Complexities in bridge construction
ROADS & HIGHWAYS

Complexities in bridge construction

The success of a bridge project depends on the management of various complex and interlinked issues such as timely decisions, robust risk assessment and its mitigation, timely approvals of design and drawings, effective mobilisation of men and machinery, material planning, implementation of right construction methods, project and financial management, prompt and timely troubleshooting, and optimal and effective usage of resources. While all these factors carry inherent complexities, there could be more issues that are technical and administrative in nature. SV Desai, Executive Vice-President & Head - Heavy Civil Infrastructure IC, L&T Construction, elaborates....

  • Availability of RoW and environmental clearances can eventually determine whether a contractor is able to deliver a project. Some L&T projects like Delhi’s Barapullah Bridge, Mandovi Bridge in Panaji, Goa, Khulna Mongla Bridge in Bangladesh and even Hyderabad’s Durgam Cheruvu Bridge have suffered initial delays owing to non-availability of RoW. A more recent example is the Mumbai Coastal Road project, stalled because of public agitations and environmental issues. A mechanism should be put in place by the respective state and central ministries to eliminate delays on account of these two factors.
  • Non-availability of skilled labour and execution staff is another pressing issue. The Government has set up a Skills Development Council to encourage industries to develop skills and create a pool of trained indigenous workforce. L&T has established eight Construction Skills Training Institutes across India to impart training in various aspects of construction and improve productivity. Development of frontline supervisors is another initiative by the company to train fresh engineers in supervisory roles by exposing them to various aspects of construction. Despite all these efforts, owing to the boom in the construction industry, contractors are feeling the acute shortfall of skilled workforce, resulting in delays in project execution. 
  • Construction challenges could be several, starting with the construction of the foundation of a bridge that depends on the type (open, pile, well, or any other), soil strata, machineries deployed and other logistic issues. In the case of the third Mandovi Bridge, special engineering techniques were adopted to counter the rock boulders left over from the construction of the two earlier bridges. Similar surprises in the foundation media can delay construction if not addressed adequately at the design stage. The next critical step is the construction of the superstructure that involves transport of heavy precast elements through busy roads/waterways, and positioning and erecting them at site. This issue must be addressed with correct design and construction technology right at the planning stage to avoid mishaps, delays and consequent cost escalation. 
  • Changes: Complexities could arise from changes in the alignment of the bridge. Unchartered utilities like underground pipe lines, gas lines, cables and high-tension electrical lines are most commonly encountered while constructing bridges. Shifting or relocating these utilities requires approvals from government bodies resulting in undue delay. In several instances, bridges have to be redesigned as some the utilities cannot be re-routed or disconnected. 
  • Adverse and challenging terrain can impact delivery. L&T’s project to construct the Kachchi Dargah Bridge in Patna across the Ganga has often been disrupted owing to frequent and sudden floods. The construction of the Panvel Nadi viaduct in Maharashtra for Konkan Railways, one of Asia’s tallest viaducts, involved the use of the innovative incremental push method across a deep gorge. Numerous such instances have been faced by L&T at various bridge projects across the country.

The success of a bridge project depends on the management of various complex and interlinked issues such as timely decisions, robust risk assessment and its mitigation, timely approvals of design and drawings, effective mobilisation of men and machinery, material planning, implementation of right construction methods, project and financial management, prompt and timely troubleshooting, and optimal and effective usage of resources. While all these factors carry inherent complexities, there could be more issues that are technical and administrative in nature. SV Desai, Executive Vice-President & Head - Heavy Civil Infrastructure IC, L&T Construction, elaborates....Availability of RoW and environmental clearances can eventually determine whether a contractor is able to deliver a project. Some L&T projects like Delhi’s Barapullah Bridge, Mandovi Bridge in Panaji, Goa, Khulna Mongla Bridge in Bangladesh and even Hyderabad’s Durgam Cheruvu Bridge have suffered initial delays owing to non-availability of RoW. A more recent example is the Mumbai Coastal Road project, stalled because of public agitations and environmental issues. A mechanism should be put in place by the respective state and central ministries to eliminate delays on account of these two factors.Non-availability of skilled labour and execution staff is another pressing issue. The Government has set up a Skills Development Council to encourage industries to develop skills and create a pool of trained indigenous workforce. L&T has established eight Construction Skills Training Institutes across India to impart training in various aspects of construction and improve productivity. Development of frontline supervisors is another initiative by the company to train fresh engineers in supervisory roles by exposing them to various aspects of construction. Despite all these efforts, owing to the boom in the construction industry, contractors are feeling the acute shortfall of skilled workforce, resulting in delays in project execution. Construction challenges could be several, starting with the construction of the foundation of a bridge that depends on the type (open, pile, well, or any other), soil strata, machineries deployed and other logistic issues. In the case of the third Mandovi Bridge, special engineering techniques were adopted to counter the rock boulders left over from the construction of the two earlier bridges. Similar surprises in the foundation media can delay construction if not addressed adequately at the design stage. The next critical step is the construction of the superstructure that involves transport of heavy precast elements through busy roads/waterways, and positioning and erecting them at site. This issue must be addressed with correct design and construction technology right at the planning stage to avoid mishaps, delays and consequent cost escalation. Changes: Complexities could arise from changes in the alignment of the bridge. Unchartered utilities like underground pipe lines, gas lines, cables and high-tension electrical lines are most commonly encountered while constructing bridges. Shifting or relocating these utilities requires approvals from government bodies resulting in undue delay. In several instances, bridges have to be redesigned as some the utilities cannot be re-routed or disconnected. Adverse and challenging terrain can impact delivery. L&T’s project to construct the Kachchi Dargah Bridge in Patna across the Ganga has often been disrupted owing to frequent and sudden floods. The construction of the Panvel Nadi viaduct in Maharashtra for Konkan Railways, one of Asia’s tallest viaducts, involved the use of the innovative incremental push method across a deep gorge. Numerous such instances have been faced by L&T at various bridge projects across the country.

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement