Afcons wins Mumbai-Ahmedabad Bullet Train’s C2 Tunnel Contract
ROADS & HIGHWAYS

Afcons wins Mumbai-Ahmedabad Bullet Train’s C2 Tunnel Contract

The National High-Speed Rail Corporation Ltd. (NHSRCL) of India and Afcons Infrastructure signed an Rs. 6397.27 crore contract on Thursday for the construction of the 20.377 km subterranean Package C-2 of the 508.17 km Mumbai-Ahmedabad High-Speed Rail (MAHSR Bullet Train).

Package C2 of the main line will consist of a roughly 3 km "undersea" tunnel through Thane Creek and will connect chainage Km 0.773 (Bandra Kurla Complex Station) to Km 21.150 (Shilphata Ramp).

Afcons Infrastructure is attempting to meet a target of 1888 days (5.17 years) and will be required to use at least three Mega Tunnel Boring Machines (TBMs) with a diameter of around 14.5 meters to bore approximately 16 kilometers of the tunnel. The next 5 kilometers will be constructed utilizing the New Austrian Tunneling Method (NATM).

Afcons was designated the lowest bidder for C2's contract in early April 2023, narrowly defeating Larsen & Toubro, and NHSCRL gave a Letter of Acceptance (LoA) to Afcons in mid-May 2023.

MAHSR-C-2 is the IFB number for this package.

Brief Scope: Construction of Tunnelling Works, including Testing and Commissioning, for a Double Line High-Speed Railway between Mumbai Underground Station at Bandra-Kurla Complex (MAHSR Km. 0.773) and Shilphata (MAHSR Km. 21.150) using (TBM) and (NATM).

Afcons will build three shafts at BKC Station, Vikhroli, and Sawli at depths of 36m, 56m, and 39m, respectively, to launch and retrieve three TBMs. NATM tunneling will be facilitated by a 42m inclined shaft at Ghansoli and a tunnel entrance at Shilphata.

With this development, Afcons will most likely begin basic preparatory work by the end of the month, building work by the end of Q3 2023, and actual tunneling work no earlier than Q1 2025.

135.45 km Package C3 (Shilphata - Zaroli) in Maharashtra is the only civil package still open for bidding. NHSRCL is now evaluating technical bids submitted in April from four firms.

The National High-Speed Rail Corporation Ltd. (NHSRCL) of India and Afcons Infrastructure signed an Rs. 6397.27 crore contract on Thursday for the construction of the 20.377 km subterranean Package C-2 of the 508.17 km Mumbai-Ahmedabad High-Speed Rail (MAHSR Bullet Train). Package C2 of the main line will consist of a roughly 3 km undersea tunnel through Thane Creek and will connect chainage Km 0.773 (Bandra Kurla Complex Station) to Km 21.150 (Shilphata Ramp). Afcons Infrastructure is attempting to meet a target of 1888 days (5.17 years) and will be required to use at least three Mega Tunnel Boring Machines (TBMs) with a diameter of around 14.5 meters to bore approximately 16 kilometers of the tunnel. The next 5 kilometers will be constructed utilizing the New Austrian Tunneling Method (NATM). Afcons was designated the lowest bidder for C2's contract in early April 2023, narrowly defeating Larsen & Toubro, and NHSCRL gave a Letter of Acceptance (LoA) to Afcons in mid-May 2023. MAHSR-C-2 is the IFB number for this package. Brief Scope: Construction of Tunnelling Works, including Testing and Commissioning, for a Double Line High-Speed Railway between Mumbai Underground Station at Bandra-Kurla Complex (MAHSR Km. 0.773) and Shilphata (MAHSR Km. 21.150) using (TBM) and (NATM). Afcons will build three shafts at BKC Station, Vikhroli, and Sawli at depths of 36m, 56m, and 39m, respectively, to launch and retrieve three TBMs. NATM tunneling will be facilitated by a 42m inclined shaft at Ghansoli and a tunnel entrance at Shilphata. With this development, Afcons will most likely begin basic preparatory work by the end of the month, building work by the end of Q3 2023, and actual tunneling work no earlier than Q1 2025. 135.45 km Package C3 (Shilphata - Zaroli) in Maharashtra is the only civil package still open for bidding. NHSRCL is now evaluating technical bids submitted in April from four firms.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement