Can India build 50 km a day?
ROADS & HIGHWAYS

Can India build 50 km a day?

From a record 37 km per day in 2020-21, the pace of National Highway construction slowed to 20.43 km a day during the first four months of 2022. Considering this, it is natural to question the feasibility of the Indian Government’s plan to augment the pace of construction to 50km a day.CW takes a closer look…

India is home to the world's second-largest road network. In the next five years, the Ministry of Road Transport and Highways (MoRTH) wants to complete 60,000 km of NH at an average daily construction rate of 40 km. Clearly, we need to pull up our socks to achieve this. Moreover, the target now is to attain 50 km a day. With an average construction cost of about Rs 30 crore per kilometre (including land acquisition costs) and a conservative inflation rate of 3 per cent for road-building costs, the total funding requirement over five years to attain this target will entail a good deal of investment from the Government.

That said, Anshumali Srivastava, Chief General Manager – Mumbai, National Highways Authority of India(NHAI), believes we are pretty much on track as far as investments are concerned. “Road investment is increasing year on year [YoY]. In 2022-23, roads have seen the highest ever investments with Rs 2.15 lakh crore. Moreover, the banks have taken an interest in the sector. Due to InvITs, funding is easily available. Further, the National Infrastructure Pipeline [NIP] has been laid out for the next five years, which provides assurance to the market.”

Cyclones, the monsoon and the secondary effect of COVID-19 did affect the pace of land acquisition because of which road construction has slowed down.But the construction of four, six and eight-lane National Highways has shot up by 300 per cent in the past seven years. So, despite the appalling effect of the pandemic, getting back to building 50km per day is not a far-fetched idea.

Keeping in mind that land acquisition continues to remain a key challenge,the Government has decided not to award any contracts until 80 per cent of land acquisition is already complete. Moreover, a good deal of political will is also getting things done.

To read the full article, CLICK HERE.

From a record 37 km per day in 2020-21, the pace of National Highway construction slowed to 20.43 km a day during the first four months of 2022. Considering this, it is natural to question the feasibility of the Indian Government’s plan to augment the pace of construction to 50km a day.CW takes a closer look… India is home to the world's second-largest road network. In the next five years, the Ministry of Road Transport and Highways (MoRTH) wants to complete 60,000 km of NH at an average daily construction rate of 40 km. Clearly, we need to pull up our socks to achieve this. Moreover, the target now is to attain 50 km a day. With an average construction cost of about Rs 30 crore per kilometre (including land acquisition costs) and a conservative inflation rate of 3 per cent for road-building costs, the total funding requirement over five years to attain this target will entail a good deal of investment from the Government. That said, Anshumali Srivastava, Chief General Manager – Mumbai, National Highways Authority of India(NHAI), believes we are pretty much on track as far as investments are concerned. “Road investment is increasing year on year [YoY]. In 2022-23, roads have seen the highest ever investments with Rs 2.15 lakh crore. Moreover, the banks have taken an interest in the sector. Due to InvITs, funding is easily available. Further, the National Infrastructure Pipeline [NIP] has been laid out for the next five years, which provides assurance to the market.” Cyclones, the monsoon and the secondary effect of COVID-19 did affect the pace of land acquisition because of which road construction has slowed down.But the construction of four, six and eight-lane National Highways has shot up by 300 per cent in the past seven years. So, despite the appalling effect of the pandemic, getting back to building 50km per day is not a far-fetched idea. Keeping in mind that land acquisition continues to remain a key challenge,the Government has decided not to award any contracts until 80 per cent of land acquisition is already complete. Moreover, a good deal of political will is also getting things done. To read the full article, CLICK HERE.

Next Story
Building Material

Trishakti Industries Secures Major Tata Steel Order

Trishakti Industries Limited has secured a significant order from Tata Steel Ltd for the deployment of advanced machinery and skilled manpower at one of the steel major’s flagship project sites.The contract, awarded domestically, involves the hiring of machines along with manpower, with execution set to be completed by 20th September 2025. The initial contract period is 12 months. The total fresh capital expenditure for the project is approximately Rs 1.5 million, while the overall contract value is expected to exceed Rs 5 million inclusive of taxes.This order marks a reinforcement of top-ti..

Next Story
Real Estate

Kalpataru Projects Secures Rs 27.2 Billion in New Orders

Kalpataru Projects International Limited (KPIL), a leading EPC player in the power transmission and distribution (T&D) and civil infrastructure sector, along with its international subsidiaries, has received new orders and notifications for projects worth approximately Rs 27.2 billion.The projects include:Power Transmission & Distribution (T&D) initiatives in India and overseas.Buildings and Factories (B&F) projects in India.Manish Mohnot, MD & CEO of KPIL, said, “We are delighted with the strong ordering momentum in our T&D and B&F businesses. The orders include ..

Next Story
Infrastructure Energy

ACME Solar Secures Rs 38.92 Billion Financing for Barmer Project

ACME Solar Holdings rose 2.05 per cent to Rs 308.50 after its wholly owned subsidiary, ACME Venus Urja, secured long-term project financing of Rs 38.92 billion from the State Bank of India (SBI).The funds will be utilised for the development and construction of a 400 MW Firm and Dispatchable Renewable Energy (FDRE) project in Barmer, Rajasthan. The loan repayment is structured over 19 years.The Barmer-based FDRE project is contracted with NHPC at a tariff of Rs 4.64 per unit. It will integrate solar power generation with a Battery Energy Storage System (BESS) to ensure higher reliability and d..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?