Can India build 50 km a day?
ROADS & HIGHWAYS

Can India build 50 km a day?

From a record 37 km per day in 2020-21, the pace of National Highway construction slowed to 20.43 km a day during the first four months of 2022. Considering this, it is natural to question the feasibility of the Indian Government’s plan to augment the pace of construction to 50km a day.CW takes a closer look…

India is home to the world's second-largest road network. In the next five years, the Ministry of Road Transport and Highways (MoRTH) wants to complete 60,000 km of NH at an average daily construction rate of 40 km. Clearly, we need to pull up our socks to achieve this. Moreover, the target now is to attain 50 km a day. With an average construction cost of about Rs 30 crore per kilometre (including land acquisition costs) and a conservative inflation rate of 3 per cent for road-building costs, the total funding requirement over five years to attain this target will entail a good deal of investment from the Government.

That said, Anshumali Srivastava, Chief General Manager – Mumbai, National Highways Authority of India(NHAI), believes we are pretty much on track as far as investments are concerned. “Road investment is increasing year on year [YoY]. In 2022-23, roads have seen the highest ever investments with Rs 2.15 lakh crore. Moreover, the banks have taken an interest in the sector. Due to InvITs, funding is easily available. Further, the National Infrastructure Pipeline [NIP] has been laid out for the next five years, which provides assurance to the market.”

Cyclones, the monsoon and the secondary effect of COVID-19 did affect the pace of land acquisition because of which road construction has slowed down.But the construction of four, six and eight-lane National Highways has shot up by 300 per cent in the past seven years. So, despite the appalling effect of the pandemic, getting back to building 50km per day is not a far-fetched idea.

Keeping in mind that land acquisition continues to remain a key challenge,the Government has decided not to award any contracts until 80 per cent of land acquisition is already complete. Moreover, a good deal of political will is also getting things done.

To read the full article, CLICK HERE.

From a record 37 km per day in 2020-21, the pace of National Highway construction slowed to 20.43 km a day during the first four months of 2022. Considering this, it is natural to question the feasibility of the Indian Government’s plan to augment the pace of construction to 50km a day.CW takes a closer look… India is home to the world's second-largest road network. In the next five years, the Ministry of Road Transport and Highways (MoRTH) wants to complete 60,000 km of NH at an average daily construction rate of 40 km. Clearly, we need to pull up our socks to achieve this. Moreover, the target now is to attain 50 km a day. With an average construction cost of about Rs 30 crore per kilometre (including land acquisition costs) and a conservative inflation rate of 3 per cent for road-building costs, the total funding requirement over five years to attain this target will entail a good deal of investment from the Government. That said, Anshumali Srivastava, Chief General Manager – Mumbai, National Highways Authority of India(NHAI), believes we are pretty much on track as far as investments are concerned. “Road investment is increasing year on year [YoY]. In 2022-23, roads have seen the highest ever investments with Rs 2.15 lakh crore. Moreover, the banks have taken an interest in the sector. Due to InvITs, funding is easily available. Further, the National Infrastructure Pipeline [NIP] has been laid out for the next five years, which provides assurance to the market.” Cyclones, the monsoon and the secondary effect of COVID-19 did affect the pace of land acquisition because of which road construction has slowed down.But the construction of four, six and eight-lane National Highways has shot up by 300 per cent in the past seven years. So, despite the appalling effect of the pandemic, getting back to building 50km per day is not a far-fetched idea. Keeping in mind that land acquisition continues to remain a key challenge,the Government has decided not to award any contracts until 80 per cent of land acquisition is already complete. Moreover, a good deal of political will is also getting things done. To read the full article, CLICK HERE.

Next Story
Infrastructure Energy

Indian Airports Shift to Green Energy with Solar Power

India is leading a solar revolution in aviation, with more than forty-four airports operating fully on renewable energy as of mid-2023. Over one hundred and twenty airports are expected to become carbon-neutral by 2025, marking a major shift in sustainable infrastructure.The movement began with Cochin International Airport, the world’s first fully solar-powered airport in 2015. Its solar farm has grown from twelve megawatts to fifty megawatts, producing over seventy million units annually and offsetting more than 1.5 million tonnes of carbon dioxide. This success has inspired similar initiat..

Next Story
Real Estate

ED Searches 13 Locations Linked to Illegal Buildings in Vasai

The Mumbai Enforcement Directorate (ED) searched thirteen locations in Vasai and Virar linked to builders involved in constructing 41 illegal buildings on a 60-acre plot earmarked for public projects. These premises were connected to those responsible for unauthorised constructions in the Vasai-Virar Municipal Corporation (VVMC) area.The 41 illegal buildings were demolished by VVMC over twenty-two days earlier this year following Bombay High Court orders. The ED’s probe began after multiple first information reports by the Mira-Bhayandar police related to the illegal constructions.The ED fou..

Next Story
Real Estate

RERA Orders Builder to Refund Buyers for Project Delay in Telangana

The Telangana Real Estate Regulatory Authority (TGRERA) has ordered R Homes Realtors Global LLP to refund six buyers for delays in completing a residential project at Beeramguda. The buyers had booked flats in Jai Vasavi’s ORR Heights in 2021, paying over Rs eight million.The builder promised construction would start by January 2022 and flats would be handed over within thirty months of approvals. However, even after more than two years, only initial digging work was done. The builder changed building plans from five floors to nine without informing buyers or obtaining consent.RERA found tha..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?