2 out of 18 pillars set for Hebbal flyover's extra ramp in Bengaluru
ROADS & HIGHWAYS

2 out of 18 pillars set for Hebbal flyover's extra ramp in Bengaluru

The progress of Bangalore Development Authority's (BDA) ambitious plan to construct a ramp and alleviate congestion on the Hebbal flyover is currently facing significant delays. According to BDA, out of the 18 pillars originally proposed from the Baptist Hospital side to support the ramp, only two have been constructed. The blame for this delay has been placed on several factors, with the BDA specifically pointing to the need for clearance from the traffic police.
A BDA official stated, "The advancement of the construction work relies on obtaining clearance from the traffic police. Whenever we receive clearance from the police, we will proceed accordingly."
Sachin Ghorpade, the Deputy Commissioner of Police (DCP) in charge of traffic for the northern region, mentioned that the traffic police are actively assisting in the construction efforts. He stated, "Considering the high traffic volume on Ballari Road, it is imperative that we do not disrupt the flow of traffic on the main lanes. Therefore, any construction work must be confined to the service road. We have requested the BDA to widen the left lane of the service road by reconstructing the existing uneven footpath and drainage system, but they have yet to do so. If we can allocate one lane for traffic on the service road, it will not only benefit the general public but also provide sufficient space for the construction work to progress."

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

The progress of Bangalore Development Authority's (BDA) ambitious plan to construct a ramp and alleviate congestion on the Hebbal flyover is currently facing significant delays. According to BDA, out of the 18 pillars originally proposed from the Baptist Hospital side to support the ramp, only two have been constructed. The blame for this delay has been placed on several factors, with the BDA specifically pointing to the need for clearance from the traffic police.A BDA official stated, The advancement of the construction work relies on obtaining clearance from the traffic police. Whenever we receive clearance from the police, we will proceed accordingly.Sachin Ghorpade, the Deputy Commissioner of Police (DCP) in charge of traffic for the northern region, mentioned that the traffic police are actively assisting in the construction efforts. He stated, Considering the high traffic volume on Ballari Road, it is imperative that we do not disrupt the flow of traffic on the main lanes. Therefore, any construction work must be confined to the service road. We have requested the BDA to widen the left lane of the service road by reconstructing the existing uneven footpath and drainage system, but they have yet to do so. If we can allocate one lane for traffic on the service road, it will not only benefit the general public but also provide sufficient space for the construction work to progress.If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App