Can India build 50 km a day?
ROADS & HIGHWAYS

Can India build 50 km a day?

From a record 37 km per day in 2020-21, the pace of National Highway construction slowed to 20.43 km a day during the first four months of 2022. Considering this, it is natural to question the feasibility of the Indian Government’s plan to augment the pace of construction to 50km a day.CW takes a closer look…

India is home to the world's second-largest road network. In the next five years, the Ministry of Road Transport and Highways (MoRTH) wants to complete 60,000 km of NH at an average daily construction rate of 40 km. Clearly, we need to pull up our socks to achieve this. Moreover, the target now is to attain 50 km a day. With an average construction cost of about Rs 30 crore per kilometre (including land acquisition costs) and a conservative inflation rate of 3 per cent for road-building costs, the total funding requirement over five years to attain this target will entail a good deal of investment from the Government.

That said, Anshumali Srivastava, Chief General Manager – Mumbai, National Highways Authority of India(NHAI), believes we are pretty much on track as far as investments are concerned. “Road investment is increasing year on year [YoY]. In 2022-23, roads have seen the highest ever investments with Rs 2.15 lakh crore. Moreover, the banks have taken an interest in the sector. Due to InvITs, funding is easily available. Further, the National Infrastructure Pipeline [NIP] has been laid out for the next five years, which provides assurance to the market.”

Cyclones, the monsoon and the secondary effect of COVID-19 did affect the pace of land acquisition because of which road construction has slowed down.But the construction of four, six and eight-lane National Highways has shot up by 300 per cent in the past seven years. So, despite the appalling effect of the pandemic, getting back to building 50km per day is not a far-fetched idea.

Keeping in mind that land acquisition continues to remain a key challenge,the Government has decided not to award any contracts until 80 per cent of land acquisition is already complete. Moreover, a good deal of political will is also getting things done.

To read the full article, CLICK HERE.

From a record 37 km per day in 2020-21, the pace of National Highway construction slowed to 20.43 km a day during the first four months of 2022. Considering this, it is natural to question the feasibility of the Indian Government’s plan to augment the pace of construction to 50km a day.CW takes a closer look… India is home to the world's second-largest road network. In the next five years, the Ministry of Road Transport and Highways (MoRTH) wants to complete 60,000 km of NH at an average daily construction rate of 40 km. Clearly, we need to pull up our socks to achieve this. Moreover, the target now is to attain 50 km a day. With an average construction cost of about Rs 30 crore per kilometre (including land acquisition costs) and a conservative inflation rate of 3 per cent for road-building costs, the total funding requirement over five years to attain this target will entail a good deal of investment from the Government. That said, Anshumali Srivastava, Chief General Manager – Mumbai, National Highways Authority of India(NHAI), believes we are pretty much on track as far as investments are concerned. “Road investment is increasing year on year [YoY]. In 2022-23, roads have seen the highest ever investments with Rs 2.15 lakh crore. Moreover, the banks have taken an interest in the sector. Due to InvITs, funding is easily available. Further, the National Infrastructure Pipeline [NIP] has been laid out for the next five years, which provides assurance to the market.” Cyclones, the monsoon and the secondary effect of COVID-19 did affect the pace of land acquisition because of which road construction has slowed down.But the construction of four, six and eight-lane National Highways has shot up by 300 per cent in the past seven years. So, despite the appalling effect of the pandemic, getting back to building 50km per day is not a far-fetched idea. Keeping in mind that land acquisition continues to remain a key challenge,the Government has decided not to award any contracts until 80 per cent of land acquisition is already complete. Moreover, a good deal of political will is also getting things done. To read the full article, CLICK HERE.

Next Story
Infrastructure Urban

PM GatiShakti Reviews Major Road, Rail and Metro Plans

The Network Planning Group (NPG) under the PM GatiShakti initiative has evaluated multiple infrastructure projects spanning road, rail, and metro systems. The review covered two highway projects by the Ministry of Road Transport and Highways (MoRTH), two railway proposals by the Ministry of Railways, and one metro project under the Ministry of Housing and Urban Affairs (MoHUA). According to the Ministry of Commerce and Industry, the projects were assessed for alignment with PM GatiShakti’s principles of integrated multimodal connectivity, last-mile linkage to economic and social hubs, and t..

Next Story
Real Estate

MahaRERA Fast-Tracks 809 Project Approvals Ahead of Diwali

As Diwali 2025 approaches, the Maharashtra Real Estate Regulatory Authority (MahaRERA) is expediting approvals for new housing projects to ensure compliance with legal, technical, and financial standards before launch. The festive season, especially Dussehra and Diwali, traditionally marks a peak period for real estate launches as developers seek to capitalise on auspicious timings and heightened buyer sentiment. This year, MahaRERA has taken a proactive approach to facilitate timely project approvals ahead of the celebrations. A total of 809 project applications were approved recently, cover..

Next Story
Infrastructure Energy

HFCL Bags Rs 2.8 Billion Export Order for Fibre Cables

Telecom equipment manufacturer HFCL has secured an export order worth USD 32.02 million (around Rs 2.8 billion) for the supply of optical fibre cables to an international client. In a regulatory filing, the company stated that the order was received through its wholly owned overseas subsidiary and is scheduled for execution by December 2026. The contract entails the supply of optical fibre cables customised to the client’s specifications, underscoring HFCL’s strong manufacturing expertise and technological capability in the global telecom infrastructure space. This order further strengt..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?