Bengaluru Civic Body Faces Criticism for Tunnel Road Report Errors
ROADS & HIGHWAYS

Bengaluru Civic Body Faces Criticism for Tunnel Road Report Errors

A detailed project report (DPR) for an ambitious tunnel road project in Bengaluru, Karnataka, has raised concerns after it was found to contain several inaccuracies, including environmental discrepancies and references to cities in Maharashtra. The DPR, prepared by New Delhi-based Rodic Consultants and submitted to the Bruhat Bengaluru Mahanagara Palike (BBMP) in November 2024, outlined plans for an 18 km tunnel road connecting Hebbal and Silk Board, at a cost of Rs 90.5 million.

The report, completed in just three months, has been criticised for including traffic volume data from two cities in Maharashtra while discussing traffic patterns in Bengaluru. A specific section of the report, which analyses traffic volumes at Malur Road, Guttahalli Main Road, and NR Road, mentions traffic characteristics between Malegaon and Nashik, prompting concerns of a "copy-paste" job.

The report stated that nine cordon points had been identified to understand the traffic characteristics in the study area, followed by a detailed account of traffic flow and counts at various junctions. However, the inclusion of traffic data from cities far from Bengaluru has led to questions about the validity of the entire report.

The tunnel project, which is estimated to cost Rs 126.90 billion, aims to alleviate traffic congestion between the two key junctions, Hebbal and Silk Board. The proposed tunnel is designed to reduce travel time from 90 minutes to just 20 minutes, with three intermediate ramps at Mekhri Circle, Racecourse, and Lalbagh, improving connectivity along the North-South Corridor.

Karnataka’s Deputy Chief Minister DK Shivakumar, who has been advocating for the project as part of his “Brand Bengaluru” initiative, believes the tunnel will significantly reduce traffic congestion, particularly at the busy Hebbal and Silk Board junctions.

In addition to the DPR, the BBMP had also commissioned a feasibility study for the same corridor from Altinok Consulting at a cost of Rs 40.7 million.

The report’s quick turnaround, completed in just three months, raised concerns among observers, as DPRs typically take nine months to a year to prepare. For comparison, the DPR for Bengaluru Metro’s 37-km Hebbal-Sarjapur corridor, prepared by RINA Consulting at a cost of Rs 10.5 million, took a full year to complete. This stark difference in both cost and timelines has further fuelled scrutiny regarding the planning process of the tunnel project.

A detailed project report (DPR) for an ambitious tunnel road project in Bengaluru, Karnataka, has raised concerns after it was found to contain several inaccuracies, including environmental discrepancies and references to cities in Maharashtra. The DPR, prepared by New Delhi-based Rodic Consultants and submitted to the Bruhat Bengaluru Mahanagara Palike (BBMP) in November 2024, outlined plans for an 18 km tunnel road connecting Hebbal and Silk Board, at a cost of Rs 90.5 million. The report, completed in just three months, has been criticised for including traffic volume data from two cities in Maharashtra while discussing traffic patterns in Bengaluru. A specific section of the report, which analyses traffic volumes at Malur Road, Guttahalli Main Road, and NR Road, mentions traffic characteristics between Malegaon and Nashik, prompting concerns of a copy-paste job. The report stated that nine cordon points had been identified to understand the traffic characteristics in the study area, followed by a detailed account of traffic flow and counts at various junctions. However, the inclusion of traffic data from cities far from Bengaluru has led to questions about the validity of the entire report. The tunnel project, which is estimated to cost Rs 126.90 billion, aims to alleviate traffic congestion between the two key junctions, Hebbal and Silk Board. The proposed tunnel is designed to reduce travel time from 90 minutes to just 20 minutes, with three intermediate ramps at Mekhri Circle, Racecourse, and Lalbagh, improving connectivity along the North-South Corridor. Karnataka’s Deputy Chief Minister DK Shivakumar, who has been advocating for the project as part of his “Brand Bengaluru” initiative, believes the tunnel will significantly reduce traffic congestion, particularly at the busy Hebbal and Silk Board junctions. In addition to the DPR, the BBMP had also commissioned a feasibility study for the same corridor from Altinok Consulting at a cost of Rs 40.7 million. The report’s quick turnaround, completed in just three months, raised concerns among observers, as DPRs typically take nine months to a year to prepare. For comparison, the DPR for Bengaluru Metro’s 37-km Hebbal-Sarjapur corridor, prepared by RINA Consulting at a cost of Rs 10.5 million, took a full year to complete. This stark difference in both cost and timelines has further fuelled scrutiny regarding the planning process of the tunnel project.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code