Is highway execution at risk in India?
ROADS & HIGHWAYS

Is highway execution at risk in India?

CRISIL Research has lowered its execution forecast for the National Highways Authority of India (NHAI) projects for fiscal 2019 to 3,600-3,800 km from the earlier anticipated 4,300 km, but is still 22 per cent higher than fiscal 2018. The firm estimates around 800 km of execution is at risk this fiscal, as dated on November 2018, because many hybrid annuity model (HAM) projects are still awaiting appointed dates for a longer duration after they were awarded.

The appointed date is the de-facto starting date of a project, when the NHAI hands over its contract letter to a developer or concessionaire. As on November 2018, CRISIL Research analysed 40 HAM projects amounting to 1,913 km (over 55 per cent of total HAM awarding that year), awarded by NHAI in fiscal 2018. In all, 3,400 km of HAM projects were awarded last fiscal. Its analysis indicates that many have achieved financial closure but most are still awaiting appointed dates on account of delays in land acquisition or regulatory clearances.

The firm’s interactions with stakeholders indicate that land acquisition for most of the projects awarded are in the advanced stage, but lenders will begin disbursements only after the mandatory 80 per cent land is at least at the 3G stage. “As per MOSPI, execution in NHAI projects increased 23 per cent YoY to 1,363 km in H1 FY2019. We expects the run rate to continue, with NHAI execution expected at 3,600-3,800 km in FY2019, albeit pending appointed dates would be a drag,” cities Hetal Gandhi, Director, CRISIL Research.

The situation with projects awarded under the engineering, procurement, construction (EPC) model is better than HAM. Typically, land acquisition is higher in EPC than HAM, because the NHAI gets an additional 150 days’ buffer on account of time taken by developers for financial closure. A sample of EPC projects awarded last fiscal shows that 54 per cent have started execution.

Some projects in the advanced stages of execution are yet to receive the balance right of way, potentially affecting execution. In case 100 per cent of land is not provided on time, road developers have two options: Await right of way from NHAI and execute projects once received, or, de-scope part of the project for which land is not available and adjust the project cost on a pro-rata basis. However, the outcome will depend on individual stretches and is finalised based on negotiations with NHAI.

CRISIL Research has lowered its execution forecast for the National Highways Authority of India (NHAI) projects for fiscal 2019 to 3,600-3,800 km from the earlier anticipated 4,300 km, but is still 22 per cent higher than fiscal 2018. The firm estimates around 800 km of execution is at risk this fiscal, as dated on November 2018, because many hybrid annuity model (HAM) projects are still awaiting appointed dates for a longer duration after they were awarded. The appointed date is the de-facto starting date of a project, when the NHAI hands over its contract letter to a developer or concessionaire. As on November 2018, CRISIL Research analysed 40 HAM projects amounting to 1,913 km (over 55 per cent of total HAM awarding that year), awarded by NHAI in fiscal 2018. In all, 3,400 km of HAM projects were awarded last fiscal. Its analysis indicates that many have achieved financial closure but most are still awaiting appointed dates on account of delays in land acquisition or regulatory clearances. The firm’s interactions with stakeholders indicate that land acquisition for most of the projects awarded are in the advanced stage, but lenders will begin disbursements only after the mandatory 80 per cent land is at least at the 3G stage. “As per MOSPI, execution in NHAI projects increased 23 per cent YoY to 1,363 km in H1 FY2019. We expects the run rate to continue, with NHAI execution expected at 3,600-3,800 km in FY2019, albeit pending appointed dates would be a drag,” cities Hetal Gandhi, Director, CRISIL Research. The situation with projects awarded under the engineering, procurement, construction (EPC) model is better than HAM. Typically, land acquisition is higher in EPC than HAM, because the NHAI gets an additional 150 days’ buffer on account of time taken by developers for financial closure. A sample of EPC projects awarded last fiscal shows that 54 per cent have started execution. Some projects in the advanced stages of execution are yet to receive the balance right of way, potentially affecting execution. In case 100 per cent of land is not provided on time, road developers have two options: Await right of way from NHAI and execute projects once received, or, de-scope part of the project for which land is not available and adjust the project cost on a pro-rata basis. However, the outcome will depend on individual stretches and is finalised based on negotiations with NHAI.

Related Stories

Gold Stories

Next Story
Real Estate

Concorde signs JDA for residential project in North Bengaluru

Bengaluru-based real estate developer Concorde has signed a Joint Development Agreement (JDA) for a premium residential project on a 3-acre land parcel in North Bengaluru. The development has an estimated potential of 400,000 sq ft and a Gross Development Value (GDV) of ₹4.5 billion.The project will add to Concorde's residential portfolio, with a focus on contemporary architecture, construction quality and lifestyle amenities.Commenting on the development, Anil RG, Managing Director, Concorde, said, “North Bengaluru is emerging as a significant growth destination, and this development mark..

Next Story
Real Estate

Alliance City Hands Over Alliance Eternis in Borivali West

"Alliance City Developers Realtors recently announced the completion and formal handover of Alliance Eternis, its boutique residential tower at Dattani Nagar, SV Road, Borivali West, Mumbai. The development received its full Occupation Certificate (OC) and was officially handed over to the housing society on 31 October 2026.The full OC confirms that the entire 14-storey residential tower has been completed in accordance with approved plans and cleared by the municipal authority for occupation, marking its transition to society management.The handover follows a series of project delivery milest..

Next Story
Equipment

John Crane invests over $5 million in Pune centre

John Crane, a global provider of flow control technologies and a business of Smiths Group plc, has invested more than $5 million in a new engineering and business services centre in Pune. Officially inaugurated by John Crane President Ruben Alvarez, the centre has capacity for around 400 people.John Crane has operated in India for more than 30 years and employs over 700 people in the country, serving customers across the energy and process industries, including oil and gas, chemicals, fertilisers, pharmaceuticals and power generation. The company also operates manufacturing and service facilit..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code