Bengaluru Civic Body Faces Criticism for Tunnel Road Report Errors
ROADS & HIGHWAYS

Bengaluru Civic Body Faces Criticism for Tunnel Road Report Errors

A detailed project report (DPR) for an ambitious tunnel road project in Bengaluru, Karnataka, has raised concerns after it was found to contain several inaccuracies, including environmental discrepancies and references to cities in Maharashtra. The DPR, prepared by New Delhi-based Rodic Consultants and submitted to the Bruhat Bengaluru Mahanagara Palike (BBMP) in November 2024, outlined plans for an 18 km tunnel road connecting Hebbal and Silk Board, at a cost of Rs 90.5 million.

The report, completed in just three months, has been criticised for including traffic volume data from two cities in Maharashtra while discussing traffic patterns in Bengaluru. A specific section of the report, which analyses traffic volumes at Malur Road, Guttahalli Main Road, and NR Road, mentions traffic characteristics between Malegaon and Nashik, prompting concerns of a "copy-paste" job.

The report stated that nine cordon points had been identified to understand the traffic characteristics in the study area, followed by a detailed account of traffic flow and counts at various junctions. However, the inclusion of traffic data from cities far from Bengaluru has led to questions about the validity of the entire report.

The tunnel project, which is estimated to cost Rs 126.90 billion, aims to alleviate traffic congestion between the two key junctions, Hebbal and Silk Board. The proposed tunnel is designed to reduce travel time from 90 minutes to just 20 minutes, with three intermediate ramps at Mekhri Circle, Racecourse, and Lalbagh, improving connectivity along the North-South Corridor.

Karnataka’s Deputy Chief Minister DK Shivakumar, who has been advocating for the project as part of his “Brand Bengaluru” initiative, believes the tunnel will significantly reduce traffic congestion, particularly at the busy Hebbal and Silk Board junctions.

In addition to the DPR, the BBMP had also commissioned a feasibility study for the same corridor from Altinok Consulting at a cost of Rs 40.7 million.

The report’s quick turnaround, completed in just three months, raised concerns among observers, as DPRs typically take nine months to a year to prepare. For comparison, the DPR for Bengaluru Metro’s 37-km Hebbal-Sarjapur corridor, prepared by RINA Consulting at a cost of Rs 10.5 million, took a full year to complete. This stark difference in both cost and timelines has further fuelled scrutiny regarding the planning process of the tunnel project.

A detailed project report (DPR) for an ambitious tunnel road project in Bengaluru, Karnataka, has raised concerns after it was found to contain several inaccuracies, including environmental discrepancies and references to cities in Maharashtra. The DPR, prepared by New Delhi-based Rodic Consultants and submitted to the Bruhat Bengaluru Mahanagara Palike (BBMP) in November 2024, outlined plans for an 18 km tunnel road connecting Hebbal and Silk Board, at a cost of Rs 90.5 million. The report, completed in just three months, has been criticised for including traffic volume data from two cities in Maharashtra while discussing traffic patterns in Bengaluru. A specific section of the report, which analyses traffic volumes at Malur Road, Guttahalli Main Road, and NR Road, mentions traffic characteristics between Malegaon and Nashik, prompting concerns of a copy-paste job. The report stated that nine cordon points had been identified to understand the traffic characteristics in the study area, followed by a detailed account of traffic flow and counts at various junctions. However, the inclusion of traffic data from cities far from Bengaluru has led to questions about the validity of the entire report. The tunnel project, which is estimated to cost Rs 126.90 billion, aims to alleviate traffic congestion between the two key junctions, Hebbal and Silk Board. The proposed tunnel is designed to reduce travel time from 90 minutes to just 20 minutes, with three intermediate ramps at Mekhri Circle, Racecourse, and Lalbagh, improving connectivity along the North-South Corridor. Karnataka’s Deputy Chief Minister DK Shivakumar, who has been advocating for the project as part of his “Brand Bengaluru” initiative, believes the tunnel will significantly reduce traffic congestion, particularly at the busy Hebbal and Silk Board junctions. In addition to the DPR, the BBMP had also commissioned a feasibility study for the same corridor from Altinok Consulting at a cost of Rs 40.7 million. The report’s quick turnaround, completed in just three months, raised concerns among observers, as DPRs typically take nine months to a year to prepare. For comparison, the DPR for Bengaluru Metro’s 37-km Hebbal-Sarjapur corridor, prepared by RINA Consulting at a cost of Rs 10.5 million, took a full year to complete. This stark difference in both cost and timelines has further fuelled scrutiny regarding the planning process of the tunnel project.

Next Story
Resources

Hindustan Zinc Joins Dow Jones ESG Index

Hindustan Zinc has been included in the Dow Jones Best-in-Class Index 2026 for Emerging Markets following the latest index rebalance by S&P Dow Jones Indices. The inclusion marks the company’s first entry into the global ESG benchmark index.Formerly known as the Dow Jones Sustainability Index, the benchmark tracks companies demonstrating strong environmental, social and governance (ESG) performance across global markets. Hindustan Zinc is among only 25 Indian companies included in the emerging markets index and one of only two companies from India’s metals and mining sector.The company..

Next Story
Products

Carlton London Enters Furniture Market with EBG Group

Carlton London has entered India’s furniture market through a partnership with EBG Group, launching Carlton Luxury Furniture with a focus on sustainable and long-life home interiors. The venture plans to open 600 franchise-led showrooms across 300 cities over the next five years through a partner-driven expansion model. The company expects the rollout to generate investments of Rs 18-20 billion from franchise stakeholders and create over 12,000 jobs across the country. The brand said the initiative will focus on sustainability-led furniture manufacturing, targeting a reduction of around 16..

Next Story
Resources

BirlaNu Opens First Vijayawada Experience Centre

BirlaNu, part of the CKA Birla Group, has launched its first Experience Centre in Vijayawada, Andhra Pradesh, marking a strategic expansion in South India.Located at Mahatma Gandhi Road, Governorpet, the centre showcases BirlaNu’s portfolio across walls, floors, pipes, putty and construction chemicals through simulated real-world application displays. The format allows customers, contractors and architects to directly evaluate products before specification or purchase.The company said the initiative addresses a long-standing gap in the building materials sector, where purchasing decisions ar..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement