Bengaluru Civic Body Faces Criticism for Tunnel Road Report Errors
ROADS & HIGHWAYS

Bengaluru Civic Body Faces Criticism for Tunnel Road Report Errors

A detailed project report (DPR) for an ambitious tunnel road project in Bengaluru, Karnataka, has raised concerns after it was found to contain several inaccuracies, including environmental discrepancies and references to cities in Maharashtra. The DPR, prepared by New Delhi-based Rodic Consultants and submitted to the Bruhat Bengaluru Mahanagara Palike (BBMP) in November 2024, outlined plans for an 18 km tunnel road connecting Hebbal and Silk Board, at a cost of Rs 90.5 million.

The report, completed in just three months, has been criticised for including traffic volume data from two cities in Maharashtra while discussing traffic patterns in Bengaluru. A specific section of the report, which analyses traffic volumes at Malur Road, Guttahalli Main Road, and NR Road, mentions traffic characteristics between Malegaon and Nashik, prompting concerns of a "copy-paste" job.

The report stated that nine cordon points had been identified to understand the traffic characteristics in the study area, followed by a detailed account of traffic flow and counts at various junctions. However, the inclusion of traffic data from cities far from Bengaluru has led to questions about the validity of the entire report.

The tunnel project, which is estimated to cost Rs 126.90 billion, aims to alleviate traffic congestion between the two key junctions, Hebbal and Silk Board. The proposed tunnel is designed to reduce travel time from 90 minutes to just 20 minutes, with three intermediate ramps at Mekhri Circle, Racecourse, and Lalbagh, improving connectivity along the North-South Corridor.

Karnataka’s Deputy Chief Minister DK Shivakumar, who has been advocating for the project as part of his “Brand Bengaluru” initiative, believes the tunnel will significantly reduce traffic congestion, particularly at the busy Hebbal and Silk Board junctions.

In addition to the DPR, the BBMP had also commissioned a feasibility study for the same corridor from Altinok Consulting at a cost of Rs 40.7 million.

The report’s quick turnaround, completed in just three months, raised concerns among observers, as DPRs typically take nine months to a year to prepare. For comparison, the DPR for Bengaluru Metro’s 37-km Hebbal-Sarjapur corridor, prepared by RINA Consulting at a cost of Rs 10.5 million, took a full year to complete. This stark difference in both cost and timelines has further fuelled scrutiny regarding the planning process of the tunnel project.

A detailed project report (DPR) for an ambitious tunnel road project in Bengaluru, Karnataka, has raised concerns after it was found to contain several inaccuracies, including environmental discrepancies and references to cities in Maharashtra. The DPR, prepared by New Delhi-based Rodic Consultants and submitted to the Bruhat Bengaluru Mahanagara Palike (BBMP) in November 2024, outlined plans for an 18 km tunnel road connecting Hebbal and Silk Board, at a cost of Rs 90.5 million. The report, completed in just three months, has been criticised for including traffic volume data from two cities in Maharashtra while discussing traffic patterns in Bengaluru. A specific section of the report, which analyses traffic volumes at Malur Road, Guttahalli Main Road, and NR Road, mentions traffic characteristics between Malegaon and Nashik, prompting concerns of a copy-paste job. The report stated that nine cordon points had been identified to understand the traffic characteristics in the study area, followed by a detailed account of traffic flow and counts at various junctions. However, the inclusion of traffic data from cities far from Bengaluru has led to questions about the validity of the entire report. The tunnel project, which is estimated to cost Rs 126.90 billion, aims to alleviate traffic congestion between the two key junctions, Hebbal and Silk Board. The proposed tunnel is designed to reduce travel time from 90 minutes to just 20 minutes, with three intermediate ramps at Mekhri Circle, Racecourse, and Lalbagh, improving connectivity along the North-South Corridor. Karnataka’s Deputy Chief Minister DK Shivakumar, who has been advocating for the project as part of his “Brand Bengaluru” initiative, believes the tunnel will significantly reduce traffic congestion, particularly at the busy Hebbal and Silk Board junctions. In addition to the DPR, the BBMP had also commissioned a feasibility study for the same corridor from Altinok Consulting at a cost of Rs 40.7 million. The report’s quick turnaround, completed in just three months, raised concerns among observers, as DPRs typically take nine months to a year to prepare. For comparison, the DPR for Bengaluru Metro’s 37-km Hebbal-Sarjapur corridor, prepared by RINA Consulting at a cost of Rs 10.5 million, took a full year to complete. This stark difference in both cost and timelines has further fuelled scrutiny regarding the planning process of the tunnel project.

Next Story
Infrastructure Transport

Uttar Pradesh unveils infrastructure-led growth roadmap at RAHSTA

Mumbai, 9 July 2026: Uttar Pradesh’s ambitious infrastructure-led growth strategy took centre stage on Day 2 of the 16th RAHSTA Expo, where senior government officials outlined how expressways, industrial corridors and technology-driven governance are transforming the state into one of India's most attractive investment destinations.Delivering the keynote address, Srihari Pratap Shahi, IAS, Additional Chief Executive Officer, Uttar Pradesh Expressways Industrial Development Authority (UPEIDA), highlighted the state's long-term vision of integrating world-class expressways with industrial dev..

Next Story
Real Estate

NCW closes PRIME Offices Fund at Rs 40 billion

Nuvama and Cushman & Wakefield Management (NCW) has announced the final close of its flagship PRIME Offices Fund at approximately Rs 40 billion, exceeding its original target of Rs 30 billion following strong investor demand.The fund was launched to provide Indian investors with access to institutional-grade commercial office assets across key office markets in the country. According to NCW, the increase in the fund size was supported by strong investor participation and the availability of investment opportunities in India's office sector.The fund has already committed around 45 per cent ..

Next Story
Real Estate

Mayfair Housing adopts Autodesk Forma for digital project planning

Mayfair Housing has entered into a three-year strategic partnership with Autodesk to deploy Autodesk Forma, an AI-enabled cloud platform, as part of its digital transformation programme aimed at improving project planning and execution across its development and redevelopment portfolio.The platform will be integrated into the company's Building Information Modelling (BIM) workflow to support architects, planners and project teams during the early stages of design and development. Autodesk Forma combines real-world data, environmental simulations and collaborative workflows to facilitate data-d..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement