Anand Vihar and Punjabi Bagh Flyovers Ready
ROADS & HIGHWAYS

Anand Vihar and Punjabi Bagh Flyovers Ready

Work on two major road infrastructure projects, the Anand Vihar flyover and the Punjabi Bagh flyover, has been completed but are yet to be opened for public use, according to officials. Located in highly congested areas, work on these projects started around two years ago.

"The work on the flyover is complete and it is ready for opening," said a PWD official on Wednesday. According to sources, both the flyovers are likely to be inaugurated closer to the assembly elections in Delhi, scheduled for early next year. During the time the work was under way, motorists faced heavy traffic congestion every day. Area residents are demanding that PWD open these flyovers immediately. Recently, a protest was organised by the residents of Punjabi Bagh at the newly completed flyover pressing for its opening. As the main road as blocked off until the flyover work was completed, vehicles were diverted to the service lane in front of the crematorium. The lane is narrow and the traffic heavy, which considerably slows down movement of cars.

This stretch carries a significant traffic load as it connects with Rohtak Road (NH-10) carrying traffic from Haryana. The construction of the flyover will streamline the traffic in Punjabi Bagh and help connect north Delhi with south Delhi, Gurgaon and other parts of NCR.

At the Anand Vihar flyover, which starts at the railway overbridge, delay in permission to fell trees have hindered the completion of the ramps and a footpath, which are unlikely to be finished by the time the flyover opens. The deadline for the Anand Vihar flyover, which includes an elevated corridor, pedestrian subway and the side ramps, was extended from Dec 2023 to April 2024, but the facility is still not open for public use. The project was initially planned in 2019, but the pandemic delayed its commencement. The foundation stone was finally laid in Oct 2022 by then chief minister Arvind Kejriwal and Delhi Assembly speaker Ram Niwas Goel.

In Aug this year, PWD started a trial run on the new flyover. After facing several delays, the main flyover is ready and is awaiting the official inauguration. Once the 1.4km flyover is opened for use, Road No. 56 will become entirely signal-free, and people living in Ramprastha Colony, Vivek Vihar and Shresth Vihar are likely to get some relief when driving.

Jyoti Gupta, a resident of Ramprastha Colony, said, "There is no check on people driving on the wrong side. The stretch is poorly illuminated, and due to the heavy traffic, driving after dark is a big problem. If the flyover work is over and it is ready, then it should be opened for public use. At present, barriers block the entry of the flyover."

Work on two major road infrastructure projects, the Anand Vihar flyover and the Punjabi Bagh flyover, has been completed but are yet to be opened for public use, according to officials. Located in highly congested areas, work on these projects started around two years ago. The work on the flyover is complete and it is ready for opening, said a PWD official on Wednesday. According to sources, both the flyovers are likely to be inaugurated closer to the assembly elections in Delhi, scheduled for early next year. During the time the work was under way, motorists faced heavy traffic congestion every day. Area residents are demanding that PWD open these flyovers immediately. Recently, a protest was organised by the residents of Punjabi Bagh at the newly completed flyover pressing for its opening. As the main road as blocked off until the flyover work was completed, vehicles were diverted to the service lane in front of the crematorium. The lane is narrow and the traffic heavy, which considerably slows down movement of cars. This stretch carries a significant traffic load as it connects with Rohtak Road (NH-10) carrying traffic from Haryana. The construction of the flyover will streamline the traffic in Punjabi Bagh and help connect north Delhi with south Delhi, Gurgaon and other parts of NCR. At the Anand Vihar flyover, which starts at the railway overbridge, delay in permission to fell trees have hindered the completion of the ramps and a footpath, which are unlikely to be finished by the time the flyover opens. The deadline for the Anand Vihar flyover, which includes an elevated corridor, pedestrian subway and the side ramps, was extended from Dec 2023 to April 2024, but the facility is still not open for public use. The project was initially planned in 2019, but the pandemic delayed its commencement. The foundation stone was finally laid in Oct 2022 by then chief minister Arvind Kejriwal and Delhi Assembly speaker Ram Niwas Goel. In Aug this year, PWD started a trial run on the new flyover. After facing several delays, the main flyover is ready and is awaiting the official inauguration. Once the 1.4km flyover is opened for use, Road No. 56 will become entirely signal-free, and people living in Ramprastha Colony, Vivek Vihar and Shresth Vihar are likely to get some relief when driving. Jyoti Gupta, a resident of Ramprastha Colony, said, There is no check on people driving on the wrong side. The stretch is poorly illuminated, and due to the heavy traffic, driving after dark is a big problem. If the flyover work is over and it is ready, then it should be opened for public use. At present, barriers block the entry of the flyover.

Next Story
Infrastructure Urban

India to Invest Rs 600 Billion to Upgrade 1,000 ITIs

As part of its drive to modernise vocational training, the Ministry of Skill Development and Entrepreneurship (MSDE), in collaboration with Gujarat’s Labour and Employment Department, held a State-Level Workshop at the NAMTECH Campus within IIT-Gandhinagar to discuss the National Scheme for ITI Upgradation.The consultation brought together key stakeholders from industry and the training ecosystem to align expectations and support implementation of the scheme, which aims to transform 1,000 Industrial Training Institutes (ITIs) across India using a hub-and-spoke model. The total outlay stands ..

Next Story
Infrastructure Urban

India Unveils Rs 600 Billion Maritime Finance Push

The Ministry of Ports, Shipping & Waterways (MoPSW) hosted the Maritime Financing Summit 2025 in New Delhi, bringing together over 250 stakeholders including policymakers, industry leaders, global investors, and financial institutions. The summit, held under the ambit of Maritime Amrit Kaal Vision (MAKV) 2047, focused on transforming India into a leading maritime power with strengthened financial, infrastructural, and technological capabilities.Union Minister Sarbananda Sonowal emphasised India's strategic progress, noting that average port turnaround times have dropped from four days to u..

Next Story
Infrastructure Urban

Govt Allocates Rs 500 Million To Boost Community Radio

The Central Government, through its ‘Supporting Community Radio Movement in India’ scheme, has allocated Rs 500 million to strengthen the community radio ecosystem across the country. The initiative aims to assist both newly established and long-operational Community Radio Stations (CRSs), ensuring their relevance to local educational, social, cultural, and developmental needs.According to the policy published by the Ministry of Information and Broadcasting, CRSs may be set up by not-for-profit organisations with at least three years of demonstrated community service. These stations are ex..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?