Chennai Peripheral Ring Road Nears 2025 Completion
ROADS & HIGHWAYS

Chennai Peripheral Ring Road Nears 2025 Completion

Spanning 132.87 kilometres, the Chennai Peripheral Ring Road (CPRR) is set to transform regional connectivity across Tamil Nadu. The six-lane, access-controlled expressway will link Ennore Port to Mahabalipuram, joining several key national highways. With an estimated cost of Rs 123 billion, the project is scheduled for completion by the end of 2025. The Tamil Nadu Road Development Company (TNRDC) is overseeing its implementation.

The CPRR will pass through seven major urban areas including Singaperumalkoil, Sriperumbudur, Tiruvallur, Tamaraipakkam, Periyapalayam, Puduvoyal, and Kattupalli. Once operational, it will connect to NH5 (Chennai–Tada), NH4 (Chennai–Bengaluru), NH45 (Chennai–Tiruchirappalli), and the East Coast Road (ECR), significantly enhancing road mobility across the region.

In addition to its main lanes, the expressway will feature service roads for local traffic to ensure seamless vehicular movement. According to a Magicbricks report, the CPRR will also directly connect Ennore and Kattupalli ports, strengthening logistics access.

The CPRR will be integrated with major National Highways Authority of India (NHAI) corridors such as the Bengaluru–Chennai and Chittoor–Thatchur expressways. Designed for speeds of up to 120 kilometres per hour, the route will include an Intelligent Transport System (ITS) to enhance road safety and traffic management.

Meanwhile, Indian Railways plans to launch the Amrit Bharat Express service between Howrah and Chennai in the 2025–26 financial year. This special train will travel via Visakhapatnam, covering the 1,662-kilometre journey in under 26 hours. Operating twice weekly, the service will offer a maximum speed of 130 km/h, further improving intercity travel between eastern and southern India.


Spanning 132.87 kilometres, the Chennai Peripheral Ring Road (CPRR) is set to transform regional connectivity across Tamil Nadu. The six-lane, access-controlled expressway will link Ennore Port to Mahabalipuram, joining several key national highways. With an estimated cost of Rs 123 billion, the project is scheduled for completion by the end of 2025. The Tamil Nadu Road Development Company (TNRDC) is overseeing its implementation.The CPRR will pass through seven major urban areas including Singaperumalkoil, Sriperumbudur, Tiruvallur, Tamaraipakkam, Periyapalayam, Puduvoyal, and Kattupalli. Once operational, it will connect to NH5 (Chennai–Tada), NH4 (Chennai–Bengaluru), NH45 (Chennai–Tiruchirappalli), and the East Coast Road (ECR), significantly enhancing road mobility across the region.In addition to its main lanes, the expressway will feature service roads for local traffic to ensure seamless vehicular movement. According to a Magicbricks report, the CPRR will also directly connect Ennore and Kattupalli ports, strengthening logistics access.The CPRR will be integrated with major National Highways Authority of India (NHAI) corridors such as the Bengaluru–Chennai and Chittoor–Thatchur expressways. Designed for speeds of up to 120 kilometres per hour, the route will include an Intelligent Transport System (ITS) to enhance road safety and traffic management.Meanwhile, Indian Railways plans to launch the Amrit Bharat Express service between Howrah and Chennai in the 2025–26 financial year. This special train will travel via Visakhapatnam, covering the 1,662-kilometre journey in under 26 hours. Operating twice weekly, the service will offer a maximum speed of 130 km/h, further improving intercity travel between eastern and southern India.

Next Story
Infrastructure Transport

MMRDA Installs 325-Tonne Steel Spans on Mumbai Metro Line 4

The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a key construction milestone on Metro Line 4 with the successful installation of three large steel spans at Bhandup West during overnight operations.The spans, together weighing 325 metric tonnes, were launched using eight heavy-duty cranes and 12 multi-axle vehicles. The operation required precise engineering and meticulous planning to minimise disruption in the densely populated suburban area.Due to effective inter-agency coordination, the work—originally scheduled across four nights—was completed within just two n..

Next Story
Infrastructure Transport

CMRL Targets March 2027 Opening for Vadapalani–Panagal Park

Chennai Metro Rail Limited (CMRL) is progressing as scheduled to open the Vadapalani–Panagal Park section of Phase II’s Corridor 4 by March 2027. The 3.5 km underground stretch is part of the 26.1 km Corridor 4 connecting Lighthouse with Poonamallee Bypass.Construction activities are advancing steadily, with tunnelling works between Vadapalani and Panagal Park already completed. Track-laying operations are expected to commence shortly. At Panagal Park station, structural works have reached the concourse and platform levels, while excavation continues at the lowest level.CMRL is also consid..

Next Story
Infrastructure Transport

Maha-Metro Invites Pune Metro Civil Maintenance Bids

Maharashtra Metro Rail Corporation Limited (Maha-Metro) has invited bids for the annual civil maintenance contract of the Pune Metro Rail Project. The tender, bearing ID and number P1-O&M-20/2025, is scheduled to close on 23 February 2026, with a pre-bid meeting slated for 10 February 2026. The earnest money deposit (EMD) for the contract is Rs 3,50,500, and the duration of the contract is one year.The scope of work includes annual civil maintenance of 28 elevated and underground stations, 28.079 km of elevated viaduct including steel bridges, 12.15 km of tunnels, and two depots under the ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App