BMC to close its Powai-Ghatkopar water tunnel contract
ROADS & HIGHWAYS

BMC to close its Powai-Ghatkopar water tunnel contract

The Brihanmumbai Municipal Corporation (BMC) has decided to close the current Powai-Ghatkopar water tunnel contract and issue a new one after failing to get a stuck tunnel boring machine (TBM) removed safely.

For the completed Powai-Veravali tunnel and incompleted Powai-Ghatkopar projects, the civic body has decided to clear the payment of Rs 147 crore.

The municipal corporation will spend Rs 360 crore more to complete the projects, including a 2.2-km tunnel from Powai to Veraval and a 4.4-km tunnel from Powai to Ghatkopar.The project was first awarded for Rs 182 crore in 2012 and was supposed to complete within 52 months.However, the cost of the project escalated to Rs 223 crore.

According to a proposal, BMC will complete the transaction of Rs 147 crore for the project completed, including Rs 38.5 crore to the contractor as the TBM is stuck. The tunnel project between Powai and Veravali was completed and commissioned in 2018. The Powai to Ghatkopar got delayed after the TBM got stuck in 2016.

The civic body approached many experts to remove the TBM safely. The 90 m length of the tunnel was excavated with the support of steel ribs. However, the work was halted as the geographical survey found that a minimum of 120 m patch ahead of the TBM cannot be excavated.

Now, BMC will issue a new contract to complete the remaining work of the Powai-Ghatkopar tunnel. It had invited bids using another technique where 400 m will be excavated using labours.

Image Source


Also read: BMC completes 2 km tunnel works of Mumbai coastal road project

The Brihanmumbai Municipal Corporation (BMC) has decided to close the current Powai-Ghatkopar water tunnel contract and issue a new one after failing to get a stuck tunnel boring machine (TBM) removed safely. For the completed Powai-Veravali tunnel and incompleted Powai-Ghatkopar projects, the civic body has decided to clear the payment of Rs 147 crore. The municipal corporation will spend Rs 360 crore more to complete the projects, including a 2.2-km tunnel from Powai to Veraval and a 4.4-km tunnel from Powai to Ghatkopar.The project was first awarded for Rs 182 crore in 2012 and was supposed to complete within 52 months.However, the cost of the project escalated to Rs 223 crore. According to a proposal, BMC will complete the transaction of Rs 147 crore for the project completed, including Rs 38.5 crore to the contractor as the TBM is stuck. The tunnel project between Powai and Veravali was completed and commissioned in 2018. The Powai to Ghatkopar got delayed after the TBM got stuck in 2016. The civic body approached many experts to remove the TBM safely. The 90 m length of the tunnel was excavated with the support of steel ribs. However, the work was halted as the geographical survey found that a minimum of 120 m patch ahead of the TBM cannot be excavated. Now, BMC will issue a new contract to complete the remaining work of the Powai-Ghatkopar tunnel. It had invited bids using another technique where 400 m will be excavated using labours. Image SourceAlso read: BMC completes 2 km tunnel works of Mumbai coastal road project

Next Story
Real Estate

Window Magic Supplies Fenestration for BDD Chawls Project

Window Magic is contributing to the redevelopment of the historic Bombay Development Department (BDD) Chawls in Worli, Mumbai, regarded as one of Asia’s largest urban redevelopment projects being executed by the Maharashtra Housing and Area Development Authority (MHADA).The redevelopment project involves transforming the century-old low-rise chawls into 33 modern residential towers of up to 40 floors each. The development will create 8,976 residential units with upgraded infrastructure and improved living conditions for residents.As part of the project, Window Magic is supplying and installi..

Next Story
Equipment

Ammann India Inaugurates Centralised Air Compressor System

Ammann India has inaugurated a new centralised air compressor system at its Machine Division as part of its green energy conservation and sustainable manufacturing initiatives.The newly installed system is designed to improve operational efficiency while optimising energy consumption, supporting the company’s long-term sustainability and carbon reduction goals. The upgrade is expected to deliver energy savings, reduce CO2 emissions, improve power efficiency and enhance production reliability.The system includes efficient air distribution, air drying and optimised load management to support r..

Next Story
Infrastructure Urban

Blue Dart posts revenue growth in FY26 on e-commerce and B2B demand

Blue Dart Express Limited, South Asia’s express air and integrated transportation and distribution company, has reported year-on-year growth in revenue for the financial year ended March 31, 2026, driven by strong momentum in e-commerce shipments and B2B surface express solutions.Announcing its financial results after the Board Meeting held in Mumbai, the company said revenue from operations rose to Rs 6,141 crore in FY2025–26, compared to Rs 5,720 crore in FY2024–25. Profit after tax for the year stood at Rs 240 crore.For the quarter ended March 31, 2026, Blue Dart reported revenue from..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->