Construction Accelerates in Silkyara-Barkot Tunnel Project
ROADS & HIGHWAYS

Construction Accelerates in Silkyara-Barkot Tunnel Project

The ambitious Silkyara-Barkot tunnel project in Uttarkashi is witnessing a significant surge in construction activities as the endeavor pushes forward to meet its milestones. Recent updates from the site reveal substantial advancements on both ends of the tunnel, marking progress in excavation and preparation for the crucial dewatering process.

According to Col Deepak Patil, the project manager of NHIDCL, the agency tasked with executing the tunnel project, significant strides have been made in securing the entrance on the Silkyara end. With this accomplishment in place, the construction team is now poised to commence the dewatering process, a pivotal phase in tunnel construction.

"We have secured the red zones on the Silkyara end and are now preparing for the dewatering process which will get started within the next three to four days," stated Col Patil. However, he acknowledged that this phase presents unique challenges, particularly in managing water accumulation at the other end of the debris.

Highlighting the complexities involved, Col Patil explained, "To reach there, we have to pass through a 50m long escape passage, which was made of 800mm diameter steel pipes during the rescue operation." This intricate maneuver underscores the meticulous planning and execution required in such endeavors.

Excavation work from the Barkot end of the tunnel has also commenced, marking significant progress in extending the tunnel's reach. As of now, approximately 4-5 meters of area have been successfully dug up, signaling the project's steady advancement.

However, amidst the progress, challenges loom large. Col Patil emphasized the risks associated with the project, including the potential for landslides in the fractured zone and the formation of poisonous gases inside the tunnel. Such hazards underscore the need for stringent safety measures and constant vigilance to mitigate risks and ensure the well-being of the construction crew.

Despite these challenges, the momentum gained in the construction of the Silkyara-Barkot tunnel underscores the commitment and resilience of all involved parties. As the project forges ahead, it promises to enhance connectivity and unlock new opportunities for the region, heralding a brighter future for Uttarkashi and its surrounding areas.

The ambitious Silkyara-Barkot tunnel project in Uttarkashi is witnessing a significant surge in construction activities as the endeavor pushes forward to meet its milestones. Recent updates from the site reveal substantial advancements on both ends of the tunnel, marking progress in excavation and preparation for the crucial dewatering process. According to Col Deepak Patil, the project manager of NHIDCL, the agency tasked with executing the tunnel project, significant strides have been made in securing the entrance on the Silkyara end. With this accomplishment in place, the construction team is now poised to commence the dewatering process, a pivotal phase in tunnel construction. We have secured the red zones on the Silkyara end and are now preparing for the dewatering process which will get started within the next three to four days, stated Col Patil. However, he acknowledged that this phase presents unique challenges, particularly in managing water accumulation at the other end of the debris. Highlighting the complexities involved, Col Patil explained, To reach there, we have to pass through a 50m long escape passage, which was made of 800mm diameter steel pipes during the rescue operation. This intricate maneuver underscores the meticulous planning and execution required in such endeavors. Excavation work from the Barkot end of the tunnel has also commenced, marking significant progress in extending the tunnel's reach. As of now, approximately 4-5 meters of area have been successfully dug up, signaling the project's steady advancement. However, amidst the progress, challenges loom large. Col Patil emphasized the risks associated with the project, including the potential for landslides in the fractured zone and the formation of poisonous gases inside the tunnel. Such hazards underscore the need for stringent safety measures and constant vigilance to mitigate risks and ensure the well-being of the construction crew. Despite these challenges, the momentum gained in the construction of the Silkyara-Barkot tunnel underscores the commitment and resilience of all involved parties. As the project forges ahead, it promises to enhance connectivity and unlock new opportunities for the region, heralding a brighter future for Uttarkashi and its surrounding areas.

Next Story
Infrastructure Urban

VECV Sales Rise 7.8 Per Cent In May 2026

VE Commercial Vehicles recorded sales of 7,978 units in May 2026, compared to 7,401 units in May 2025, registering growth of 7.8 per cent. This included 7,789 units from the Eicher brand and 189 units from the Volvo brand.Eicher branded trucks and buses reported sales of 7,789 units during the month, up 7.3 per cent from 7,258 units a year earlier. In the domestic commercial vehicle market, Eicher sales rose 9.1 per cent to 7,375 units from 6,758 units in May 2025.Exports declined 17.2 per cent to 414 units from 500 units in the corresponding month last year. Volvo Trucks and Volvo Buses recor..

Next Story
Infrastructure Urban

Table Space Strengthens DESYN Leadership Team

Table Space has announced strategic leadership appointments within DESYN, its integrated Design and Build business, as it looks to strengthen operations across key enterprise and GCC markets in India. DESYN was launched as a strategic extension of Table Space’s workspace solutions portfolio to meet rising demand for agile, high-quality and rapidly deployable enterprise workspaces.Shruti Ookabhoy has joined DESYN as Executive Director and will lead the Design vertical, focusing on design capability, operational excellence and team development across markets. She brings over 22 years of experi..

Next Story
Infrastructure Transport

Concord Associate Bags Rs 2.79 Bn Kavach Order

Concord Control Systems said its associate company, Progota India, has received a Rs 2.79 bn domestic order from Indian Railways for the supply, installation, testing and commissioning of on-board Kavach 4.0 loco equipment.The order is scheduled for execution within 12 months and strengthens Concord’s role in India’s railway safety and signalling ecosystem. Kavach is India’s indigenous automatic train protection system, designed to improve operational safety by helping prevent signal passing at danger and reducing collision risks.Gaurav Lath, Joint Managing Director, Concord Control Syst..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->