+
Case Studies of Indian companies following Lean Construction
ROADS & HIGHWAYS

Case Studies of Indian companies following Lean Construction

When HCC was constructing the two-tier Bogibeel Bridge—the country’s longest rail-cum-road bridge—placing the 125-m long fully-welded steel spans, each weighing 1,700 tonne, on the pillars embedded in the riverbed was a challenge. “On-site engineers had two choices for a more practical and economical method, either lifting the spans with floating cranes or erecting them with a launching truss,” shares Amit Uplenchwar, CEO, HCC E&C. “After weighing the pros and cons, the team came up with a third solution of pulling the steel trusses with a set of jacks and winches on the pillars. This eliminated the need to enter the river. Besides, it also ensured safer working conditions, precluded the mobilisation of a giant setup on either side of the river and accelerated the project’s pace. The strategy proved testament to the global practice of Lean construction, which is changing the way projects are executed from design to construction.”

Shapoorji Pallonji Engineering & Construction has implemented Lean for an IT park spread over 40 acre with a built-up area of 3.5 m sq ft. It required coordination among 46 contractors having more than 2,000 workers at a time. “The project was struggling with coordination issues within and among teams, and wastage of material and labour at the same time,” says SC Dixit, Executive Director, Shapoorji Pallonji Engineering & Construction. “The implementation of Lean tools such as Last Planner System (LPS) helped in coordination and streamlining communication, while Value Stream Mapping (VSM) practices helped in reducing man days and improving productivity. Further, pull-based planning ensured optimistic targets, which is further reinforced by the rest of the tools, resulting in improved productivity; and a sense of waste reduction is nurtured in the team, which resulted in improved coordination and higher percentage plan completion.”

At one of Tata Realty and Infrastructure’s recent projects in Gurugram, a large SEZ project of about 5 million sq ft, “we have implemented Lean and created a Big Room,” says Prakash Patil, Secretary General, The Institute for Lean Construction Excellence, and Vice President-Projects, Tata Realty and Infrastructure. “We are using the Last Planner (r) System (LPS), Pull Planning, BIM etc, extensively here.”

- SERAPHINA D’SOUZA

When HCC was constructing the two-tier Bogibeel Bridge—the country’s longest rail-cum-road bridge—placing the 125-m long fully-welded steel spans, each weighing 1,700 tonne, on the pillars embedded in the riverbed was a challenge. “On-site engineers had two choices for a more practical and economical method, either lifting the spans with floating cranes or erecting them with a launching truss,” shares Amit Uplenchwar, CEO, HCC E&C. “After weighing the pros and cons, the team came up with a third solution of pulling the steel trusses with a set of jacks and winches on the pillars. This eliminated the need to enter the river. Besides, it also ensured safer working conditions, precluded the mobilisation of a giant setup on either side of the river and accelerated the project’s pace. The strategy proved testament to the global practice of Lean construction, which is changing the way projects are executed from design to construction.”Shapoorji Pallonji Engineering & Construction has implemented Lean for an IT park spread over 40 acre with a built-up area of 3.5 m sq ft. It required coordination among 46 contractors having more than 2,000 workers at a time. “The project was struggling with coordination issues within and among teams, and wastage of material and labour at the same time,” says SC Dixit, Executive Director, Shapoorji Pallonji Engineering & Construction. “The implementation of Lean tools such as Last Planner System (LPS) helped in coordination and streamlining communication, while Value Stream Mapping (VSM) practices helped in reducing man days and improving productivity. Further, pull-based planning ensured optimistic targets, which is further reinforced by the rest of the tools, resulting in improved productivity; and a sense of waste reduction is nurtured in the team, which resulted in improved coordination and higher percentage plan completion.”At one of Tata Realty and Infrastructure’s recent projects in Gurugram, a large SEZ project of about 5 million sq ft, “we have implemented Lean and created a Big Room,” says Prakash Patil, Secretary General, The Institute for Lean Construction Excellence, and Vice President-Projects, Tata Realty and Infrastructure. “We are using the Last Planner (r) System (LPS), Pull Planning, BIM etc, extensively here.”- SERAPHINA D’SOUZA

Next Story
Equipment

Liebherr secures 130-dozer deal with Turkey’s State Hydraulic Works

Liebherr Turkey has signed a major equipment supply agreement with the Turkish State Hydraulic Works (DSİ) for the delivery of 130 crawler tractors to be used across the country’s key infrastructure and environmental projects.The agreement covers 120 PR 756 Litronic and 10 PR 736 Litronic crawler tractors, with production scheduled at Liebherr’s facility in Telfs, Austria. This marks a significant continuation of the long-standing collaboration between DSİ and Liebherr, which began over a decade ago with the delivery of PR 754 Litronic dozers.Designed for heavy-duty operations, the PR 75..

Next Story
Infrastructure Transport

Noida to Revamp Transport Nagar Chowk with Rs 4-Crore Beautification Plan

The Noida Authority has unveiled plans to redevelop Transport Nagar Chowk in Sector 67 with a Rs 4-crore beautification project. Aimed at enhancing connectivity, accessibility, and urban aesthetics, the project will upgrade a 500-metre stretch along DSC Road with modern, inclusive, and sustainable infrastructure.Officials stated that the stretch will be enhanced with ornamental lighting, sculptures, seating areas, bollards, food kiosks, and ramps for differently-abled individuals. A tender for the project is expected to be issued soon.Neelima Rana, partner at Orionn Architects—the firm behin..

Next Story
Infrastructure Transport

Centre Approves Noida Metro Extension to Bodaki Multimodal Hub

The Central government has approved the extension of the Noida Metro Aqua Line from Depot Station to the upcoming Multimodal Transport Hub (MMTH) at Bodaki, marking a major push for enhanced connectivity in the National Capital Region (NCR). The 2.6-km extension is expected to be completed within three years.The project, already cleared by the Uttar Pradesh Cabinet, will now move to the construction stage under the supervision of the Noida Metro Rail Corporation (NMRC). The extended route will include two additional stations — Junpat Village and Bodaki — connecting to the MMTH, which will ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?