Can India build 50 km a day?
ROADS & HIGHWAYS

Can India build 50 km a day?

From a record 37 km per day in 2020-21, the pace of National Highway construction slowed to 20.43 km a day during the first four months of 2022. Considering this, it is natural to question the feasibility of the Indian Government’s plan to augment the pace of construction to 50km a day.CW takes a closer look…

India is home to the world's second-largest road network. In the next five years, the Ministry of Road Transport and Highways (MoRTH) wants to complete 60,000 km of NH at an average daily construction rate of 40 km. Clearly, we need to pull up our socks to achieve this. Moreover, the target now is to attain 50 km a day. With an average construction cost of about Rs 30 crore per kilometre (including land acquisition costs) and a conservative inflation rate of 3 per cent for road-building costs, the total funding requirement over five years to attain this target will entail a good deal of investment from the Government.

That said, Anshumali Srivastava, Chief General Manager – Mumbai, National Highways Authority of India(NHAI), believes we are pretty much on track as far as investments are concerned. “Road investment is increasing year on year [YoY]. In 2022-23, roads have seen the highest ever investments with Rs 2.15 lakh crore. Moreover, the banks have taken an interest in the sector. Due to InvITs, funding is easily available. Further, the National Infrastructure Pipeline [NIP] has been laid out for the next five years, which provides assurance to the market.”

Cyclones, the monsoon and the secondary effect of COVID-19 did affect the pace of land acquisition because of which road construction has slowed down.But the construction of four, six and eight-lane National Highways has shot up by 300 per cent in the past seven years. So, despite the appalling effect of the pandemic, getting back to building 50km per day is not a far-fetched idea.

Keeping in mind that land acquisition continues to remain a key challenge,the Government has decided not to award any contracts until 80 per cent of land acquisition is already complete. Moreover, a good deal of political will is also getting things done.

To read the full article, CLICK HERE.

From a record 37 km per day in 2020-21, the pace of National Highway construction slowed to 20.43 km a day during the first four months of 2022. Considering this, it is natural to question the feasibility of the Indian Government’s plan to augment the pace of construction to 50km a day.CW takes a closer look… India is home to the world's second-largest road network. In the next five years, the Ministry of Road Transport and Highways (MoRTH) wants to complete 60,000 km of NH at an average daily construction rate of 40 km. Clearly, we need to pull up our socks to achieve this. Moreover, the target now is to attain 50 km a day. With an average construction cost of about Rs 30 crore per kilometre (including land acquisition costs) and a conservative inflation rate of 3 per cent for road-building costs, the total funding requirement over five years to attain this target will entail a good deal of investment from the Government. That said, Anshumali Srivastava, Chief General Manager – Mumbai, National Highways Authority of India(NHAI), believes we are pretty much on track as far as investments are concerned. “Road investment is increasing year on year [YoY]. In 2022-23, roads have seen the highest ever investments with Rs 2.15 lakh crore. Moreover, the banks have taken an interest in the sector. Due to InvITs, funding is easily available. Further, the National Infrastructure Pipeline [NIP] has been laid out for the next five years, which provides assurance to the market.” Cyclones, the monsoon and the secondary effect of COVID-19 did affect the pace of land acquisition because of which road construction has slowed down.But the construction of four, six and eight-lane National Highways has shot up by 300 per cent in the past seven years. So, despite the appalling effect of the pandemic, getting back to building 50km per day is not a far-fetched idea. Keeping in mind that land acquisition continues to remain a key challenge,the Government has decided not to award any contracts until 80 per cent of land acquisition is already complete. Moreover, a good deal of political will is also getting things done. To read the full article, CLICK HERE.

Next Story
Real Estate

Indian REITs Offer 6-7.5 per cent Yield, Surpassing Many Global Markets

Indian Real Estate Investment Trusts (REITs) are delivering average yields of 6–7.5 per cent for unitholders, outperforming many mature markets, including the US, according to a report by Credai and Anarock.Credai, the apex body of Indian real estate developers, and property consultant Anarock released the report Indian REITs – A Gateway to Institutional Real Estate at an event in India.Currently, India has five listed REITs – Brookfield India Real Estate Trust, Embassy Office Parks REIT, Mindspace Business Parks REIT, Nexus Select Trust, and Knowledge Realty Trust. Nexus Select Trust pr..

Next Story
Infrastructure Energy

Insolation Energy Wins 226 MW Solar Projects Under PM-KUSUM

Insolation Energy on Monday announced securing multiple solar projects totalling 226.45 MW, with an investment of Rs 7.5 billion, under the PM-KUSUM scheme. The orders were awarded to its wholly-owned subsidiary, Insolation Green Energy Pvt Ltd, by Jaipur Vidyut Vitran Nigam Limited for 20 sites and Ajmer Vidyut Vitran Nigam Limited for 115 sites, the company informed the exchanges.“The combined SPV solar power plants will total 226.45 MW under PM-KUSUM Component A, with the final levelised tariff at Rs 3.04 per unit for 16 sites, Rs 2.82 per unit for 5 sites, Rs 2.75 per unit for 53 sites, ..

Next Story
Infrastructure Energy

Numaligarh Refinery Awards EPC Contract for Rooftop Solar Projects

State-owned Numaligarh Refinery Ltd. (NRL) has awarded a Letter of Award to Solarium Green Energy Ltd. for the rate contract covering the Engineering, Procurement, and Construction (EPC) of grid-connected rooftop solar PV projects at various locations. The projects fall within the categories of 51–200 kW and 201–1000 kW. Notable projects include a 140 kW rooftop solar plant at NRL Assam, a 760 kW plant at NRL Assam, and a 280 kW plant at NRL West Bengal.The supply order covers ex-manufacturing works and the dispatch price for plant and equipment for the 140 kW, 760 kW, and 280 kW rooftop s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?