2 out of 18 pillars set for Hebbal flyover's extra ramp in Bengaluru
ROADS & HIGHWAYS

2 out of 18 pillars set for Hebbal flyover's extra ramp in Bengaluru

The progress of Bangalore Development Authority's (BDA) ambitious plan to construct a ramp and alleviate congestion on the Hebbal flyover is currently facing significant delays. According to BDA, out of the 18 pillars originally proposed from the Baptist Hospital side to support the ramp, only two have been constructed. The blame for this delay has been placed on several factors, with the BDA specifically pointing to the need for clearance from the traffic police.
A BDA official stated, "The advancement of the construction work relies on obtaining clearance from the traffic police. Whenever we receive clearance from the police, we will proceed accordingly."
Sachin Ghorpade, the Deputy Commissioner of Police (DCP) in charge of traffic for the northern region, mentioned that the traffic police are actively assisting in the construction efforts. He stated, "Considering the high traffic volume on Ballari Road, it is imperative that we do not disrupt the flow of traffic on the main lanes. Therefore, any construction work must be confined to the service road. We have requested the BDA to widen the left lane of the service road by reconstructing the existing uneven footpath and drainage system, but they have yet to do so. If we can allocate one lane for traffic on the service road, it will not only benefit the general public but also provide sufficient space for the construction work to progress."

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

The progress of Bangalore Development Authority's (BDA) ambitious plan to construct a ramp and alleviate congestion on the Hebbal flyover is currently facing significant delays. According to BDA, out of the 18 pillars originally proposed from the Baptist Hospital side to support the ramp, only two have been constructed. The blame for this delay has been placed on several factors, with the BDA specifically pointing to the need for clearance from the traffic police.A BDA official stated, The advancement of the construction work relies on obtaining clearance from the traffic police. Whenever we receive clearance from the police, we will proceed accordingly.Sachin Ghorpade, the Deputy Commissioner of Police (DCP) in charge of traffic for the northern region, mentioned that the traffic police are actively assisting in the construction efforts. He stated, Considering the high traffic volume on Ballari Road, it is imperative that we do not disrupt the flow of traffic on the main lanes. Therefore, any construction work must be confined to the service road. We have requested the BDA to widen the left lane of the service road by reconstructing the existing uneven footpath and drainage system, but they have yet to do so. If we can allocate one lane for traffic on the service road, it will not only benefit the general public but also provide sufficient space for the construction work to progress.If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Next Story
Infrastructure Transport

Railways Opens First Section of Bullet Train Tunnel in Maharashtra

The Mumbai–Ahmedabad bullet train project has achieved a key milestone with the opening of the first section of a 21-km undersea tunnel between Ghansoli and Shilphata in Maharashtra. The high-speed rail corridor, powered entirely by Japanese Shinkansen technology, has seen 310 km of viaducts completed, alongside rapid progress in track laying, electrical works, and station construction. Five of the 12 stations are complete, with three more nearing completion. The BKC station, located 32.5 metres underground, is designed to support a 95-metre structure above. The next-generation E10 Shin..

Next Story
Infrastructure Urban

Mahindra, Osaka Ink Pact to Boost Japanese Investment

Mahindra Industrial Park Chennai (MIPCL), along with its Japanese stakeholder Sumitomo Corporation, has signed a strategic cooperation agreement with the Osaka Prefecture and Osaka Industrial Development Bureau to support Osaka-based businesses entering India.The partnership aims to streamline entry for Japanese manufacturers, providing support such as business visits, regulatory guidance, and market insights. MIPCL and Sumitomo will act as local facilitators, while Osaka authorities will identify and recommend companies for expansion.With India’s projected GDP growth of 6.3 per cent in FY25..

Next Story
Building Material

Govt Plans Mandatory Public Procurement of Green Steel

The Ministry of Steel is working on modalities to mandate public procurement of green steel, as part of its efforts to decarbonise the industry. A Rs 150 billion Green Steel Mission is being formulated to support emission reduction and move towards net-zero targets.The mission will include a PLI scheme, incentives for renewable energy use, and mandates for government agencies to buy green steel. Green steel is produced with significantly lower carbon emissions compared to conventional methods.Speaking at the India Steel Conclave 2025, a senior official said procurement mandates are under consi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?