Case Studies of Indian companies following Lean Construction
ROADS & HIGHWAYS

Case Studies of Indian companies following Lean Construction

When HCC was constructing the two-tier Bogibeel Bridge—the country’s longest rail-cum-road bridge—placing the 125-m long fully-welded steel spans, each weighing 1,700 tonne, on the pillars embedded in the riverbed was a challenge. “On-site engineers had two choices for a more practical and economical method, either lifting the spans with floating cranes or erecting them with a launching truss,” shares Amit Uplenchwar, CEO, HCC E&C. “After weighing the pros and cons, the team came up with a third solution of pulling the steel trusses with a set of jacks and winches on the pillars. This eliminated the need to enter the river. Besides, it also ensured safer working conditions, precluded the mobilisation of a giant setup on either side of the river and accelerated the project’s pace. The strategy proved testament to the global practice of Lean construction, which is changing the way projects are executed from design to construction.”

Shapoorji Pallonji Engineering & Construction has implemented Lean for an IT park spread over 40 acre with a built-up area of 3.5 m sq ft. It required coordination among 46 contractors having more than 2,000 workers at a time. “The project was struggling with coordination issues within and among teams, and wastage of material and labour at the same time,” says SC Dixit, Executive Director, Shapoorji Pallonji Engineering & Construction. “The implementation of Lean tools such as Last Planner System (LPS) helped in coordination and streamlining communication, while Value Stream Mapping (VSM) practices helped in reducing man days and improving productivity. Further, pull-based planning ensured optimistic targets, which is further reinforced by the rest of the tools, resulting in improved productivity; and a sense of waste reduction is nurtured in the team, which resulted in improved coordination and higher percentage plan completion.”

At one of Tata Realty and Infrastructure’s recent projects in Gurugram, a large SEZ project of about 5 million sq ft, “we have implemented Lean and created a Big Room,” says Prakash Patil, Secretary General, The Institute for Lean Construction Excellence, and Vice President-Projects, Tata Realty and Infrastructure. “We are using the Last Planner (r) System (LPS), Pull Planning, BIM etc, extensively here.”

- SERAPHINA D’SOUZA

When HCC was constructing the two-tier Bogibeel Bridge—the country’s longest rail-cum-road bridge—placing the 125-m long fully-welded steel spans, each weighing 1,700 tonne, on the pillars embedded in the riverbed was a challenge. “On-site engineers had two choices for a more practical and economical method, either lifting the spans with floating cranes or erecting them with a launching truss,” shares Amit Uplenchwar, CEO, HCC E&C. “After weighing the pros and cons, the team came up with a third solution of pulling the steel trusses with a set of jacks and winches on the pillars. This eliminated the need to enter the river. Besides, it also ensured safer working conditions, precluded the mobilisation of a giant setup on either side of the river and accelerated the project’s pace. The strategy proved testament to the global practice of Lean construction, which is changing the way projects are executed from design to construction.”Shapoorji Pallonji Engineering & Construction has implemented Lean for an IT park spread over 40 acre with a built-up area of 3.5 m sq ft. It required coordination among 46 contractors having more than 2,000 workers at a time. “The project was struggling with coordination issues within and among teams, and wastage of material and labour at the same time,” says SC Dixit, Executive Director, Shapoorji Pallonji Engineering & Construction. “The implementation of Lean tools such as Last Planner System (LPS) helped in coordination and streamlining communication, while Value Stream Mapping (VSM) practices helped in reducing man days and improving productivity. Further, pull-based planning ensured optimistic targets, which is further reinforced by the rest of the tools, resulting in improved productivity; and a sense of waste reduction is nurtured in the team, which resulted in improved coordination and higher percentage plan completion.”At one of Tata Realty and Infrastructure’s recent projects in Gurugram, a large SEZ project of about 5 million sq ft, “we have implemented Lean and created a Big Room,” says Prakash Patil, Secretary General, The Institute for Lean Construction Excellence, and Vice President-Projects, Tata Realty and Infrastructure. “We are using the Last Planner (r) System (LPS), Pull Planning, BIM etc, extensively here.”- SERAPHINA D’SOUZA

Next Story
Technology

Panasonic Showcases Advanced Automation Solutions at India Warehousing Show 2025

Panasonic Life Solutions India’s Industrial Division showcased its latest automation solutions at the India Warehousing Show 2025. Demonstrating over four decades of design expertise, the company presented its comprehensive portfolio, including advanced PLCs, high-speed sensors, servo systems, HMIs, and laser markers designed to optimise manufacturing productivity, safety, and control. The event highlighted solutions across key sectors such as automotive, electronics, pharmaceuticals, textiles, packaging, and warehousing. Among the innovations on display were the HL-G2 Series laser sens..

Next Story
Real Estate

Signature Global to Raise Rs 8.75 billion via NCDs for Debt Refinancing, Expansion

Realty major Signature Global has announced plans to raise up to Rs 8.75 billion through the issuance of secured, listed, redeemable non-convertible debentures (NCDs) on a private placement basis. The fundraising will be executed in one or more tranches and is expected to conclude by August, subject to shareholder approval. Of the total proceeds, Rs 4.5 billion will be utilised to refinance existing debt, while the remaining amount will support business expansion initiatives, Chairman Pradeep Kumar Aggarwal confirmed to PTI. The board has approved the proposal and the company will no..

Next Story
Real Estate

Capacit’e Infraprojects Wins Rs 6.21 billion order from Saifee Burhani Upliftment Trust

Capacit’e Infraprojects has secured a Letter of Intent (LOI) worth Rs 6.21 billion (excluding GST) from Saifee Burhani Upliftment Trust (SBUT) for the execution of core and shell works, finishing, MEPF services, and other associated components of the redevelopment project—Sector 07 of the Saifee Burhani Upliftment Project—located at Ward ‘C’, Bhendi Bazaar, Mumbai. This is the third repeat order from SBUT to Capacit’e Infraprojects, underscoring the trust and satisfaction of a long-standing client in the company’s project delivery capabilities. Commenting on the develop..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?