Is highway execution at risk in India?
ROADS & HIGHWAYS

Is highway execution at risk in India?

CRISIL Research has lowered its execution forecast for the National Highways Authority of India (NHAI) projects for fiscal 2019 to 3,600-3,800 km from the earlier anticipated 4,300 km, but is still 22 per cent higher than fiscal 2018. The firm estimates around 800 km of execution is at risk this fiscal, as dated on November 2018, because many hybrid annuity model (HAM) projects are still awaiting appointed dates for a longer duration after they were awarded.

The appointed date is the de-facto starting date of a project, when the NHAI hands over its contract letter to a developer or concessionaire. As on November 2018, CRISIL Research analysed 40 HAM projects amounting to 1,913 km (over 55 per cent of total HAM awarding that year), awarded by NHAI in fiscal 2018. In all, 3,400 km of HAM projects were awarded last fiscal. Its analysis indicates that many have achieved financial closure but most are still awaiting appointed dates on account of delays in land acquisition or regulatory clearances.

The firm’s interactions with stakeholders indicate that land acquisition for most of the projects awarded are in the advanced stage, but lenders will begin disbursements only after the mandatory 80 per cent land is at least at the 3G stage. “As per MOSPI, execution in NHAI projects increased 23 per cent YoY to 1,363 km in H1 FY2019. We expects the run rate to continue, with NHAI execution expected at 3,600-3,800 km in FY2019, albeit pending appointed dates would be a drag,” cities Hetal Gandhi, Director, CRISIL Research.

The situation with projects awarded under the engineering, procurement, construction (EPC) model is better than HAM. Typically, land acquisition is higher in EPC than HAM, because the NHAI gets an additional 150 days’ buffer on account of time taken by developers for financial closure. A sample of EPC projects awarded last fiscal shows that 54 per cent have started execution.

Some projects in the advanced stages of execution are yet to receive the balance right of way, potentially affecting execution. In case 100 per cent of land is not provided on time, road developers have two options: Await right of way from NHAI and execute projects once received, or, de-scope part of the project for which land is not available and adjust the project cost on a pro-rata basis. However, the outcome will depend on individual stretches and is finalised based on negotiations with NHAI.

CRISIL Research has lowered its execution forecast for the National Highways Authority of India (NHAI) projects for fiscal 2019 to 3,600-3,800 km from the earlier anticipated 4,300 km, but is still 22 per cent higher than fiscal 2018. The firm estimates around 800 km of execution is at risk this fiscal, as dated on November 2018, because many hybrid annuity model (HAM) projects are still awaiting appointed dates for a longer duration after they were awarded. The appointed date is the de-facto starting date of a project, when the NHAI hands over its contract letter to a developer or concessionaire. As on November 2018, CRISIL Research analysed 40 HAM projects amounting to 1,913 km (over 55 per cent of total HAM awarding that year), awarded by NHAI in fiscal 2018. In all, 3,400 km of HAM projects were awarded last fiscal. Its analysis indicates that many have achieved financial closure but most are still awaiting appointed dates on account of delays in land acquisition or regulatory clearances. The firm’s interactions with stakeholders indicate that land acquisition for most of the projects awarded are in the advanced stage, but lenders will begin disbursements only after the mandatory 80 per cent land is at least at the 3G stage. “As per MOSPI, execution in NHAI projects increased 23 per cent YoY to 1,363 km in H1 FY2019. We expects the run rate to continue, with NHAI execution expected at 3,600-3,800 km in FY2019, albeit pending appointed dates would be a drag,” cities Hetal Gandhi, Director, CRISIL Research. The situation with projects awarded under the engineering, procurement, construction (EPC) model is better than HAM. Typically, land acquisition is higher in EPC than HAM, because the NHAI gets an additional 150 days’ buffer on account of time taken by developers for financial closure. A sample of EPC projects awarded last fiscal shows that 54 per cent have started execution. Some projects in the advanced stages of execution are yet to receive the balance right of way, potentially affecting execution. In case 100 per cent of land is not provided on time, road developers have two options: Await right of way from NHAI and execute projects once received, or, de-scope part of the project for which land is not available and adjust the project cost on a pro-rata basis. However, the outcome will depend on individual stretches and is finalised based on negotiations with NHAI.

Next Story
Products

Durakraft Expands Presence in Home Improvement Market

Durakraft Extrusions is expanding its presence in India’s home improvement market through its range of uPVC windows and doors, supported by a wider channel partner and fabricator network across Tier I, II and III cities.The company said growing demand for energy-efficient, durable and low-maintenance building solutions is driving increased adoption of modern uPVC fenestration products among Indian homeowners.Durakraft’s product portfolio focuses on thermal performance, sound insulation, weather resistance and durability for both new and existing residential developments.As part of its expa..

Next Story
Real Estate

ESNAAD Hands Over The Spark Project in Dubai

ESNAAD Real Estate Development has announced the handover of The Spark by ESNAAD, its residential project located in Mohammed Bin Rashid City, Dubai.The development comprises a ground floor, five residential floors and a rooftop, with 50 one and two-bedroom apartments. The project has been designed with a focus on practical layouts, contemporary architecture and long-term value for homeowners and investors.Located in District 11 of Mohammed Bin Rashid City, the project offers connectivity to Downtown Dubai, DIFC, Meydan, Dubai Marina and Dubai International Airport through Dubai Al Ain Road.Th..

Next Story
Equipment

L&T Achieves Double Tunnel Breakthrough at Dibang

Larsen & Toubro (L&T) has achieved a historic double milestone at the Dibang Multipurpose Project (Lot-02) in Arunachal Pradesh. On 28 April 2026, its Heavy Civil Infrastructure team recorded simultaneous breakthroughs in Diversion Tunnel-4 and Diversion Tunnel-5, successfully coordinating two daylighting blasts on the same day amid the difficult geological and environmental conditions of the Lower Dibang Valley.With this, the project has now completed breakthroughs in three of the five diversion tunnels, following DT-3 in February. The 2880 MW Dibang Multipurpose Project is a critical..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement