Ton Ring Crane for Heavy Lifting

XCMG has announced that the first main unit of the world's first 14,000-ton ring crane has rolled off the production line, marking a historic breakthrough in ultra-heavy lifting technology. Jointly developed by XCMG and Sinopec Heavy Lifting & Transportation Co., Ltd., the crane will be the largest-capacity ring crane ever built, setting a new benchmark for major construction projects worldwide.The crane features a modular configuration comprising two main units that work in tandem. The first main unit has completed final assembly and can independently perform lifting operations. Once both..

Next Story
Infrastructure Urban

Thriveni Logistics orders 200 tip trailers from Jagdamba trailers

Jagdamba Trailers (JTPL), one of India’s growing trailer manufacturers, has secured a significant order for 200 Tip Trailers from Thriveni Transport and Logistics Pvt. Ltd., a leading mining and logistics company serving operations across India and overseas.The order, placed for iron ore transportation, is a major milestone for JTPL, particularly as the company secured the business after competing with more than 10 established trailer manufacturers. It also strengthens an already successful relationship between the two companies. Approximately one and a half years ago, Thriveni Transport and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code