Case Studies of Indian companies following Lean Construction
ROADS & HIGHWAYS

Case Studies of Indian companies following Lean Construction

When HCC was constructing the two-tier Bogibeel Bridge—the country’s longest rail-cum-road bridge—placing the 125-m long fully-welded steel spans, each weighing 1,700 tonne, on the pillars embedded in the riverbed was a challenge. “On-site engineers had two choices for a more practical and economical method, either lifting the spans with floating cranes or erecting them with a launching truss,” shares Amit Uplenchwar, CEO, HCC E&C. “After weighing the pros and cons, the team came up with a third solution of pulling the steel trusses with a set of jacks and winches on the pillars. This eliminated the need to enter the river. Besides, it also ensured safer working conditions, precluded the mobilisation of a giant setup on either side of the river and accelerated the project’s pace. The strategy proved testament to the global practice of Lean construction, which is changing the way projects are executed from design to construction.”

Shapoorji Pallonji Engineering & Construction has implemented Lean for an IT park spread over 40 acre with a built-up area of 3.5 m sq ft. It required coordination among 46 contractors having more than 2,000 workers at a time. “The project was struggling with coordination issues within and among teams, and wastage of material and labour at the same time,” says SC Dixit, Executive Director, Shapoorji Pallonji Engineering & Construction. “The implementation of Lean tools such as Last Planner System (LPS) helped in coordination and streamlining communication, while Value Stream Mapping (VSM) practices helped in reducing man days and improving productivity. Further, pull-based planning ensured optimistic targets, which is further reinforced by the rest of the tools, resulting in improved productivity; and a sense of waste reduction is nurtured in the team, which resulted in improved coordination and higher percentage plan completion.”

At one of Tata Realty and Infrastructure’s recent projects in Gurugram, a large SEZ project of about 5 million sq ft, “we have implemented Lean and created a Big Room,” says Prakash Patil, Secretary General, The Institute for Lean Construction Excellence, and Vice President-Projects, Tata Realty and Infrastructure. “We are using the Last Planner (r) System (LPS), Pull Planning, BIM etc, extensively here.”

- SERAPHINA D’SOUZA

When HCC was constructing the two-tier Bogibeel Bridge—the country’s longest rail-cum-road bridge—placing the 125-m long fully-welded steel spans, each weighing 1,700 tonne, on the pillars embedded in the riverbed was a challenge. “On-site engineers had two choices for a more practical and economical method, either lifting the spans with floating cranes or erecting them with a launching truss,” shares Amit Uplenchwar, CEO, HCC E&C. “After weighing the pros and cons, the team came up with a third solution of pulling the steel trusses with a set of jacks and winches on the pillars. This eliminated the need to enter the river. Besides, it also ensured safer working conditions, precluded the mobilisation of a giant setup on either side of the river and accelerated the project’s pace. The strategy proved testament to the global practice of Lean construction, which is changing the way projects are executed from design to construction.”Shapoorji Pallonji Engineering & Construction has implemented Lean for an IT park spread over 40 acre with a built-up area of 3.5 m sq ft. It required coordination among 46 contractors having more than 2,000 workers at a time. “The project was struggling with coordination issues within and among teams, and wastage of material and labour at the same time,” says SC Dixit, Executive Director, Shapoorji Pallonji Engineering & Construction. “The implementation of Lean tools such as Last Planner System (LPS) helped in coordination and streamlining communication, while Value Stream Mapping (VSM) practices helped in reducing man days and improving productivity. Further, pull-based planning ensured optimistic targets, which is further reinforced by the rest of the tools, resulting in improved productivity; and a sense of waste reduction is nurtured in the team, which resulted in improved coordination and higher percentage plan completion.”At one of Tata Realty and Infrastructure’s recent projects in Gurugram, a large SEZ project of about 5 million sq ft, “we have implemented Lean and created a Big Room,” says Prakash Patil, Secretary General, The Institute for Lean Construction Excellence, and Vice President-Projects, Tata Realty and Infrastructure. “We are using the Last Planner (r) System (LPS), Pull Planning, BIM etc, extensively here.”- SERAPHINA D’SOUZA

Next Story
Infrastructure Transport

RAHSTA 2026 to Host Certified Highway Construction Masterclass

RAHSTA 2026 will organise the Certified Highway Construction Masterclass, a specialised two-day corporate training programme for highway construction professionals, on July 8–9, 2026, at the Jio World Convention Centre.The Masterclass will be delivered by RASTA – Center for Road Technology and supported by Construction World and FIRST Construction Council.Designed as an industry-led refresher programme, the Masterclass aims to help engineering and project teams stay updated with the latest advancements in highway construction, pavement technologies, sustainable materials, intelligent compa..

Next Story
Infrastructure Urban

Grand Mercure Mysuru Turns 10; BHVL to Invest Rs 1,000 Crore in Karnataka

Brigade Hotel Ventures Limited (BHVL) has marked the 10th anniversary of its flagship property, Grand Mercure Mysuru, by announcing a major investment plan of around Rs 1,000 crore in Karnataka over the next five years. The company said the investment will be directed towards new hospitality projects as well as modernisation of existing assets, aligning with the evolving demand for experiential tourism.The announcement comes as BHVL reiterated its focus on strengthening Mysuru’s position as a prominent global tourism destination by supporting the local micro-economy and adopting sustainable ..

Next Story
Infrastructure Urban

Ottobock and Celcius Set Up Prosthetics Warehouse in India

Celcius Logistics, a domestic third-party logistics (3PL) company specialising in end-to-end cold-chain solutions, has partnered with Ottobock India, the Indian arm of Germany-based Ottobock, to establish a dedicated prosthetics warehouse and logistics distribution hub in India. As part of the collaboration, a technology-enabled facility has been launched in Thane to streamline storage and nationwide movement of prosthetic and assistive devices.The dedicated warehouse is expected to strengthen the medical supply chain by reducing turnaround time and improving access to prosthetic products acro..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement