2 out of 18 pillars set for Hebbal flyover's extra ramp in Bengaluru
ROADS & HIGHWAYS

2 out of 18 pillars set for Hebbal flyover's extra ramp in Bengaluru

The progress of Bangalore Development Authority's (BDA) ambitious plan to construct a ramp and alleviate congestion on the Hebbal flyover is currently facing significant delays. According to BDA, out of the 18 pillars originally proposed from the Baptist Hospital side to support the ramp, only two have been constructed. The blame for this delay has been placed on several factors, with the BDA specifically pointing to the need for clearance from the traffic police.
A BDA official stated, "The advancement of the construction work relies on obtaining clearance from the traffic police. Whenever we receive clearance from the police, we will proceed accordingly."
Sachin Ghorpade, the Deputy Commissioner of Police (DCP) in charge of traffic for the northern region, mentioned that the traffic police are actively assisting in the construction efforts. He stated, "Considering the high traffic volume on Ballari Road, it is imperative that we do not disrupt the flow of traffic on the main lanes. Therefore, any construction work must be confined to the service road. We have requested the BDA to widen the left lane of the service road by reconstructing the existing uneven footpath and drainage system, but they have yet to do so. If we can allocate one lane for traffic on the service road, it will not only benefit the general public but also provide sufficient space for the construction work to progress."

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

The progress of Bangalore Development Authority's (BDA) ambitious plan to construct a ramp and alleviate congestion on the Hebbal flyover is currently facing significant delays. According to BDA, out of the 18 pillars originally proposed from the Baptist Hospital side to support the ramp, only two have been constructed. The blame for this delay has been placed on several factors, with the BDA specifically pointing to the need for clearance from the traffic police.A BDA official stated, The advancement of the construction work relies on obtaining clearance from the traffic police. Whenever we receive clearance from the police, we will proceed accordingly.Sachin Ghorpade, the Deputy Commissioner of Police (DCP) in charge of traffic for the northern region, mentioned that the traffic police are actively assisting in the construction efforts. He stated, Considering the high traffic volume on Ballari Road, it is imperative that we do not disrupt the flow of traffic on the main lanes. Therefore, any construction work must be confined to the service road. We have requested the BDA to widen the left lane of the service road by reconstructing the existing uneven footpath and drainage system, but they have yet to do so. If we can allocate one lane for traffic on the service road, it will not only benefit the general public but also provide sufficient space for the construction work to progress.If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Next Story
Equipment

Schwing Stetter India Unveils New Innovations at Excon 2025

Schwing Stetter India unveiled more than 20 new machines at Excon 2025, marking one of its most significant showcases and introducing several India-first technologies to the construction equipment sector. The company launched the country’s first 56-metre boom pump designed and manufactured in India, the first fully electric truck mixer, the first CNG mixer variant and the first hybrid boom pump. Executives said the launch portfolio was engineered to support India’s move toward faster, greener and more vertically oriented infrastructure through advanced engineering, clean-energy solutions a..

Next Story
Infrastructure Energy

SEPC Resolves Hindustan Copper Dispute, Wins Rs 725 Mn Order

Engineering, procurement and construction firm SEPC Ltd has recently settled a dispute with Hindustan Copper Ltd (HCL) and secured a mining infrastructure order valued at Rs 725 million from the state-owned company. SEPC informed the stock exchanges that it has executed a settlement deed with HCL, bringing closure to all inter-se claims and counterclaims arising from arbitration proceedings. As part of the settlement, SEPC will receive Rs 304.5 million as full and final payment, marking the resolution of all pending disputes between the two entities. The company also stated that Hindustan Co..

Next Story
Infrastructure Energy

20% Ethanol Blending Cuts India’s CO2 Emissions by 73.6 Mn Tonnes

Union Road Transport and Highways Minister Nitin Gadkari recently said that India has reduced carbon dioxide emissions by 73.6 million metric tonnes due to the adoption of 20 per cent ethanol blending in petrol. He made the statement while replying to supplementary questions during the Question Hour in the Lok Sabha. Describing ethanol as a green fuel, the minister said it plays a key role in reducing pollution while also supporting higher incomes for farmers. He underlined that ethanol blending contributes both to environmental sustainability and rural economic growth. Nitin Gadkari also po..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App