Construction Accelerates in Silkyara-Barkot Tunnel Project
ROADS & HIGHWAYS

Construction Accelerates in Silkyara-Barkot Tunnel Project

The ambitious Silkyara-Barkot tunnel project in Uttarkashi is witnessing a significant surge in construction activities as the endeavor pushes forward to meet its milestones. Recent updates from the site reveal substantial advancements on both ends of the tunnel, marking progress in excavation and preparation for the crucial dewatering process.

According to Col Deepak Patil, the project manager of NHIDCL, the agency tasked with executing the tunnel project, significant strides have been made in securing the entrance on the Silkyara end. With this accomplishment in place, the construction team is now poised to commence the dewatering process, a pivotal phase in tunnel construction.

"We have secured the red zones on the Silkyara end and are now preparing for the dewatering process which will get started within the next three to four days," stated Col Patil. However, he acknowledged that this phase presents unique challenges, particularly in managing water accumulation at the other end of the debris.

Highlighting the complexities involved, Col Patil explained, "To reach there, we have to pass through a 50m long escape passage, which was made of 800mm diameter steel pipes during the rescue operation." This intricate maneuver underscores the meticulous planning and execution required in such endeavors.

Excavation work from the Barkot end of the tunnel has also commenced, marking significant progress in extending the tunnel's reach. As of now, approximately 4-5 meters of area have been successfully dug up, signaling the project's steady advancement.

However, amidst the progress, challenges loom large. Col Patil emphasized the risks associated with the project, including the potential for landslides in the fractured zone and the formation of poisonous gases inside the tunnel. Such hazards underscore the need for stringent safety measures and constant vigilance to mitigate risks and ensure the well-being of the construction crew.

Despite these challenges, the momentum gained in the construction of the Silkyara-Barkot tunnel underscores the commitment and resilience of all involved parties. As the project forges ahead, it promises to enhance connectivity and unlock new opportunities for the region, heralding a brighter future for Uttarkashi and its surrounding areas.

The ambitious Silkyara-Barkot tunnel project in Uttarkashi is witnessing a significant surge in construction activities as the endeavor pushes forward to meet its milestones. Recent updates from the site reveal substantial advancements on both ends of the tunnel, marking progress in excavation and preparation for the crucial dewatering process. According to Col Deepak Patil, the project manager of NHIDCL, the agency tasked with executing the tunnel project, significant strides have been made in securing the entrance on the Silkyara end. With this accomplishment in place, the construction team is now poised to commence the dewatering process, a pivotal phase in tunnel construction. We have secured the red zones on the Silkyara end and are now preparing for the dewatering process which will get started within the next three to four days, stated Col Patil. However, he acknowledged that this phase presents unique challenges, particularly in managing water accumulation at the other end of the debris. Highlighting the complexities involved, Col Patil explained, To reach there, we have to pass through a 50m long escape passage, which was made of 800mm diameter steel pipes during the rescue operation. This intricate maneuver underscores the meticulous planning and execution required in such endeavors. Excavation work from the Barkot end of the tunnel has also commenced, marking significant progress in extending the tunnel's reach. As of now, approximately 4-5 meters of area have been successfully dug up, signaling the project's steady advancement. However, amidst the progress, challenges loom large. Col Patil emphasized the risks associated with the project, including the potential for landslides in the fractured zone and the formation of poisonous gases inside the tunnel. Such hazards underscore the need for stringent safety measures and constant vigilance to mitigate risks and ensure the well-being of the construction crew. Despite these challenges, the momentum gained in the construction of the Silkyara-Barkot tunnel underscores the commitment and resilience of all involved parties. As the project forges ahead, it promises to enhance connectivity and unlock new opportunities for the region, heralding a brighter future for Uttarkashi and its surrounding areas.

Next Story
Infrastructure Transport

PM to Inaugurate Indore Metro Phase 1 and Datia Satna Airports on May 31

Prime Minister Narendra Modi is scheduled to inaugurate the first phase of the Indore Metro Rail project, along with the Datia and Satna airports, via video conferencing during his visit to Bhopal on May 31, according to a senior Madhya Pradesh cabinet official.During his day-long visit to Bhopal, the Prime Minister will also participate in a conference organized to commemorate the 300th birth anniversary of Devi Ahilyabai Holkar, the historic queen of the Malwa kingdom, now part of Madhya Pradesh, as stated by the Parliamentary Affairs Minister and Cabinet spokesperson Kailash Vijayvargiya.It..

Next Story
Infrastructure Transport

Kochi Metro Holds Talks with BPCL to Restore Greenery on Medians

Kochi Metro Rail (KMRL), facing increasing criticism for not maintaining the green spaces along the medians in the metro corridor, has initiated discussions with Bharat Petroleum Corporation (BPCL) and the Ernakulam District Horticulture Society to revive the project.Sources reveal that KMRL is also making fresh efforts to find sponsors to care for and maintain the gardens located between the metro pillars. Previously, several sponsors had withdrawn, which led to the neglect of these green areas.There are 989 medians along the 28-km Kochi Metro stretch. Of these, 465 are under the National Hig..

Next Story
Infrastructure Transport

Rajasthan CM Approves DPR for Jaipur Metro Phase-2 Expansion

Rajasthan Chief Minister Bhajanlal Sharma approved the detailed project report (DPR) of Jaipur Metro Phase-2 and forwarded it to the Central Government.The construction work for the project is set to begin once the Union Ministry of Housing and Urban Affairs grants approval to the DPR.Phase 2 of Jaipur Metro had been announced in the state budget for 2025-26.The project, covering a 42.80-km stretch from Todi Mode to Prahladpura, will be implemented by the Rajasthan Metro Rail Corporation—a newly formed 50:50 joint venture between the state and Central governments. The corporation will be res..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?