Afcons wins Mumbai-Ahmedabad Bullet Train’s C2 Tunnel Contract
ROADS & HIGHWAYS

Afcons wins Mumbai-Ahmedabad Bullet Train’s C2 Tunnel Contract

The National High-Speed Rail Corporation Ltd. (NHSRCL) of India and Afcons Infrastructure signed an Rs. 6397.27 crore contract on Thursday for the construction of the 20.377 km subterranean Package C-2 of the 508.17 km Mumbai-Ahmedabad High-Speed Rail (MAHSR Bullet Train).

Package C2 of the main line will consist of a roughly 3 km "undersea" tunnel through Thane Creek and will connect chainage Km 0.773 (Bandra Kurla Complex Station) to Km 21.150 (Shilphata Ramp).

Afcons Infrastructure is attempting to meet a target of 1888 days (5.17 years) and will be required to use at least three Mega Tunnel Boring Machines (TBMs) with a diameter of around 14.5 meters to bore approximately 16 kilometers of the tunnel. The next 5 kilometers will be constructed utilizing the New Austrian Tunneling Method (NATM).

Afcons was designated the lowest bidder for C2's contract in early April 2023, narrowly defeating Larsen & Toubro, and NHSCRL gave a Letter of Acceptance (LoA) to Afcons in mid-May 2023.

MAHSR-C-2 is the IFB number for this package.

Brief Scope: Construction of Tunnelling Works, including Testing and Commissioning, for a Double Line High-Speed Railway between Mumbai Underground Station at Bandra-Kurla Complex (MAHSR Km. 0.773) and Shilphata (MAHSR Km. 21.150) using (TBM) and (NATM).

Afcons will build three shafts at BKC Station, Vikhroli, and Sawli at depths of 36m, 56m, and 39m, respectively, to launch and retrieve three TBMs. NATM tunneling will be facilitated by a 42m inclined shaft at Ghansoli and a tunnel entrance at Shilphata.

With this development, Afcons will most likely begin basic preparatory work by the end of the month, building work by the end of Q3 2023, and actual tunneling work no earlier than Q1 2025.

135.45 km Package C3 (Shilphata - Zaroli) in Maharashtra is the only civil package still open for bidding. NHSRCL is now evaluating technical bids submitted in April from four firms.

The National High-Speed Rail Corporation Ltd. (NHSRCL) of India and Afcons Infrastructure signed an Rs. 6397.27 crore contract on Thursday for the construction of the 20.377 km subterranean Package C-2 of the 508.17 km Mumbai-Ahmedabad High-Speed Rail (MAHSR Bullet Train). Package C2 of the main line will consist of a roughly 3 km undersea tunnel through Thane Creek and will connect chainage Km 0.773 (Bandra Kurla Complex Station) to Km 21.150 (Shilphata Ramp). Afcons Infrastructure is attempting to meet a target of 1888 days (5.17 years) and will be required to use at least three Mega Tunnel Boring Machines (TBMs) with a diameter of around 14.5 meters to bore approximately 16 kilometers of the tunnel. The next 5 kilometers will be constructed utilizing the New Austrian Tunneling Method (NATM). Afcons was designated the lowest bidder for C2's contract in early April 2023, narrowly defeating Larsen & Toubro, and NHSCRL gave a Letter of Acceptance (LoA) to Afcons in mid-May 2023. MAHSR-C-2 is the IFB number for this package. Brief Scope: Construction of Tunnelling Works, including Testing and Commissioning, for a Double Line High-Speed Railway between Mumbai Underground Station at Bandra-Kurla Complex (MAHSR Km. 0.773) and Shilphata (MAHSR Km. 21.150) using (TBM) and (NATM). Afcons will build three shafts at BKC Station, Vikhroli, and Sawli at depths of 36m, 56m, and 39m, respectively, to launch and retrieve three TBMs. NATM tunneling will be facilitated by a 42m inclined shaft at Ghansoli and a tunnel entrance at Shilphata. With this development, Afcons will most likely begin basic preparatory work by the end of the month, building work by the end of Q3 2023, and actual tunneling work no earlier than Q1 2025. 135.45 km Package C3 (Shilphata - Zaroli) in Maharashtra is the only civil package still open for bidding. NHSRCL is now evaluating technical bids submitted in April from four firms.

Next Story
Infrastructure Urban

Infrastructure Opportunity Outlook by IMPACCT.Info

India’s infrastructure pipeline is witnessing dynamic activity across stages — from immediate bidding to future planning. IMPACCT segments these into three categories: Immediate, 3–6 Month, and Future Opportunities, enabling businesses to identify, prepare, and participate in high-value tenders and projects across sectors...To read the full article Click Here..

Next Story
Real Estate

Serene Communities, Prathima Group Invest Rs 4 billion in Hyderabad

Serene Communities by Columbia Pacific, India’s largest senior living operator, has partnered with Prathima Group to develop two senior living projects in Hyderabad, marking its entry into Telangana. The collaboration represents an investment of Rs 4 billion, combining Serene’s international expertise with Prathima’s local development experience. The first project, Serene BILVANI One, launched in Shankarpally, is Hyderabad’s first premium senior living community. Designed for independent and active ageing, it features senior-friendly architecture, barrier-free design, and wellness..

Next Story
Infrastructure Urban

India remains our most important market

Foundamental, the world’s leading venture capital platform focused on the project economy, has launched its third fund to strengthen its presence in India, APAC, and other global markets. Led by Berlin-based Managing Partners Shubhankar Bhattacharya and Patric Hellermann, Fund III aims for a final close by the end of 2025. In an exclusive interaction with CW, Bhattacharya shares insights on the fund’s mandate, India’s role in their strategy, and the opportunities they see in the construction-tech and project-based sectors. Can you briefly explain Fund III’s mandate and how In..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?