Bharatmala highways project plagued by cost, time escalation
ROADS & HIGHWAYS

Bharatmala highways project plagued by cost, time escalation

The Union government’s slow-moving Bharatmala Project - a plan to develop over 30,000 km of national highways - is seeing completion times and costs escalate, according to a new report from ICRA.

The report says the project is likely to be complete in FY28, a six-year delay from the original timeline. The cost of the project has already risen by 99% to Rs 10,630 billion and is poised to see another 15-20% increase.

First announced in July 2015, the project was originally estimated to cost the country Rs 5,350 billion to develop 24,800 km of national highways and another 10,000 km of highways pending under the erstwhile National Highway Development Programme by FY22. Calculations made in 2015 pegged the project cost at Rs 155.20 million crore per km.

ICRA's findings point to land acquisition as being a major problem area for the project. Funding is also a likely roadblock, with costs almost doubling since 2015. Highways Minister Nitin Gadkari has hinted at that the National Highways Authority of India (NHAI) may raise additional debt.

The Bharatmala Project is being undertaken by NHAI, the Union Road Transport and Highways Ministry, and the National Highways and Infrastructure Development Corporation, with the bulk of the project under NHAI.

See also:
CM commends NHAI for Amravati Highway
Tiruninravur-Tiruvallur high road will shortly be widened


The Union government’s slow-moving Bharatmala Project - a plan to develop over 30,000 km of national highways - is seeing completion times and costs escalate, according to a new report from ICRA. The report says the project is likely to be complete in FY28, a six-year delay from the original timeline. The cost of the project has already risen by 99% to Rs 10,630 billion and is poised to see another 15-20% increase. First announced in July 2015, the project was originally estimated to cost the country Rs 5,350 billion to develop 24,800 km of national highways and another 10,000 km of highways pending under the erstwhile National Highway Development Programme by FY22. Calculations made in 2015 pegged the project cost at Rs 155.20 million crore per km. ICRA's findings point to land acquisition as being a major problem area for the project. Funding is also a likely roadblock, with costs almost doubling since 2015. Highways Minister Nitin Gadkari has hinted at that the National Highways Authority of India (NHAI) may raise additional debt. The Bharatmala Project is being undertaken by NHAI, the Union Road Transport and Highways Ministry, and the National Highways and Infrastructure Development Corporation, with the bulk of the project under NHAI.See also: CM commends NHAI for Amravati Highway Tiruninravur-Tiruvallur high road will shortly be widened

Next Story
Resources

Skyview by Empyrean is Making Benchmarks in the Indian Ropeway Industry

FIL Industries Private Limited, the parent company of Empyrean Skyview Projects that pioneered ropeway mobility solutions in India with Jammu’s Skyview Gondola, is currently developing the Dehradun-Mussoorie ropeway and is on track to complete Phase I by September 2026. The ropeway is set to be India’s longest passenger aerial monocable covering 5.8 km between the foothills of Dehradun in Purkulgam and MDDA taxi stand in the hills of Mussoorie in just under 20 minutes. The firm pioneered green mobility solutions in India with the development of the flagship Skyview Gondola in Jam..

Next Story
Technology

Creativity is for Humans, Productivity is for Robots!

On most construction sites, the rhythm of progress is measured by the clang of steel, the hum of machinery and the sweat of thousands. But increasingly, new sounds are entering the mix: the quiet efficiency of algorithms, the hum of drones overhead, and the precision of robotic arms at work. Behind the concrete and cables, an invisible force is taking hold: data. It is turning blueprints into living simulations, managing fleets of machines, and helping engineers make decisions before a single brick is laid. This is not the construction of tomorrow; it is the architecture of today – built on ..

Next Story
Infrastructure Urban

Bhartiya Urban Unveils ‘Bhartiya Converge’ GCC Enablement Platform

Bhartiya Urban has launched Bhartiya Converge, its latest business venture designed to become India’s premier platform for enabling Global Capability Centres (GCCs). The initiative offers an integrated ecosystem aimed at helping global clients gain a competitive edge in today’s rapidly evolving business environment. Focused on enhancing turnaround time and operational efficiencies, the company seeks to deliver better business outcomes powered by top-tier talent. Bhartiya Converge presents a customised and integrated suite of microservices that addresses the nuanced and evolving operational..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?