Anand Vihar and Punjabi Bagh Flyovers Ready
ROADS & HIGHWAYS

Anand Vihar and Punjabi Bagh Flyovers Ready

Work on two major road infrastructure projects, the Anand Vihar flyover and the Punjabi Bagh flyover, has been completed but are yet to be opened for public use, according to officials. Located in highly congested areas, work on these projects started around two years ago.

"The work on the flyover is complete and it is ready for opening," said a PWD official on Wednesday. According to sources, both the flyovers are likely to be inaugurated closer to the assembly elections in Delhi, scheduled for early next year. During the time the work was under way, motorists faced heavy traffic congestion every day. Area residents are demanding that PWD open these flyovers immediately. Recently, a protest was organised by the residents of Punjabi Bagh at the newly completed flyover pressing for its opening. As the main road as blocked off until the flyover work was completed, vehicles were diverted to the service lane in front of the crematorium. The lane is narrow and the traffic heavy, which considerably slows down movement of cars.

This stretch carries a significant traffic load as it connects with Rohtak Road (NH-10) carrying traffic from Haryana. The construction of the flyover will streamline the traffic in Punjabi Bagh and help connect north Delhi with south Delhi, Gurgaon and other parts of NCR.

At the Anand Vihar flyover, which starts at the railway overbridge, delay in permission to fell trees have hindered the completion of the ramps and a footpath, which are unlikely to be finished by the time the flyover opens. The deadline for the Anand Vihar flyover, which includes an elevated corridor, pedestrian subway and the side ramps, was extended from Dec 2023 to April 2024, but the facility is still not open for public use. The project was initially planned in 2019, but the pandemic delayed its commencement. The foundation stone was finally laid in Oct 2022 by then chief minister Arvind Kejriwal and Delhi Assembly speaker Ram Niwas Goel.

In Aug this year, PWD started a trial run on the new flyover. After facing several delays, the main flyover is ready and is awaiting the official inauguration. Once the 1.4km flyover is opened for use, Road No. 56 will become entirely signal-free, and people living in Ramprastha Colony, Vivek Vihar and Shresth Vihar are likely to get some relief when driving.

Jyoti Gupta, a resident of Ramprastha Colony, said, "There is no check on people driving on the wrong side. The stretch is poorly illuminated, and due to the heavy traffic, driving after dark is a big problem. If the flyover work is over and it is ready, then it should be opened for public use. At present, barriers block the entry of the flyover."

Work on two major road infrastructure projects, the Anand Vihar flyover and the Punjabi Bagh flyover, has been completed but are yet to be opened for public use, according to officials. Located in highly congested areas, work on these projects started around two years ago. The work on the flyover is complete and it is ready for opening, said a PWD official on Wednesday. According to sources, both the flyovers are likely to be inaugurated closer to the assembly elections in Delhi, scheduled for early next year. During the time the work was under way, motorists faced heavy traffic congestion every day. Area residents are demanding that PWD open these flyovers immediately. Recently, a protest was organised by the residents of Punjabi Bagh at the newly completed flyover pressing for its opening. As the main road as blocked off until the flyover work was completed, vehicles were diverted to the service lane in front of the crematorium. The lane is narrow and the traffic heavy, which considerably slows down movement of cars. This stretch carries a significant traffic load as it connects with Rohtak Road (NH-10) carrying traffic from Haryana. The construction of the flyover will streamline the traffic in Punjabi Bagh and help connect north Delhi with south Delhi, Gurgaon and other parts of NCR. At the Anand Vihar flyover, which starts at the railway overbridge, delay in permission to fell trees have hindered the completion of the ramps and a footpath, which are unlikely to be finished by the time the flyover opens. The deadline for the Anand Vihar flyover, which includes an elevated corridor, pedestrian subway and the side ramps, was extended from Dec 2023 to April 2024, but the facility is still not open for public use. The project was initially planned in 2019, but the pandemic delayed its commencement. The foundation stone was finally laid in Oct 2022 by then chief minister Arvind Kejriwal and Delhi Assembly speaker Ram Niwas Goel. In Aug this year, PWD started a trial run on the new flyover. After facing several delays, the main flyover is ready and is awaiting the official inauguration. Once the 1.4km flyover is opened for use, Road No. 56 will become entirely signal-free, and people living in Ramprastha Colony, Vivek Vihar and Shresth Vihar are likely to get some relief when driving. Jyoti Gupta, a resident of Ramprastha Colony, said, There is no check on people driving on the wrong side. The stretch is poorly illuminated, and due to the heavy traffic, driving after dark is a big problem. If the flyover work is over and it is ready, then it should be opened for public use. At present, barriers block the entry of the flyover.

Next Story
Real Estate

MoHUA Sanctions 1.47 Lakh Additional Houses Under PMAY-U 2.0

In a major push towards the Government’s Housing for All mission, the Ministry of Housing and Urban Affairs (MoHUA) has approved 1,46,582 additional pucca houses under Pradhan Mantri Awas Yojana – Urban 2.0 (PMAY-U 2.0) for 14 States/UTs, bringing total sanctions under the revamped scheme to 8.56 lakh.The decision came during the fourth meeting of the Central Sanctioning and Monitoring Committee (CSMC), chaired by Srinivas Katikithala, Secretary, MoHUA, at the Ministry’s Kasturba Gandhi Marg office. Senior officials, State Principal Secretaries, and PMAY-U Mission Directors participated ..

Next Story
Real Estate

Piyush Goyal Inaugurates Expanded ISA Building at Intellectual Property Office

Union Minister of Commerce and Industry, Piyush Goyal, today inaugurated the newly expanded International Searching Authority (ISA) building at the Intellectual Property Office (IPO) in Dwarka, New Delhi, marking a major step forward in India’s intellectual property ecosystem.Addressing the gathering, Goyal highlighted that innovation has been central to India’s heritage for centuries, citing the engineering brilliance of the Konark Temple as a historic example. He emphasised that innovation is not just intellectual property but a symbol of sovereignty, and a key driver in India’s journe..

Next Story
Real Estate

SIEGER Boosts Automation in Mumbai Realty

SIEGER, a leading automation solutions provider, is expanding its advanced manufacturing capabilities to meet the surging demand for precision, high-speed automation in Mumbai’s rapidly growing real estate sector.Operating from a 21,000 m² advanced production hub in Coimbatore—part of a 40,000 m² integrated campus—SIEGER offers complete solutions from design and prototyping to manufacturing and deployment. The fully digitalised facility features CNC machining, QR-coded component tracking, conveyorized powder coating, and a Government of India–certified R&D centre, ensuring unmatc..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?